Beijing DB11/T 2382-2024 fire-protection works consumption scope: unit self-commissioning included, no independent system-commissioning sub-items, boundary divisions, and cross-discipline borrowing rules
Beijing DB11/T 2382-2024 "Construction Works Consumption Standards" Chapter 6.9: fire works are itemized in five classes — water extinguishing, gas extinguishing, foam extinguishing, automatic fire alarm, and intelligent emergency lighting/evacuation indication; indoor/outdoor fire piping is bounded at 1.50 m from the building's outer wall face; the installation sub-items of automatic fire alarm (6.9.43) and intelligent emergency lighting/evacuation indication (6.9.51) already include "self-commissioning of the equipment itself" — not counted again; the standard contains no independent "fire system commissioning" sub-item, so where a tender bill of quantities carries a system commissioning item coded 030909 per GB/T 50856-2024 it must be priced by applying the quota scope agreed in the contract or supplementary sub-items issued by the cost authority.
Applicable Codes
- DB11/T 2382-2024 建设工程施工消耗量标准 第6.9章 消防工程
- GB/T 50856-2024 通用安装工程工程量计算标准 App. J Table J.9.1、J.11.9
Topic Positioning
The key scope points of Chapter 6.9 "Fire protection works" of Beijing's DB11/T 2382-2024 "Construction Works Consumption Standards": division of fire systems and the indoor/outdoor boundary line, cost attribution of the "self-commissioning of the equipment itself" already included in installation sub-items, cross-discipline borrowing boundaries, and the pricing path for fire system commissioning (GB/T 50856-2024 code 030909) under the Beijing quota system.
Core Conclusions
- System and boundary division: fire works shall be itemized by water extinguishing system, gas extinguishing system, foam extinguishing system, automatic fire alarm system, and intelligent emergency lighting and evacuation indication system (6.9.1); indoor/outdoor fire piping is bounded at 1.50 m from the building's outer wall face (6.9.2).
- Key commissioning cost scope: the installation consumption of the automatic fire alarm system (6.9.43) and the intelligent emergency lighting and evacuation indication system (6.9.51) already includes the work content of "self-commissioning of the equipment itself" — stand-alone/unit commissioning is not counted again; the Beijing 2024/2021 installation quota manuals provide no independent "fire system commissioning" sub-item, so where a tender bill of quantities carries a 030909 system commissioning item, it must be priced by applying the quota scope agreed in the contract or supplementary sub-items issued by the cost authority.
- Cross-discipline borrowing boundaries (6.9.3-6.9.9): fire pumps and pressure-stabilizing pumps are installed per mechanical equipment installation works; welded stainless steel (copper) pipe and fittings per industrial piping works; valves, pressure tanks, fire water tanks, sleeves, support fabrication and erection, buried outdoor piping, press-fit stainless steel (copper) pipe and fittings, chlorinated polyvinyl chloride (PVC-C) pipe and fittings, and welded hydrant piping per water supply, drainage, heating and gas works; painting, anticorrosion and insulation per the corresponding works; cable laying, cable tray installation, conduit and wiring, junction boxes, motor connection and wiring check, lightning protection and grounding devices, and chasing and holing per electrical equipment installation works; instrumentation and the wiring and circuit checking of electric-signal valves, pressure switches, driving devices and leak-alarm switches per automatic control instrumentation installation works; pipe trench and pit earthwork, backfill, bedding, foundations, masonry, and concrete pipe supports per building and decoration works and structure works.
- Water extinguishing measurement: pipe installation is measured by the design centerline length of the pipe, without deducting the length occupied by valves, fittings and various components (6.9.13); galvanized steel pipe (threaded connection) consumption includes the fitting installation work content, with fitting material quantities taken per design quantities or per the reference table in Table 6.9.14 (pieces/m); steel pipe (grooved connection) includes grooved direct coupling installation, while grooved fittings such as elbows, tees and crosses are listed separately by specification and measured per design quantities, each grooved fitting set including the clamp and gasket (6.9.16); alarm devices, indoor/outdoor hydrants and fire department connections are treated as complete sets (Table 6.9.23 — e.g., the wet alarm device set includes wet valve, supply and device pressure gauges, test valve, drain test valve, test-pipe flowmeter, strainer, retard chamber, water motor gong, alarm stop valve, funnel, pressure switch).
- Gas extinguishing: consumption for the installation of seamless steel pipe, steel fittings, selector valves etc. is compiled for heptafluoropropane and IG541 extinguishing systems; for high-pressure CO2 extinguishing systems, labour and machinery consumption should be multiplied by a factor of 1.20 (6.9.30); storage device installation consumption includes the support frames for fixing the agent storage containers and drive bottles, system components (headers, container valves, gas and liquid check valves, high-pressure hoses), and the installation of storage and drive devices such as safety valves, nitrogen pressurization, and system component testing (6.9.29).
- Height-related inefficiency: where the installation height of equipment or material exceeds 6 m, the labour inefficiency caused by work at height follows clause 6.1.2 of this standard (6.9.10).
Applicable Boundaries
- Applies to projects in Beijing priced under DB11/T 2382-2024; other regions follow the quota scope currently in force locally.
- "Self-commissioning included" refers only to the installation sub-items of the automatic fire alarm system and the intelligent emergency lighting and evacuation indication system; the interlocked commissioning (030909) of water, gas and foam extinguishing systems remains an independent bill item and must be priced by applying the commissioning sub-items under the contract's quota system.
- Where the Beijing quota manuals have no independent commissioning sub-item, commissioning sub-items of other disciplines must not be substituted at will; bill points (measured per GB/T 50856-2024 Appendix J, J.11.9) and quota point steps are two different scopes and cannot be used interchangeably.
- Stand-alone commissioning is already included in the equipment installation work content (GB/T 50856-2024 clause 3.0.11) and is not counted again; the cost of joint test-run under load belongs to project costs other than the works (= expenditure − income) and is not merged into the cost of works (construction and installation).
