Scenario split for applying quota line items to PE-ERT pipes under Beijing DB11/T 2382-2024: assignment between floor radiant heating pipes (C10-7-41 to 43) and plastic water supply pipes (C10-2 / C10-1 series), with a comparison against PP-R and PE-X

Under Beijing DB11/T 2382-2024, PE-ERT pipes are priced by use scenario. Floor radiant heating pipes take C10-7-41 to 43 (pipe OD within 16/20/25 mm, unit m, under the heating-appliances items); the stated work content already covers "pipes of polyethylene and similar materials", so the items apply directly without material conversion. For plastic water supply pipes (fusion jointed), indoor takes C10-2-77 to 87, buried / in-wall takes C10-2-89 to 92, and outdoor takes C10-1-43 to 52. The floor-heating and water-supply line item families must never be cross-applied (the table note states expressly that buried laying "is not applicable to floor heating"); PP-R and PE-ERT share the same tables and items (main material converted per the design type), while PE-X cannot be fusion jointed and must not directly take the fusion-connection items.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. C 通用安装工程(Table C.10.15-2、Table C.10.15-3、Table C.10.4-1、C10-7-41~43)

Topic Positioning

This card settles the quota-selection question for PE-ERT (heat-resistant polyethylene) piping under Beijing's Construction Works Consumption Quota Standard (DB11/T 2382-2024): separating, by use, the two line-item families of "laying of floor radiant heating pipes" and "plastic water supply pipes (fusion connection)", giving the specific item assignment, key consumption quantities and applicability boundaries, and comparing how PP-R and PE-X are alike and different in application, including the prohibited zones.

Core Conclusions

1. Floor radiant heating scenario (PE-ERT as heating pipe) - C10-7-41 to 43

Work content, original wording: "the work includes on-site handling, checking and cleaning of pipes, marking and setting out, pipe cutting, straightening, pipe layout, tying, fixing, hydraulic pressure testing and water flushing, and co-ordination with floor casting; the laying of floor radiant heating pipes applies to the laying of pipes of aluminium-plastic composite, polybutylene, polypropylene, polyethylene and similar materials." PE-ERT is a polyethylene-class pipe, sits within the covered materials, and takes the items directly without material conversion.

Consumption table (unit of measurement m):

Item code Pipe OD (mm, not exceeding) All-in labour Grade II (workdays) Floor radiant heating pipe (m) Floor-heating fixing clips (No.) Hacksaw blades (No.)
C10-7-41 16 0.0160 1.0200 2.6250 0.0024
C10-7-42 20 0.0160 1.0200 2.6250 0.0030
C10-7-43 25 0.0170 1.0200 2.5250 0.0037

Items shared by all three bands: plastic hose d25 0.0204 m/m, nylon abrasive disc d100 3.0000%, pressure-test pump 0.0002 machine-shift/m, other plant 3.0000%.

2. Water supply scenario (PE-ERT as water pipe, fusion jointed)

  • Indoor: table C.10.15-2 "plastic water supply pipes (fusion connection)", items C10-2-77 to 87 (DN15 to 150). Work content, original wording: "on-site handling, checking and cleaning of pipes, pipe cutting, pairing-up, preheating, fusion jointing, installation of pipes and fittings, pipe-clip fixing, hydraulic pressure testing, water flushing." Anchor: DN40 band C10-2-81 - all-in labour Grade II 0.1110 workday/m, plastic pipe 1.0200 m/m, plastic fittings 0.7990 No./m, plastic pipe clips 40 1.1692 No./m.
  • Buried / in-wall: table C.10.15-3 "buried laying of plastic water supply pipes (fusion connection)", items C10-2-89 to 92 (DN15 to 32). Table note, original wording: "buried laying of plastic water supply pipes applies to water supply and heating pipes laid in the ground or within walls, and does not apply to floor heating; the laying of floor heating pipes shall follow the corresponding items under heating appliances"; a further note: "buried laying of plastic water supply pipes includes the process of threading corrugated plastic sleeves, whose material quantity shall be computed separately; where laid in floor trenches this item still applies, but grooves left open and insulation backfilling shall be computed separately." Anchor: DN25 band C10-2-91 - all-in labour 0.0690 workday/m, plastic pipe 1.0200 m/m, Omega-type plastic pipe clip 32 1.1025 No./m.
  • Outdoor: table C.10.4-1 "outdoor plastic water supply pipes (fusion connection)", items C10-1-43 to 52. Anchor: DN40 band C10-1-45 - all-in labour 0.0530 workday/m, plastic pipe 1.0150 m/m, plastic fittings 0.2860 No./m.

