Pricing and setting of pressure-reducing orifice plates in fire-water systems: quota item selection (Tianjin 7-31 to 35, Beijing 1-68 to 72, DB11/T 2382-2024 C9-1-68 to 72), counting per piece regardless of mounting position, companion flanges added as design quantities without double counting, the boundary against pressure-reducing valve sets (static versus dynamic pressure), and the mandatory code rules on orifice position and construction

Orifice-plate installation is counted per piece and graded by nominal diameter into pressure-reducing orifice plate installation items (Tianjin 2025 volume 7, 7-31 to 35; Beijing 2021 volume 9, 1-68 to 72; DB11/T 2382-2024 C9-1-68 to 72); whether installed in a flange, a union or a hydrant interface, the same item applies, and the item already covers pre-installation, removal and re-installation. The flange body is not included: when installed inside a flange pair, 'the flange quantity shall be calculated separately per the design drawings' (the two plates gripping the orifice count as one pair in the pipeline flange quantity), while the steel-pipe flanged-connection item already includes fitting and flange installation - so the same pair must never run the flange installation item again. Orifice plates reduce dynamic pressure only (installed downstream of alarm valves on distribution pipes and branches, orifice diameters stepping down where distribution-pipe inlet pressures exceed 0.40 MPa), whereas pressure-reducing valves cut both static and dynamic pressure (installed ahead of the alarm valve set) - the two are not interchangeable.

Applicable Codes

  • 天津市安装工程工程量清单计价指引(2025)表 J.1 水灭火系统(编码 030901)03-09-01-007 减压孔板;表 K.2 管道附件(编码 031002)031002009 法兰
  • 京建发〔2021〕201号《2021预算消耗量标准》通用安装第九册 消防工程 第一章 水灭火系统 说明三/四/五/十、第五节 减压孔板 1-68~1-72
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. C 通用安装工程 Table C.9.4-2(C9-1-68~C9-1-72)
  • GB 50084-2017《自动喷水灭火系统设计规范》第4.3.2条、第8.0.7条、第9.3.1条、第9.3.5条、附录D
  • GB 50974-2014《消防给水及消火栓系统技术规范》第10.3.1条
  • GB 50261-2017 · Code for Construction and Acceptance of Sprinkler Fire Extinguishing Systems 第5.4.8条
  • DB11 T 1832.13-2022《建筑工程施工工艺规程 第13部分:给水与排水工程》第10.4.17条
  • GB/T 50668-2011《节能建筑评价标准》第4.4.5条

Subject positioning

This card addresses pressure-reducing orifice plates in sprinkler (and hydrant) systems at two levels: pricing - which quota item, what unit of measurement, what the item includes, and how companion flanges are added without omission or duplication; and technical - the division of labour between orifice plates and pressure-reducing valves, when a plate is required, and on which pipe run it sits. For fire-water bills and budget review compiled under Tianjin 2025, Beijing 2021 or DB11/T 2382-2024.

Core conclusions

1. Identity: the orifice plate reduces dynamic pressure - it is not a valve

GB 50084-2017 (sprinkler systems design code) clause 4.3.2(2): 'sections controlling static pressure should be zoned or fitted with pressure-reducing valves; sections controlling dynamic pressure should be fitted with pressure-reducing orifice plates or throttle pipes.' The commentary: the provisions control pipe pressure by orifice plates and throttle pipes lowering dynamic pressure, and by zoning or pressure-reducing valves lowering static pressure.

The two are not interchangeable (GB/T 50668-2011 clause 4.4.5 commentary): 'a pressure-reducing valve reduces both static and dynamic pressure... a pressure-reducing orifice plate reduces only dynamic pressure, not static pressure, and its downstream pressure varies with upstream pressure and flow - insufficiently stable. Being cheap, it may be considered where water quality is good and supply pressure stable.'

2. Item selection and measurement

Pricing basis Bill item Quota (base price) item Unit
Tianjin installation pricing guide (2025), table J.1 water systems (code 030901) 03-09-01-007 pressure-reducing orifice plate (features: material, specification; connection) combinable only 7-31 to 35 'pressure-reducing orifice plate installation' (five consecutive items by nominal diameter), work content 'body installation' piece
Jing Jian Fa [2021] No. 201, volume 9 fire works, chapter 1, section 5 - 1-68 to 1-72 'pressure-reducing orifice plate', nominal diameter (mm up to) 50 / 65 / 80 / 100 / 150 piece
DB11/T 2382-2024, appendix C general installation - C9-1-68 (up to DN50) to C9-1-72 (up to DN150), table C.9.4-2 piece