Further Reading
DB11/T 2382-2024 "Construction Works Consumption Standards" Chapter 6.9 fire protection works full text (6.9.1-6.9.53: I General provisions 6.9.1-6.9.11, II Water extinguishing systems 6.9.12-6.9.24, III Gas extinguishing systems 6.9.25-6.9.37, IV Foam extinguishing systems 6.9.38-6.9.41, V Automatic fire alarm systems 6.9.42-6.9.49, VI Intelligent emergency lighting and evacuation indication systems 6.9.50-6.9.53, incl. Table 6.9.14 reference table of fittings for galvanized steel pipe (threaded connection) and Table 6.9.23 complete-set products); companion GB/T 50856-2024 Appendix J Table J.9.1 (code 030909) and the notes on J.11.9; cost boundaries between stand-alone and system interlocked commissioning also in GB/T 50856-2024 clause 3.0.11 and GB 50261-2017 clause 7.2.1.
Keywords
- 消防工程
- fire protection system commissioning
- DB11/T 2382
- 北京消耗量标准
- 本体调试
- 界限划分
- 030909
- 火灾自动报警
Related Cards
- →
Calculating fire-protection system commissioning fees: BOQ listing, measurement units, and point-count rules (GB/T 50856-2024 Appendix J, code 030909)
Fire-protection system commissioning fees are listed separately in the BOQ (GB/T 50856-2024 code 030909), not charged as a percentage of the works cost, but measured by system/point/count with commissioning items: water extinguishing control devices by points from flow indicators/hydrant pump-start buttons/monitor counts, gas extinguishing by cylinder-valve count as points, automatic alarm and other systems by device counts as points and measured by "system", fire barrier control devices by count (valves) or unit (fire lifts); when applying quotas, price by the point-tier steps of the chosen quota — local standards differ in caliber.
- →
The difference between single-equipment commissioning and system joint commissioning in equipment installation: concepts, sequence, and cost attribution
Single-equipment commissioning covers the action functions and performance parameters of a single machine, already included in the equipment installation work content (GB/T 50856-2024 Clause 3.0.11), not charged separately; system joint commissioning covers the overall system functions and interlocking logic, with fire system commissioning listed as an independent BOQ item under Appendix J code 030909; loaded joint test running belongs to the other costs of project construction (joint test-run cost = expenditure − income), excluding single-machine and no-load linkage test-run costs. Sequence: single machine → sub-system → no-load linkage → loaded joint running — the order cannot be inverted.
Cited By
- ←
Pricing boundary of fire sprinkler system commissioning: equipment installation already includes commissioning of the equipment itself and single-machine trial runs (the negative conclusion, not separately payable), while system interlock commissioning is separately itemised under code 030909 with its point-counting rules, and water extinguishing commissioning and fire alarm commissioning are itemised separately
GB/T 50856-2024 Clause 3.0.11: 'the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs' - single-machine trial runs and commissioning of the unit may never be charged outside the equipment installation items; only interlocking across equipment and across systems is listed separately under Annex J Table J.9.1 fire protection system commissioning (code 030909): water extinguishing control devices counted in points (branches) by the number of water flow indicators (sprinkler systems), hydrant pump-start buttons and fire monitors; automatic alarm and the other systems take their points from the device and component counts and are measured as 'systems'; gaseous extinguishing counts points by the cylinder head valves; fire barrier control devices by the piece and fire lifts by the lift; water extinguishing commissioning and fire alarm commissioning must be itemised separately.
- ←
BOQ measurement of system commissioning versus single-machine trial runs: heating and air-conditioning water system commissioning (code 031008) and ventilation works inspection, commissioning and testing (code 030704) listed 'by system', while equipment installation items already include commissioning of the unit and single-machine trial runs and are not separately payable
GB/T 50856-2024 Clause 3.0.11 provides that the equipment installation work content of this standard includes commissioning of the equipment itself and single-machine trial runs - single-machine trial runs may therefore not be listed as a separate BOQ item nor priced under a separate commissioning quota item; what is listed separately and measured 'by system' is the system (interlock) commissioning group of BOQ items: heating and air-conditioning water system commissioning per Table K.8.1 (code 031008), ventilation works inspection, commissioning and testing per Table G.4.1 (code 030704), and fire protection system commissioning under Annex J code 030909.
- ←
Preventing double counting of pipes and fittings in fire water extinguishing systems: length by centreline without deducting fittings, threaded fittings absorbed into the pipe quota line items, grooved fittings counted separately per 'set' (with clamp duplication checks and size-band omission checks)
Fire piping has a single layer of length measurement: by the pipe centreline length shown on the design drawings, without deducting valves, fittings and components (DB11/T 2382-2024 clause 6.9.13; Beijing 2021 volume 10 chapter 2 measurement rules: 'pipes are measured by length along the centreline shown on the drawings, without deducting fittings, valves and attachments; fitting installation is measured by the quantities shown'). Fittings split into two bases: for galvanized steel pipe (threaded), the pipe consumption already includes fitting installation, and fitting material quantities follow the drawn quantities or table 6.9.14 contents (pieces/m: DN25 total 0.590, DN50 0.808, DN100 0.520) - threaded fitting installation or main material must not be listed again; for steel pipe (grooved), the pipe item covers only the grooved straight coupling, and grooved elbows, tees and crosses are separate fitting installation items counted per 'set' by drawn quantity, each set including the clamp and seal ring (clause 6.9.16, matching the two item sets of volume 9 fire works, 'fitting installation (grooved coupling)' and 'fitting installation (cut-in connection)', e.g. DN100 grooved 9-1-35, cut-in 9-1-25). The only source of duplication is listing the 'clamp' three times: the sensible clamp ceiling = pipe length x grooved-coupling content of the pipe item (about 0.1667 set/m) + fitting count x grooved-coupling content of the fitting item (1.005 set/set); for DN100, 100m and 20 fittings that is 16.67 + 20.1 = 36.77 sets - a markedly higher figure signals duplication.