3. PP-R / PE-X comparison

  • PP-R: same tables and same items as PE-ERT. The water supply item is named "plastic water supply pipe" and its main-material column is the generic "plastic pipe / plastic fittings"; items are not subdivided by base material, and the main material is entered and converted at the selected design price. The floor-heating item's work content expressly covers "polypropylene pipes".
  • PE-X (cross-linked polyethylene): once cross-linked it cannot take socket-fusion joints (the norm is compression / slip-on mechanical connection), so it must not directly take the "fusion connection" items; no water supply item named for PE-X appears, so application must be checked against the actual jointing method, or converted or supplemented. In floor-heating scenarios it takes C10-7-41 to 43 under the "polyethylene and similar materials" wording.
  • Aluminium-plastic composite pipes and PB (polybutylene) pipes are likewise covered by C10-7-41 to 43 in floor-heating scenarios.

4. Application points

  1. Floor heating and water supply are mutually exclusive: floor-heating pipe laying must follow the corresponding heating-appliances items (C10-7-41 to 43) and must not take water supply / buried plastic pipe items; conversely, water supply pipes must not take floor-heating items.
  2. The work content of both families already includes hydraulic pressure testing and water flushing, so testing / flushing must not be itemised separately; the floor-heating items already include tying and fixing of the clips and "co-ordination with floor casting".
  3. The main material is not locked to a base material ("floor radiant heating pipe" / "plastic pipe"); in independent rate build-up it is entered and converted at the actually selected PE-ERT price.
  4. Different banding bases: floor heating C10-7 bands by pipe OD (within 16/20/25 mm); water supply C10-2 / C10-1 bands by nominal diameter DN.

Applicability Boundaries

  • Applies to plastic-pipe item selection under Beijing DB11/T 2382-2024 (Annex C, general building services works); other regions or editions must be checked against the local current quota.
  • Data-registration caution: in the electronic data C10-7-41 to 43 have "Table C.10.59 unit-heater installation" registered as their owning table, which conflicts with their work content (laying of floor radiant heating pipes) and is suspected to be a registration misalignment; when applying, verify by item code plus work content.
  • Not settled: the item assignment of mechanically jointed pipes such as PE-X (check against the actual jointing method or supplement), the itemising of system components such as manifolds and valves, and rates and on-costs.
  • This card contains no monetary amounts.

Further Reading

  • DB11/T 2382-2024 Construction Works Consumption Quota Standard, Annex C general building services works:
    • Table C.10.15-2 plastic water supply pipes (fusion connection): C10-2-77 to 87;
    • Table C.10.15-3 buried laying of plastic water supply pipes (fusion connection): C10-2-89 to 92;
    • Table C.10.4-1 outdoor plastic water supply pipes (fusion connection): C10-1-43 to 52;
    • Laying of floor radiant heating pipes: C10-7-41 to 43 (corresponding heating-appliances items; the electronic data marks the owning table as "Table C.10.59 unit-heater installation" - verify before use).
  • Cross-checks: the buried-laying table notes on threading corrugated plastic sleeves and on trench grooves and insulation backfill being computed separately; the boundaries of hydraulic pressure testing and water flushing in each item's work content.