Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Measurement rules for the matching flanges of flanged valves: in water supply/drainage, heating and gas works the flanges are not applied separately, while in industrial-pipeline works the valve and its matching flanges are calculated separately (DB11/T 2382-2024)

Per the Beijing local standard DB11/T 2382-2024 "Construction Consumption Standard", general installation works: in water-supply-and-drainage, heating and gas works, the flanged-valve installation sub-items are compiled on the basis of flange connections on both sides - the matching flanges and bolts are included in the valve installation sub-items and flange installation sub-items are not applied separately (where only one side is flanged, the flange and bolt quantities are halved, a consumption adjustment); in industrial-pipeline works "the installation of all flanged valves and the installation of the matching flanges shall have their quantities calculated separately" (6.8.54) - the valve sub-item does not include installation of the flange body (only the installation of one gasket and one set of flange bolts, with bolt materials charged separately), and the matching flanges must be applied under separate flange-installation sub-items; the same basis applies to medium- and high-pressure valves (6.10.52, 6.8.73 to 6.8.79).

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 通用安装工程(6.8 工业管道工程、6.10 给排水、采暖、燃气工程)

Topic Positioning

This card answers a high-frequency dispute in applying consumption standards: when a flanged valve is installed, must the matching flanges connecting it to the pipe be applied under separate flange-installation sub-items? The basis is the Beijing local standard DB11/T 2382-2024 "Construction Consumption Standard", general installation works - the rules of the water-supply/drainage/heating/gas system and the industrial-pipeline system are exactly opposite; the card serves to prevent omissions and duplicate pricing in budget compilation.

Core Conclusions

1. Water supply and drainage, heating and gas works: no separate flange application.

  • 6.10.49: "The construction consumptions of flanged valves may be compiled assuming flange connections on both sides; where only one side is flanged, the flange and bolt quantities shall be halved." The flanged-valve sub-items are thus compiled on the both-side flange-connection basis; the pipe-side matching flanges and bolts are included in the valve installation sub-item; with only one flanged side, the "halving" adjusts the flange and bolt contents inside the sub-item and is not a separate flange-installation sub-item.
  • 6.10.48: "The construction consumptions of valve installation shall include the sampling-inspection work of strength and tightness tests before valve installation."
  • 6.10.52: "Medium- and high-pressure valve installation shall be executed under the corresponding items of industrial-pipeline works." - medium/high-pressure valves within the water-supply-and-drainage volume revert to the industrial-pipeline "calculate separately" basis.

2. Industrial-pipeline works: flange-installation sub-items must be applied separately.

  • 6.8.54: "The installation of all flanged valves and the installation of the matching flanges shall have their quantities calculated separately." The valve and the matching (pipe-side) flange are two independent sub-items, measured separately.
  • The valve sub-item does not include installation of the flange body: the work content of low-pressure flanged-valve sub-item C8-7-13 is "preparation, valve shell pressure test and seal test, valve installation, bolting with molybdenum disulfide coating", with the note "flanged-valve installation includes the installation of one gasket and one set of flange bolts; the gasket material shall be determined by the design; the bolt material consumption is charged separately".
  • Consumption basis of the flange-installation sub-items (6.8.67): "The construction consumptions of low-pressure flange installation shall include the installation of one gasket, one set of flange bolts and blank plates (blinds), and shall not include cold/hot re-tightening during system commissioning after installation."
  • Adjustment rules, 6.8.68 (original text): "For stub-end lapped flanges of stainless steel and non-ferrous metals, the corresponding lapped-flange installation items apply; for fully heated jacketed flanges, the items for the inner-pipe flange diameter apply with the construction consumptions multiplied by 2.00; for single-flange installation, the corresponding flange-installation items apply with the consumptions multiplied by 0.61, the bolt quantity unchanged; throttle (flow-restriction) devices execute the flange-installation items with the consumptions multiplied by 0.70; welded blank plates (heads) execute the pipe-fitting connection items with the consumptions multiplied by 0.60."
  • 6.8.69: "Quantities of all flange installations shall be calculated by the numbers shown on the design drawings." 6.8.70: "For pipes connected by flanges, the pipe and the flange shall have their quantities calculated separately."
  • Bolts: 6.8.55 "the bolt specification and quantity shall be determined by the design"; 6.8.71 directs bolt calculation to Clause 6.8.55.
  • Medium and high pressure, same basis: 6.8.73 and 6.8.77 - the medium- and high-pressure flange-installation consumptions likewise "shall include the installation of one gasket, one set of flange bolts and blank plates"; 6.8.74 - "for single-flange installation the corresponding flange-installation items apply with the consumptions multiplied by 0.61, the bolt quantity unchanged; ... medium-pressure threaded flanges execute the low-pressure threaded-flange items with the consumptions multiplied by 1.20; medium-pressure slip-on welded flanges execute the low-pressure slip-on items with the consumptions multiplied by 1.20"; 6.8.79 refers execution to Clauses 6.8.69 and 6.8.70.