- ←
Commissioning of power supply and distribution apparatus systems - unit of measurement and the rules for splitting the number of 'systems': division per the electrical schematic diagram, systems counted by qualifying circuit breakers (rated tripping current no less than 100 A, etc.), circuits from distribution boards direct to motors counting only motor commissioning, and cable tests and insulation withstand already included
Commissioning of power supply and distribution apparatus systems is measured in 'systems' (GB/T 50856-2024 Table D.16.1 electrical testing and commissioning, code 030416, quantities per the design drawings), the systems being divided on the electrical schematic diagram; the items up to 10 kV apply to low-voltage supply circuits from distribution apparatus to sub-distribution boards, the quantity being the number of circuit breakers in the works meeting all of: rated tripping current no less than 100 A; not a breaker on the HV or LV side of a transformer or inside a motor control board or cabinet; not a breaker serving only maintenance isolation with no protective role in the design - and each unit works counts at least one circuit; circuits from a distribution board direct to a motor count only motor commissioning; cable tests and insulation withstand are already inside system commissioning and are not counted again.
- ←
Split quota pricing of motorised two-way control valves (temperature-control valves) on chilled-water systems: valve-body item plus electric-actuator item (plus a wiring item) as three charges, versus the single all-in item for ordinary globe and gate valves, and the criteria for charging wiring
A motorised two-way control valve is not covered by one valve line item but split into three charges: the valve body takes a valve-installation line item by connection form and size (DB11/T 2382-2024: threaded valve DN20 is C10-5-2, all-in labour category II 0.060 workdays per valve; welded-flange valve DN50 is C10-5-35, 0.295 workdays per valve); the electric actuator takes the building-equipment-monitoring 'motorised two-way control valve' item (C5-3-59 up to DN50, 0.522 workdays per valve; C5-3-63 up to DN100, 1.017 workdays per valve, the work content already including actuator installation, wiring and testing); wiring is charged separately or not depending on which volume applies (electrical volume C4-4-156 'valve wiring', 0.126 workdays per valve; instrumentation volume C6-2-45/C6-2-46 'valve check-out and wiring', 0.290/0.336 workdays per unit, only for control valves already installed on industrial pipework). Ordinary globe and gate valves are covered by one line item whose work content already includes pipe cutting, beveling, flange gasket fabrication and installation, valve and flange installation and pressure-test-pump machine-shifts.
- ←
Pricing and member-wise itemisation of stone balustrades (granite balustrades): the basis test, the post / panel / sill items and their measurement rules
Stone balustrades route by works basis first: landscape / scenic and antique-style balustrades (posts + panels + continuous sill as grouped stonework) take Beijing 2024 antique volume B.2 stonework (B-2-15 to B-2-19) or landscape volume E.3.3-10 / 11; modern stone panels of stairs, corridors and outdoor platforms take building volume A.15.3-7. Member-wise measurement: sill stones by length m (landscape) or volume m3 (antique); posts by size per piece; Xunzhang and Luohan panels by drawn height x base length in m2; drum-end stones by base length x mean height in m2. BOQ itemisation per GB/T 50855-2024 Table B.2.1 (code 020202) or GB/T 50854-2024 Table Q.3.1 (code 011503).
- ←
Splitting the laying mode of fire low-current conduit (fire PA, fire telephone and fire door monitoring circuits of automatic fire alarm systems): by exposed / concealed wiring, not by the structural-embedding / decorative-stage construction phase - with the material constraints, measurement and quota item bases
The wire conduit of fire PA, fire telephone and fire door monitoring circuits is banded in pricing by the design laying mode, not by construction stage - quota items offer only exposed / concealed (including within suspended ceilings) bands; embedded-with-structure corresponds to concealed and decorative-stage exposed runs to exposed. Concealed means the conduit runs inside the structural layer of walls, floors, slabs or columns, enclosed by non-combustible structure with cover at least 30 mm (GB 50116-2013 Article 11.2.3 preferably not under 30 mm; GB 50166-2019 Article 3.2.2 not under 30 mm); exposed means on wall / ceiling surfaces, within ceilings or on supports with the pipe visible. Material constraints: concealed may use metal conduit, flexible (metal) electrical conduit or rigid plastic conduit of class B1 or better; exposed only metal conduit, flexible (metal) electrical conduit or closed metal trunking (no plastic) - so exposed runs take the metal-conduit exposed items. Measurement per GB/T 50856-2024 Appendix D Table D.12.1 (code 030412): conduit by drawn length in m, boxes per piece, chases under Appendix N.
- ←
Routing monitoring / signal poles and their concrete foundations to quota disciplines: poles to general installation or municipal works, foundations always charged separately under building civil works
The discipline routing of monitoring / signal poles turns on whether the road sits within municipal jurisdiction: poles (monitoring poles, street lights) along plant and residential-estate roads follow general installation works electrical equipment installation (GB/T 50856-2024 Appendix D); only city-road lighting systems / municipal traffic facilities follow GB/T 50857 municipal itemisation. The concrete foundations of poles and equipment (including foundation earthworks and anchor-bolt embedment) are excluded by every installation item and follow the building and decoration (or structures) works items, with secondary grouting under machinery installation.
- ←
Discipline attribution and quota application of split boxes (splitters): telecom cable split boxes, outdoor cable split boxes and CATV splitters / taps must not borrow items across volumes
The split box / splitter is not one single item: attribute by discipline first, never borrowing across volumes - telecom cable split boxes under railway TB/T 10826-2024 Volume 5 Telecommunications Works TY-256 to 259 (by G0D12 / G0D24 / G0D36 / G0D48 types, unit per piece); outdoor cable split boxes under Beijing DB11/T 2382-2024 Table G.3.27 (split by internal / external wall and pair-count bands, e.g. G3-5-27 internal wall up to 30 pairs, G3-5-29 external wall up to 100 pairs, unit per piece); CATV splitters / taps belong to intelligent building weak-current works, under Table C.5.59 line equipment C5-4-95 (subscriber taps and splitters up to 8 ways, unit per piece).
- ←
Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)
Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.
- ←
Luminaire classes and listing notes for the lighting installation bill (code 030413) of GB/T 50856-2024
Per GB/T 50856-2024 Annex D table D.13.1 (lighting installation, code 030413) notes: luminaires divide into ordinary lamps, decorative lamps, factory lamps, high-point (obstruction) lamps, medical lamps, neon, campus street lamps, landscape lamps and lighting switches; neon covers tubes, strips, transformers, controllers, relays, timers and control boxes - all components; mid-mast lamps mount on poles 19 m high or less, high-mast lamps on poles over 19 m; where measured in "m" the item description shall state the lamp width, in "m2" the lamp size.
