Handling path for missing quota items: similar-process application -> compilation from similar-project data -> compilation from technical conditions -> approval/filing (including power and railway industry differences)
Missing quota items are handled in step-down order: (1) preferentially refer to quotas of similar construction processes (power first refers to similar power quotas, then cross-industry/local ones with matching fee standards); (2) with no similar sub-item but similar-project budget/settlement data available, compile the supplementary quota therefrom; (3) with no data, compile per the project's specific technical conditions; (4) submit the supplementary quota to the quota administration agency for approval before use; in railway, file a copy with the industry standard administration agency. Railway passenger station buildings, canopies, and overpasses may borrow the provincial local quota at the project location with matching fee standards. Unapproved supplementary quotas do not stand in settlement and audit.
Applicable Codes
- DL/T 5468-2013
- DL/T 5469-2013
- DL/T 5464-2013
- DL/T 5591-2021
- TB 10801-2024
Topic Positioning
The standard handling path for missing quota items (no applicable sub-item): the step-down order from reference application through supplementary compilation to approval/filing, and the procedural differences between the power and railway industries. Applicable when encountering missing quota items in compiling estimates/budgets, bid prices, and settlements.
Core Conclusions
Missing items are handled in step-down order: (1) preferentially reference quotas of similar construction processes — the power industry first refers to similar-process power quotas, failing which to similar-process quotas of other industries or localities (cross-industry borrowing must adopt the corresponding fee standards); (2) with no similar or referable sub-item, a supplementary quota may be compiled based on construction-drawing budgets or settlement data of similar projects; (3) with no data for reference, compile the supplementary quota per the project's specific technical conditions; (4) the supplementary quota must comply with current quota compilation administration regulations and be approved by the quota administration agency before use (verified at budget review). Railway industry differences: passenger station buildings, station complexes, canopies, and overpasses may adopt the provincial local quota at the project location, with labor/material/machinery prices and fee quotas adopted in a matching manner; other railway works — the investor organizes compilation of supplementary unit-price analyses per the construction process and files a copy with the industry standard administration agency — "filing a copy" is procedurally slightly lighter than power's "use after approval".
Applicable Boundaries
Applies where retrieval confirms no applicable sub-item exists; different from "adjusted application" for technical-condition differences — where technical conditions differ greatly, adjusted application per the quota provisions takes priority; missing items are the channel for supplementary compilation. When borrowing local/other-industry quotas, fees must match the borrowed quota system — mixed fees are a high-frequency audit issue; unapproved supplementary quotas do not stand in settlement and audit. The local quota borrowing permission is limited to railway station-building works and does not apply to non-station works.
Further Reading
Power: DL/T 5468-2013 Guidelines for compilation of construction-drawing budgets of power transmission and transformation projects, §4.1.4, §4.1.12; DL/T 5469-2013 Guidelines for investment estimates at feasibility study, §4.1.4; DL/T 5464-2013 Guidelines for preliminary design estimates of thermal power projects, §4.1.5; DL/T 5591-2021 Guidelines for construction budget compilation of 20 kV and below distribution network projects, §4.1.10 (finer tiers: power quota -> other industry/local -> budget/settlement data -> technical conditions). Railway: TB 10801-2024 Measures for compiling design estimates (budgets) of railway capital construction projects, §2.4 (2.4.1-2.4.3).
Keywords
- work items not covered by the quota manuals
- supplementary quota items
- 补充单价分析
- pricing by applying quota line items
- 定额管理机构
- 铁路工程定额
- 输变电工程
- 省级地方定额