Engineering Knowledge Cards.

pricing by applying quota line items

25 knowledge cards · sorted by most recently updated

Concept Guide

Concept

In the Chinese quota-based pricing system, pricing by applying quota line items is the central priced act when preparing the maximum price set for tendering, when bidding, or when reviewing a settlement. The estimator matches the described characteristics of a work section against the quota manuals, locates the corresponding quota line item, and applies its base price — labour cost plus material cost plus machine cost — either directly or after conversion. Quota line items rest on consumption quota (resource norm) standards issued by government or industry authorities and are used together with regional unit price tables. GB 50500-2013 and its successor GB/T 50500-2024 set out the bills-of-quantities valuation rules; the role of the quota norms is narrowing — under the 2013 regime they were the basis for preparing the tender price ceiling and for settlement review, but from the 2020 reform circular (建办标〔2020〕38号) and GB/T 50500-2024 (in force 1 September 2025) ceiling preparation shifts to comparable-project data and market price information, with quotas remaining a reference in settlement review and cost expert assessment during the transition.

Three situations arise. First, direct application: the work characteristics match the quota line item exactly and its base price is adopted as it stands. Second, conversion of quota items to suit conditions: the design conditions differ from the quota assumptions — for example a different mortar or concrete strength grade or mix — so material and machine consumption and unit prices are adjusted under the prescribed conversion rules before application. Third, work items not covered by the quota manuals: the estimator may borrow a neighbouring quota line item, prepare supplementary quota items (a one-off supplementary unit price schedule that does not change the quota system), or build up a price from market enquiries.

Institutionally, the quota supplies a uniform consumption yardstick and pricing benchmark, so that tendering, bidding and settlement produce comparable prices and fewer valuation disputes. The decision-makers are government, industry authorities and cost management institutions, and the pricing basis carries the character of an administrative normative document.

FIDIC Mapping

Aligned terms: 定额 = quota norms (prescribed resource consumption standards); 定额子目 = quota line item; 定额套用 = pricing by applying quota line items; 综合单价 = all-in unit rate; 定额换算 = conversion of quota items to suit conditions; 定额缺项 = work items not covered by the quota manuals; 补充定额 = supplementary quota items.

Relation: absent. The FIDIC Red Book and Yellow Book (2017) contain no equivalent pricing infrastructure — no state-issued resource consumption standard to be applied line item by line item. Under FIDIC the unit rates in the Bill of Quantities are formed competitively by the tenderer and reflect its own construction methods, resource procurement and risk assessment. Pricing by applying quota line items therefore has no nominal counterpart; only a functional analogy exists.

The mapping value lies in comparing two routes. The Chinese route for missing items: no quota line item exists, so a neighbouring item is borrowed, a supplementary item is prepared, or the price is built up from market enquiries. The FIDIC route: new work outside the Contract Price is priced by agreeing or determining new rates or prices; each new rate or price should be derived from relevant rates or prices specified in the Bill of Quantities or other Schedule, with reasonable adjustments for the applicable matters, and where no specified rates are relevant, from the reasonable Cost of executing the work plus the percentage for profit stated in the Contract Data. Variations and adjustments are instructed under Clause 13 [Variations and Adjustments], and the agreement or determination process is subject to the time limits of Sub-Clause 3.7.3.

Usage caution: a literal rendering of the Chinese term should not be presented as internationally standard usage. In international contracts the functional counterpart is change valuation through the agreement or determination of new rates, grounded in competitive pricing and the Engineer's discretion rather than in administrative quota references. Where the parties do adopt quota-based pricing in a contract, the edition of the quota and the accompanying unit price tables should be named expressly.

Chinese TermEnglish TermFIDIC TermRelationNotes
定额套用pricing by applying quota line itemsagreement or determination of new rates or pricesabsent中国侧由造价人员依定额手册按子目套价,缺项时借用相邻定额或编补充定额;FIDIC 无此计价基础设施,合同价外新增工作只能由工程师与承包商商定或由工程师确定新费率或价格,并受 Sub-Clause 3.7.3 时限约束。
综合单价all-in unit raterate or price specified in the Bill of Quantitiesadjacent两者在构成上相似(均含人工、材料、机械与相应费用及利润),但定价基础不同:FIDIC 清单费率由投标人竞争形成,反映其自身施工组织与风险判断;中国综合单价以政府发布的定额消耗量为组价依据。
定额换算conversion of quota items to suit conditionsreasonable adjustments to relevant rates or pricesadjacent定额换算是在行政性消耗量标准内部按既定规则机械重算材料、机械消耗量与单价;FIDIC 的调整是就变更事项对工程量清单既有费率作商业性合理调整,决策主体、依据与程序均不相同。

Updated 2026-09-13