- ←
Splitting rules for applying consumption items to framed partitions: framing and boards set apart, infills charged separately as insulation, double-faced boards doubled, fire rating never a selection basis (Beijing DB11/T 2382-2024 chapter 4.13 and Annex A.12)
Applying consumption items to fire rock-wool board partitions turns on the build-up and board type, never the fire rating (no "fire partition" subject exists; fire endurance is a design requirement): framed partitions itemise framing and boards separately per DB11/T 2382-2024 clause 4.13.16 item 2; rock-wool and like infills sit outside the partition items per 4.13.20 and execute under 4.11.1 to 4.11.10 (insulation); boards are determined per face, doubled where two-faced, per 4.13.16 item 3; partition quantities per 4.13.27 compute on the frame envelope area without deducting single holes of 0.30 m2 or less.
- ←
Quota line-item application for pneumatic ON/OFF valves (gate/ball valves) under the consumption standard: no separate line item by actuation mode - valve body installation under the piping chapters, checking and wiring under the automatic control instrumentation / electrical chapters, complete-set actuators not split off (DB11/T 2382-2024)
Pneumatic ON/OFF valves (gate/ball valves) are priced as two separate entries: (1) valve body installation applies the valve installation line items of the piping chapter the valve belongs to - industrial pipeline works set items "according to influencing factors such as valve type and size" (6.8.48; likewise medium- and high-pressure), while water supply and drainage, heating and gas works set items "according to influencing factors such as valve type, connection form and size" (6.10.47); the actuation mode (pneumatic/electric) does not create separate line items; (2) checking and wiring follows the corresponding "valve checking and wiring" items of the automatic control instrumentation works (6.6.20 item 1, for regulating valves already installed on the pipelines, such as butterfly valves, on/off valves and shut-off valves), while checking and wiring of electrically actuated valves follows the corresponding items of the electrical equipment installation works (6.8.51). Quantities of electrically and pneumatically actuated regulating valves are measured as complete-set installation and commissioning, including the actuator and the valve, the handwheel and the supplied complete-set accessories, and must not be split off and counted separately (6.6.21).
- ←
Quantity calculation and consumption-standard sub-item application for grooved-connection fittings of sprinkler pipes (mechanical tees, grooved fittings, couplings/clamps) - mainly Beijing DB11/T 2382-2024
Sprinkler pipes are calculated by the centre-line length shown on the design, without deducting the lengths of fittings and components; mechanical tees/crosses (hole-cut type) apply the "steel pipe (grooved connection) hole-cut fittings" sub-items, finished elbows/tees/crosses apply the "steel pipe (grooved connection) grooved fittings" sub-items - both measured per "set" by the design quantities, each set including the clamp and gasket (material content 1.0050 set/set); couplings are not itemized separately - butt joints of straight pipes are included in the pipe sub-items (grooved coupling 0.1667 set/m, about one per 6 m), and couplings at fittings are included in the fitting sub-items. GB 50261-2017 Clause 5.1.11: mains (risers) and horizontal pipes shall not be connected by mechanical tees; the hole spacing of mechanical tees shall not be less than 500 mm and of mechanical crosses not less than 1000 mm.
- ←
Beijing DB11/T 2382-2024 consumption standard: quota-application method for water-tank (assembled / integral) installation - capacity banding, measurement per unit, and the treatment of accessories and peripheral works
Water-tank installation quantities shall be classified by total tank capacity and calculated by the numbers shown on the design (Clause 6.10.88), measured per "unit"; site panel assembly applies Table C.10.72-2 assembled-tank installation (work content includes panel assembly and water testing), and factory-finished whole tanks delivered to site apply Table C.10.72-1 integral-tank installation (including fitting-up of parts and the full-water test). Accessories supplied complete with the tank are included in the sub-item work content and not itemized separately; the tank body is priced as an unpriced main material/equipment; steel-section supports are executed under equipment-support fabrication and installation per Clause 6.10.41 (classified by support-group weight, calculated by the design mass in kg); control cabinets (panels) follow the electrical volume, and vibration-isolation devices follow the machinery volume.
- ←
Beijing DB11/T 2382-2024 consumption standard: pricing application of the water-tightness test and ball-passing test of drainage pipelines (water-tightness test included in the pipe-laying sub-items, ball-passing test handled by coefficient adjustment on the indoor pipe-installation sub-item - neither itemized separately)
Under Beijing DB11/T 2382-2024 neither test is applied under a separate sub-item: the water-tightness test is already included in the consumptions of "drainage pipeline laying" (7.4.26 - no separate sub-item, no separate BOQ item); the ball-passing test is handled by coefficient adjustment on the indoor drainage pipe installation sub-item (labor x 1.10, other-materials fee ratio +1.00%, other-tools fee ratio +0.05%, 6.10.30, triggered only when required by the design or the code); indoor pipe hydrostatic testing and water flushing are included in the installation consumptions (6.10.25), and the work content of drainage plastic-pipe sub-items additionally includes the water-filling test (e.g. C10-2-104).
- ←
Applying quotas to copper wire in conduit: distinguishing "lighting" vs "power" wire-pulling sub-items (<=4 mm2 classified by use; Beijing 2024 C4-11-284/C4-11-288 compared)
Conduit wire-pulling sub-items are classified by use, not cross-section alone: wires <= 4 mm2 for lighting and similar uses (including ordinary 220 V socket circuits) take lighting sub-items; power uses or lighting circuits > 4 mm2 take power sub-items. 4 mm2 is the overlap tier between Beijing 2024's lighting table (C4-11-284) and power table (C4-11-288) — attribution follows use; Shenzhen SJG 181.7-2024 Clause 6.1.2 states expressly: lighting-circuit conductors >= 6 mm2 execute the corresponding power-circuit wire-pulling sub-items.