3. Omission/duplication checks.

  • The flanges shipped on the valve body: priced with the valve material; installation not counted in either system.
  • The pipe-side matching flanges (including the flanges on both sides of wafer-type valves): in the water-supply/drainage/heating/gas system they are included in the valve-installation sub-item - do not re-apply; in the industrial-pipeline system they must be applied under separate flange-installation sub-items.
  • Common errors: in industrial pipelines applying only the valve and omitting the matching flanges = omission; in the water-supply system re-applying flange installation for a flanged valve = duplicate pricing.

Applicable Boundaries

  • These rules come from Chapter 6 of the Beijing local standard DB11/T 2382-2024 (general installation works); the volume-note bases of other provinces'/cities' standards or the national unified quota may differ - verify the volume/chapter notes and sub-item work content of the applicable standard before cross-region use.
  • "No separate flange application" is limited to flanged-valve items of the water-supply/drainage/heating/gas system; the industrial-pipeline system (including medium/high-pressure valves within the water volume) requires the valve and the matching flanges to be measured separately.
  • Content halving and the coefficient adjustments (0.61, 1.20, 2.00, 0.70, 0.60 etc.) are consumption-adjustment rules, not new sub-items; apply coefficients per the original text of the standard.
  • Wafer-type valves (wafer butterfly valves, wafer check valves etc. whose bodies carry no flange): in the industrial-pipeline system both pipe-side connections are matching flanges, counted under flange-installation sub-items; in the water system they are covered by the two-side flange content of the valve sub-item.
  • Flange and bolt materials are quantified per the design; bolt specification and quantity per Clause 6.8.55.

Further Reading

  • DB11/T 2382-2024 Chapter 6 "General Installation Works", 6.10 water supply/drainage, heating and gas works, VI "Valves and pipe accessories", 6.10.47 to 6.10.60 (esp. 6.10.49 and 6.10.52).
  • The same standard, 6.8 industrial-pipeline works: VIII "Low-pressure valve installation" 6.8.48-6.8.55; XI "Low-pressure flange installation" 6.8.66-6.8.71; XII "Medium-pressure flange installation" 6.8.72-6.8.75; "High-pressure flange installation" 6.8.76-6.8.79.
  • Appendix C, general installation works, Table C.8.49 "Low-pressure flanged valves", sub-item C8-7-13 (example of work content and consumption composition, incl. the gasket-included / bolts-charged-separately basis).
  • Related extensions: 6.8.50 (valve shell pressure and seal tests - where no test is done, the consumptions of the corresponding items are multiplied by 0.60); 6.10.51 (solenoid valves, filters, steam traps and pressure-reducing valves execute the valve-installation items, with their labor coefficient provisions).

Keywords

  • 法兰阀门
  • 单独套法兰
  • 法兰安装子目
  • 配套法兰
  • 分别计算工程量
  • 工业管道
  • 给排水采暖燃气
  • 消耗量标准