- ←
Pricing pavement removal: selection criteria between milling and demolition sub-items, with corresponding Beijing DB11/T 2382-2024 Appendix D municipal sub-items and consumptions
Pavement removal is not a binary choice but split by construction essence: asphalt course shaving (maintenance/overlay, milling machine, milled material loaded and recycled) applies milling sub-items; wholesale pavement excavation (structure abolition, pipeline trenching) applies demolition sub-items; full-depth cement-concrete removal can only apply demolition (the milling group has only a "texturing within 1 cm" tier); pre-overlay surface texturing applies milling - texturing. Criteria: material, depth, and the approved method-statement process — all three indispensable. Beijing 2024: milling group D1-6-14-19 (100 m2), demolition group D1-6-1-6, 8-9, 10-11, 26-29 (pneumatic-pick type per 10 m2, mechanical per 100 m2); milling work content already includes loading (do not double-count loading), demolition only "piling old material" without loading/haul — count separately; demolition of pavement/base courses is computed by area.
- ←
Beijing DB11/T 2382-2024: determining chapter by chapter and material by material whether pipe installation quota line items include pipe fittings (gas piping: only galvanized steel pipe with threaded joints includes fittings; indoor water supply/drainage and heating piping include fittings)
Beijing DB11/T 2382-2024: in gas piping, only the galvanized steel pipe (threaded joints) installation items include fittings and pipe clamps (6.10.34); for welded steel pipe, PE pipe and other materials, the fittings must additionally follow the "fitting and pipe-clamp installation" items; the indoor water supply, drainage and heating piping runs the opposite way - the pipe installation items include the fitting installation content, the fitting materials being taken as the design-shown quantities or per Table 6.10.32 (6.10.32). Pipes are measured along the design-shown centreline length without deducting the lengths occupied by fittings, valves and accessories (6.10.36); fittings are measured as the design-shown number of pieces (6.10.37).
- ←
Quantity take-off for curb backrests (concrete support behind curbs) and pricing by applying quota line items under Beijing DB11/T 2382-2024 (sub-items D2-3-44, D2-5-1, E-3-75)
Curb backrests (back-support concrete) are measured separately in m3 per the design dimensions (section area x length), listed apart from curb setting (measured in m); under Beijing DB11/T 2382-2024 municipal works apply D2-3-44 concrete support behind curbs (per m3: composite labor class II 0.9480 workdays, ready-mixed pea-gravel concrete C20 1.0100 m3, 4 t water truck 0.0615 shifts); landscape projects apply E-3-75 (identical consumptions), with formwork under D2-5-1 formwork curb (m2); note D2-3-43 "cast-in-place concrete curb" (C30) is the curb-body sub-item, not the backrest.
- ←
Septic tank pricing by applying quota line items (Beijing DB11/T 2382-2024 structures works): line-item selection along the three construction routes of cast-in-place concrete / masonry / GRP factory-made tanks, work content already included, and measurement adjustment rules
Under the Beijing DB11/T 2382-2024 system a septic tank belongs to the structures works and is priced by a composite line item per tank ("zuo"): cast-in-place concrete tanks use Table F.1.5-2.4 (F-1-57 to F-1-79, selecting size number / effective volume / with or without groundwater / H+h earth cover), masonry tanks use Table F.2.3-2.1 (F-2-10 to F-2-23), and GRP factory-made tanks use F.3.2 (from F-3-107, further selecting trafficable / non-trafficable); the items already include earthworks, rebar, waterproofing and covers (factory-made tanks also include the riser and vent pipe) and must not be double counted; formwork is billed separately under the preliminary (measures) items; where the riser height differs from the standard atlas, adjust by the number of risers using the "riser, for each 0.10 m increase or decrease" items; integral precast concrete tanks delivered and installed on site are work items not covered by the quota manuals and are handled through supplementary quota items.
- ←
Measurement rules for the matching flanges of flanged valves: in water supply/drainage, heating and gas works the flanges are not applied separately, while in industrial-pipeline works the valve and its matching flanges are calculated separately (DB11/T 2382-2024)
Per the Beijing local standard DB11/T 2382-2024 "Construction Consumption Standard", general installation works: in water-supply-and-drainage, heating and gas works, the flanged-valve installation sub-items are compiled on the basis of flange connections on both sides - the matching flanges and bolts are included in the valve installation sub-items and flange installation sub-items are not applied separately (where only one side is flanged, the flange and bolt quantities are halved, a consumption adjustment); in industrial-pipeline works "the installation of all flanged valves and the installation of the matching flanges shall have their quantities calculated separately" (6.8.54) - the valve sub-item does not include installation of the flange body (only the installation of one gasket and one set of flange bolts, with bolt materials charged separately), and the matching flanges must be applied under separate flange-installation sub-items; the same basis applies to medium- and high-pressure valves (6.10.52, 6.8.73 to 6.8.79).
- ←
Beijing 2024 consumption standard (DB11/T 2382-2024) waterproof mortar: sub-item selection cross-referenced by position and method - roof A-9-83/84/85/89, walls A-9-166/167, floors A-9-209
Under Appendix A.9 of the Beijing 2024 "Construction Consumption Standard" (DB11/T 2382-2024), waterproof mortar has independent sub-items set by "position + method" and they must not be applied across positions: within the roof rigid-waterproofing table, A-9-84 (with waterproofing agent), A-9-83 (SF polymer), A-9-85 (cementitious capillary crystalline), A-9-89 (waterproof concrete); walls A-9-166 (dry-mixed rendering mortar DP M10 + waterproofing agent), A-9-167 (SF polymer); floors A-9-209 (with waterproofing agent). All are measured in m2; the corresponding 2021-edition numbers are 9-84/9-83/9-85/9-89, 9-166/9-167 and 9-209 (the 2024 edition adds the "A-" prefix in one-to-one correspondence).
- ←
Beijing DB11/T 2382-2024 quota application for cooling-tower installation: Table C.7.11 banded by treated water flow, the applicability basis for closed-circuit towers and the multi-motor coefficient
Cooling-tower (including closed-circuit tower) installation applies "Table C.7.11 cooling-tower installation" of the general installation works of Beijing DB11/T 2382-2024 "Construction Consumption Standard", banded by the tower's own cooling-water flow (treated flow) and measured per "unit" (C7-1-166 is the within-100 m3/h band, C7-1-171 the within-700 m3/h band); Clause 6.7.23 provides that quantities are calculated by the numbers shown on the design; where one tower is fitted with multiple motors, the corresponding item is executed by the total cooling-water flow with the labor and tool consumptions multiplied by 1.1; the work content excludes on-site assembly, and anchor bolts are considered supplied with the equipment.
- ←
Quota sub-item application and BOQ itemizing basis for special switch panels (sound-light control / key-switch / sensor / residual-current protection) (Beijing DB11/T 2382-2024 sub-items + GB/T 50856-2024 BOQ rules)
The Beijing 2024 consumption standard sets dedicated sub-items for special switch panels (no need to borrow): sound-light control (time-delay energy-saving) applies C4-4-113 time-delay energy-saving concealed switch (0.052 work-days/unit); key-operated switch applies C4-4-115 (0.061 work-days/unit); sensor panels apply C4-4-117 (0.085 work-days/set); rail-mounted residual-current protective switches apply C4-4-48/49 "single-phase" and C4-4-50 "with fuse" (0.05/0.226/0.535 work-days/unit); main materials enter at actual prices. BOQ itemizing per GB/T 50856-2024: sound-light-control types fall under "lighting switches" (Table D.13.1 note 9), residual-current switches under "low-voltage electrical switches / residual-current protective switches" (Table D.5.1 note 1), smart-home panels under Table E.7.1 (code 030507).
- ←
Pricing rules for fan-coil-unit installation: the installation sub-item measured per "unit" by installation type, the unit body listed separately as an unpriced main material, and supports distinguished between supplied with the equipment (included) and fabricated on site (applying equipment-support fabrication and installation banded by each support's weight) - per Beijing DB11/T 2382-2024 Section 6.7, with a railway TB/T 10831-2024 quota comparison
FCU pricing splits into three blocks: (1) installation applies the corresponding "ventilation and air-conditioning works - fan coil installation" item, classified by installation type and counted by the design quantities per "unit" (DB11/T 2382-2024 Clause 6.7.11); (2) the equipment body is an unpriced main material listed separately at compilation-period prices, shown in brackets and excluded from the other-materials fee base (Clause 6.7.3); (3) supports are judged first by supply mode: supports/underlay supplied with the equipment are included in the equipment-installation consumptions and not re-applied (Clause 6.7.5), while site-fabricated supports apply "equipment-support fabrication and installation", classified by each support's weight and calculated by the design mass (Clause 6.7.24). Railway TB/T 10831-2024 comparison: FCU exposed FY-2670 (RMB 69.13/unit), concealed FY-2671 (RMB 172.46/unit); equipment supports FY-2675 (<= 50 kg, RMB 907.54/100 kg), FY-2676 (> 50 kg, RMB 624.47/100 kg).
- ←
Point-count listing and simulated-discharge test requirements for gas extinguishing system commissioning (030909)
Gas extinguishing system commissioning is a separate bill item (GB/T 50856-2024 code 030909), counted in "points" on the cylinder valves of the gas extinguishing system units - not as a percentage of the installation items. In rate build-up some provincial quotas band "gas extinguishing system unit commissioning" by test vessel size (e.g. 40 L / 70 L / 90 L / 155 L / 270 L), measured per point. At construction acceptance the commissioning shall run a simulated discharge test on every protected zone or object per section E.3 of GB 50263-2007, and it shall pass; for pre-engineered systems such as cabinet gas extinguishing units and hot-aerosol units, one set of each is preferably tested per the linked-operation provisions of the product standard.
- ←
Deciding quota pricing of combustible gas alarms across systems: the split between the industrial-instrument "safety monitoring device" (per set) and the fire "point-type detector" (per unit), the code basis and the unit difference
Pricing a combustible gas alarm is not "either-or, take the dearer" but a match on three gauges: (1) system attribution (which controller receives the alarm signal); (2) device make-up (a lone sensor head, or head plus alarm controller as a set); (3) the quota item's unit and work content. Signals into DCS / PLC used for process interlocks price under the automatic-control instrument "safety monitoring device - combustible gas alarm" per "set" (integral installation of head plus alarm, system test); signals into the fire alarm panel used only for warning and fire interlocks price as "point-type detector - combustible gas" per "unit" (head plus base, in-situ commissioning). The hardest basis is GB 50116-2013 clause 8.1.2: "the combustible gas detection and alarm system shall stand alone, and combustible gas detectors shall not connect into the detector loops of the fire alarm panel; where the gas alarm signal must enter the automatic fire alarm system, it shall be brought in through the combustible gas alarm controller." Writing one basis down (or up) into the other is mis-application / unsupported cross-system borrowing, refutable on the code.
- ←
Deciding the quota items for pre-laid bond waterproof sheets: taking foundation sheet waterproofing under Beijing DB11/T 2382-2024 as the example, separating the "pre-laying method" items from the "torch-on method" items by construction process, with item work content, consumption and the companion measurement rules
Pre-laid bond (polymer self-adhesive film sheets) takes the "pre-laying method" items: Beijing DB11/T 2382-2024 foundation sheet waterproofing A-9-243 (HDPE self-adhesive film sheet, pre-laying, raft single layer, all-in labour Grade II 0.0630 workday/m2, HDPE film waterproof sheet 1.2 mm 1.3760 m2/m2) and A-9-244 (flat slab single layer, labour 0.0600 workday/m2, sheet 1.2510 m2/m2); the torch-on items must not be used. Basis: DB11/T 2382-2024 clause 4.10.8 "sheet waterproofing shall be itemised and determined by construction process"; the commentary to GB/T 51310-2018 clause 16.3.2 states plainly "cold-applied self-adhesive sheets must not be laid by the torch-on method".
- ←
Measurement of metal-surface rust removal (and painting, anti-corrosion): routed by object - plant and piping by area m2, metal structures by theoretical mass t/kg - with the companion rule of matching the unit of the quota item applied
Rust-removal quantities route by the OBJECT treated, not an either-or: plant and piping rust removal is computed by area (m2) on the design-shown surface, metal-structure rust removal by the theoretical mass of the structure (DB11/T 2382-2024 clauses 6.12.8, 6.12.9), and the outcome must match the unit of the quota item applied. Within metal structures a further split applies: general steelwork (hangers, supports, brackets, ladders, railings, platforms) and pipe-rack steelwork measure in kg; steelwork of sections over 300 mm and H sections over 300 mm measure by developed area in m2 (GB/T 50856-2024 Annex M table M.1.1 note 8); pipe surface S = pi x D x L, with fittings, valves, flanges, manholes and nozzle irregularities comprehended and not added. The municipal basis agrees (DB11/T 2382-2024 clause 7.4.51: pipe rust removal and painting on pipe surface area; steelwork rust removal and metal-structure painting on theoretical mass).
- ←
BOQ and quota item selection for compact package unit substations (prefabricated substations): the mainstream principle of billing the complete unit per set; splitting into transformer plus HV/LV panels only for non-package supply, missing quota bands or contract-required splits; with commissioning and handover-test interfaces and a Beijing / Shenzhen / railway / national-standard comparison
For package unit substations (compact / prefabricated substations) the principle is to bill the complete unit: apply one installation item per set by capacity band, the work content already covering positioning, wiring and checking, earthing and individual commissioning, with no split into transformer plus HV/LV panels; only non-package supply, missing quota bands or contract-required splits justify splitting, split and unsplit being mutually exclusive with strictly no double counting of included content. Beijing DB11/T 2382-2024 clause 6.4.19 (one container body counts as one unit), Shenzhen SJG 181.7-2024 (measured per set) and GB/T 50856-2024 (switchgear installation 030402 covers prefabricated substations; clause 3.0.11 - equipment installation includes commissioning of the equipment itself) are consistent; railway TB/T 10829-2024 splits installation (DY-1074 to DY-1084) and commissioning (DY-1407 to DY-1410) into two items per unit, likewise without splitting the body.
- ←
Indoor/outdoor boundaries for water-sewer, heating, gas, and fire-water pipes: scope of the 1.5m-outside-wall rule, manhole/valve attribution, and railway vs Beijing system differences
Water and heating pipes divide indoor/outdoor at 1.5m outside the building face (at the entrance valve where set; heating with an outdoor entrance unit at the circulation-pipe tee); drainage at the first exit inspection well — the 1.5m rule does not apply to drainage; gas by entry type at the first indoor valve (underground) or first tee outside the wall (above ground) (GB/T 50856-2024 Annex K K.9.1). Boundary components: valves belong to water/sewer works, wells to outdoor installation works (SJG 77-2020, 6.1.4). Railway has no 1.5m band: water at the entrance meter or junction well (direct entry at the building face), drainage at the first exit well (or septic tank) (TB/T 10832-2024 Vol. 11 volume notes).
- ←
Applying quota items to civil-defence duct airtight sleeves (airtight wall-penetrating spools with sealing flange rings) under the Beijing 2024 consumption quota standard: select Type I / III by the wall-penetration form, band by diameter within d300 / d600 / d1000, measured per "piece"; fabrication and installation of the sealing rib and the spool body are included in the item and not charged separately
Civil-defence duct airtight sleeves take the dedicated "pipes through airtight walls" tables: where a plain steel-plate duct is cast directly into the reinforced concrete wall, take Type I (C7-11-68/69/70, within d300/d600/d1000); where the duct is not cast in and a spool with a sealing flange ring is embedded, take Type III (C7-11-72/73/74), measured per "piece" (one per penetration); the sealing rib (sealing flange ring) and the spool body, both fabrication and installation, are already included in the item consumption (plate 2.6 mm to 3.2 mm is the spool body, 4.1 mm to 7 mm is the flange ring) - no separate sealing-rib / steel-piece item, and no duplicate charging of the main material.
- ←
Beijing DB11/T 2382-2024 consumption standard: rules for determining whether pipe installation quota line items include pipe fittings - in the gas chapter only galvanized steel pipe (threaded joints) items include fittings and pipe clamps while fittings of other materials are billed separately; pipe items of the water supply/drainage and heating chapters include fitting installation
Under DB11/T 2382-2024 clauses 6.10.32/6.10.34: pipe line items for indoor water supply, drainage and heating "shall include the fitting installation content" (fitting material quantities taken as the design-shown quantities or per Table 6.10.32), so no separate fitting-installation item may be applied; for gas piping, only galvanized steel pipe (threaded joints) items include fittings and pipe clamps, while for other materials (welded steel pipe, PE pipe, steel-skeleton plastic composite pipe etc.) the fittings and clamps must follow the corresponding "fitting and pipe-clamp installation" items. Pipes are measured along the design-shown centreline length with no deduction for lengths occupied by fittings and valves (6.10.36); fittings are counted as the design-shown number of pieces (6.10.37) - in gas works "pipe (m)" and "fittings (piece)" are two independent billed items.
- ←
Item-selection determination for graded-gravel replacement fill in excavation pits: the distinction among replacement-fill ground treatment (A-2-4 gravel spreading), foundation backfill and bedding layers, and quantity calculation (Beijing DB11/T 2382-2024 basis)
Under the Beijing DB11/T 2382-2024 "Construction Consumption Standard": the strengthening of soft or non-uniform soil layers after pit excavation is itemized as "replacement-fill ground treatment" (Appendix A, Table A.2.1-1); graded gravel uses A-2-4 "spreading, gravel" (m3; work content: spreading in layers, leveling, compaction), and sand/stone-chip replacement uses A-2-3. The replacement-fill sub-items exclude excavation of the in-situ soil (executed separately under Clauses 4.2.1 to 4.2.27); quantities are calculated by volume per the design dimensions (4.3.16). The distinction from backfill and bedding lies in position and design intent, not in material: foundation/room backfill uses backfill sub-items (e.g. A-1-38 graded sand-gravel; quantities calculated under 4.2.21/4.2.22), and bedding layers are itemized under the bedding tables A.4.5 and A.5.1-1 - the three must not be interchanged.
- ←
Quantity-calculation rules and itemizing method for busways (low-voltage enclosed plug-in busway / common-enclosure busway): by centre-line length, supports included, accessories listed separately by count - distinct from strip busbars
Common-enclosure busway and low-voltage enclosed plug-in busway installation quantities are calculated by the centre-line length of the dimensions shown on the design (m); support installation is included in the installation consumptions and not listed separately; tap-off (plug-in) boxes, end (staring) boxes, copper-busbar expansion joints, supporting insulators etc. are listed separately by the design quantities, and flexible copper connections are calculated per "phase/unit". Strip busbars follow different rules: calculated by per-phase length (including reservations) - 0.30 m/end for busbar terminations and 0.50 m/end for terminations to branch lines or equipment. Basis: DB11/T 2382-2024 Clauses 6.4.21-6.4.24 and Table 6.4.23; the BOQ basis is GB/T 50856-2024 Appendix D, Table D.3.1 (code 030403).
- ←
Scenario split for applying quota line items to PE-ERT pipes under Beijing DB11/T 2382-2024: assignment between floor radiant heating pipes (C10-7-41 to 43) and plastic water supply pipes (C10-2 / C10-1 series), with a comparison against PP-R and PE-X
Under Beijing DB11/T 2382-2024, PE-ERT pipes are priced by use scenario. Floor radiant heating pipes take C10-7-41 to 43 (pipe OD within 16/20/25 mm, unit m, under the heating-appliances items); the stated work content already covers "pipes of polyethylene and similar materials", so the items apply directly without material conversion. For plastic water supply pipes (fusion jointed), indoor takes C10-2-77 to 87, buried / in-wall takes C10-2-89 to 92, and outdoor takes C10-1-43 to 52. The floor-heating and water-supply line item families must never be cross-applied (the table note states expressly that buried laying "is not applicable to floor heating"); PP-R and PE-ERT share the same tables and items (main material converted per the design type), while PE-X cannot be fusion jointed and must not directly take the fusion-connection items.
- ←
Building automation system (BAS) / HVAC automatic control - BOQ item setting and appendix attribution under GB/T 50856-2024 Appendix E (code 030503)
HVAC automatic control / building automation (BAS) corresponds to the "building automation system" (code 030503) in GB/T 50856-2024 and is listed under Appendix E Building Intelligentization Engineering; items are set per Table E.3.1 (communication network control equipment 030503001, controllers 030503002, etc.; the unit of measurement is "unit (set)" and quantities are calculated as the numbers shown on the design drawings). Civil building automation systems apply Appendix E, while industrial automation systems shall be itemized under Appendix F Automation Control Instrument Installation Engineering; conduit, raceways, cable trays, junction boxes and electrical equipment associated with the intelligentization works shall be itemized under Appendix D Electrical Equipment Installation Engineering and must not be double-counted in the intelligentization BOQ.
- ←
Ventilation duct quantity calculation and classified measurement: whether supply / exhaust / fresh-air ducts are computed separately, the developed (unfolded) area rules, BOQ listing, and quota-norm tiering basis
Ducts are computed from design dimensions as developed (unfolded) area (m2): no deduction is made for inspection ports, measuring ports, supply openings or suction openings; length is taken along the design centreline (main and branch ducts divided at their centreline intersections), including the length of elbows, tees, reducers and rectangular-to-round adapters, but excluding the length occupied by components. Supply, exhaust and fresh-air systems are governed by one and the same rule set — there are no per-system differences in the calculation method; "separation" is expressed at the BOQ listing and rate build-up levels — listed by item description (use/name, material, shape, size, plate thickness, joint form), and split when quota line items are applied according to tiering factors such as joint form and size; the system itself is not a tiering factor.
- ←
Attribution of fire-power monitoring, electrical-fire monitoring, and fire-door monitoring systems: fire-service nature and calibers under the three systems of fire acceptance, construction-quality acceptance, and cost division
All three are companion subsystems of the automatic fire alarm system (FAS) and inherently "fire" (costing language: "fire electrical"): DBJ/T 15-248-2022 Clause 8.1.1 states "the automatic fire alarm system includes electrical-fire monitoring, fire-door monitoring, fire-shutter monitoring, fire-equipment power monitoring and other subsystems"; GB 50116-2013 Chapter 9 and Clause 6.11.3, GB 55036-2022 Clause 12.0.14, and GB 51348-2019 Clause 13.3.8 all regulate them as fire facilities/alarm-system matters. The "weak current" label comes only from the construction-quality-acceptance system — GB 50300 places the fire alarm system as a sub-division of the intelligent-building division (followed by DBJ/T 15-248-2022 Clause 8.1.1). The cost-division caliber (SJG 77-2020 Clause 6.6.3) groups all three under the "fire electrical system".
- ←
Pricing position for post-cast strip formwork under Beijing DB11/T 2382-2024: measurement on contact area, dedicated items by position (never the beam-and-slab item), and treatment of the formwork height exceedance
Post-cast strip formwork and supports are measured on the contact area with the strip (clause 4.17.6 item 6); dedicated items apply by position - foundation strip A-16-41/42, wall strip A-16-43, slab-type strip A-16-44 - and the beam-and-slab, flat slab and flat plate items (A-16-33) must not be used. The quick-closure expanded-metal mesh for the side stop-ends is already contained in the post-cast strip concrete items (foundation slab, beams, walls 4.2 m/m3; floor slabs 2.1 m/m3) and is not priced separately. The height-exceeding part follows its host member under the "each additional 1 m above 3.60 m" items, computed on the whole area of the exceeding part; an exceeding part under 1 m still executes the per-additional-1 m item (clause 4.17.1 item 4).
- ←
Applying quota items to socket solvent-cement jointing of UPVC water and drainage pipes under Beijing DB11/T 2382-2024, and judging the fittings content: take the "(solvent cement)" series, never the fusion series; match indoor / outdoor tables and diameter bands; fittings take no separate installation item; material quantities per the design-shown numbers or the fittings reference tables
UPVC socket solvent-cement jointing takes the "(solvent cement)" series items (indoor water supply table C.10.15-1, indoor drainage table C.10.17-1, outdoor water supply table C.10.4-2, outdoor drainage table C.10.5-2) and must not take the "fusion connection" series; the pipe items' work content already includes fitting installation, fittings take no separate installation item, and fitting material quantities are computed per the design-shown numbers or per the fittings reference tables 6.10.32 (indoor) / 6.10.23 (outdoor); pipe quantities are computed by length on the design-shown pipe centreline, without deducting the lengths fittings occupy.