Three measurement and non-duplication points:

  1. Counted per piece by design quantity, independent of pipe length; the plate ignores its mounting position - the notes state expressly that 'a pressure-reducing orifice plate installed in a flange, a union or a hydrant interface all executes the same item' - no separate item or coefficient for position.
  2. The work content already includes pre-installation and re-installation. Beijing 2021 volume 9, this section: yard transport, visual inspection, pre-installation of the orifice plate, removal and re-installation. This sequence serves the pressure-test-and-flush procedure and is inside the item - no separate removal or re-installation charge.
  3. Consumption make-up (Beijing 1-68 to 1-72, per piece): all-in labour class 2 - DN50 0.086, DN65 0.133, DN80 0.152, DN100 0.181, DN150 0.200 workdays; materials - orifice plate (content 1.0000 per piece, in parentheses as unpriced main material, priced separately to the design specification) x1, gasket material ('rubber sheet' in 2021, 'non-asbestos braided cord' in 2024) DN50 0.070 / DN65 0.090 / DN80 0.130 / DN100 0.170 / DN150 0.280 kg, other materials at 3% of material cost; machinery - other machinery at 3% of labour cost.

3. Companion flanges: added as design quantities, never re-itemised

Original note (Beijing 2021 volume 9 note 10; DB11/T 2382-2024 table C.9.4-2 note 2 identical): 'a pressure-reducing orifice plate installed in a flange, a union or a hydrant interface all executes the same item; where installed in a flange, the flange quantity shall be calculated separately per the design drawings.'

Correct reading and operation:

  • What is 'calculated separately' is the flange quantity, not a new installation item. The two flanges gripping the plate count as one pair in that pipe run's flange quantity.
  • The reason only the quantity is added - and the flange installation item is not run again - is that the pipe installation item already carries the operation: volume 9 note 3, 'steel pipe, flange connection includes the installation of fittings and flanges, but fitting and flange quantities are calculated separately per the design drawings, bolts per design quantity plus 3% wastage'. The flange erection labour is inside the pipe item; only the flange body is added as material.
  • Under Tianjin 2025, flanges have their own bill item 031002009 'flange' (per pair, with base-price items 8-734 to 757 'flange installation'). First test whether the chosen pipe item already includes flange installation: if included, add only the flange material and never run 8-734 to 757; if not, list per pair - avoiding 'once inside the pipe item, once again under the flange item'.

4. Boundary against pressure-reducing valve sets

Test Orifice plate Pressure-reducing valve (set)
What it reduces dynamic pressure only; downstream pressure varies with upstream pressure and flow, unstable both static and dynamic pressure; stable outlet pressure
Position distribution pipes and branches downstream of alarm valves (orifice diameters stepping down by floor / zone) GB 50084-2017 clause 9.3.5(1): 'shall be located ahead of the alarm valve set inlet'
Cost and management cheap, simple system, easy management higher investment; needs strainers, control valves, gauges
Pricing orifice installation item per piece where a 'pressure reducer (set)' item exists, one item per set (Tianjin 031002004 -> 8-705 to 720); otherwise split by connection type into valve items per unit

Further mandatory rules for pressure-reducing valves (GB 50084-2017 clause 9.3.5): (2) a strainer upstream, easy to drain; (3) a standby reducing valve where two or more alarm valve sets connect; (4) vertically set valves should flow downward; (5) proportional valves set vertically, adjustable valves horizontally; (6) control valves and pressure gauges on both sides (omittable where the main body carries a gauge); (7) valves preferably protected or locked against adjustment. Reason for item (1): apart from signal valves at flow-switch inlets, no other valves may be added freely on alarm valve outlet piping.

Because plates cut only dynamic pressure: where static pressure is excessive (static reduction needed), zoning or reducing valves are mandatory - plates cannot solve it; plates serve only branch loops whose static pressure is fine but local dynamic pressure too high.

5. Deciding whether and where to set the plate

  1. Dynamic-pressure control line: GB 50084-2017 clause 8.0.7: 'pipe diameters shall be set by hydraulic computation; distribution piping shall balance inlet pressures. In light- and ordinary-hazard occupancies, distribution-pipe inlet pressures should not exceed 0.40 MPa.' Design practice: compute hydraulically per alarm valve; from the first floor (or zone) whose distribution-pipe inlet exceeds 0.40 MPa, set an orifice plate at the start of that floor's distribution pipe (downstream of the flow switch), stepping orifice diameters down floor by floor (zone by zone).
  2. Constructive preconditions: GB 50084-2017 clause 9.3.1 / GB 50974-2014 clause 10.3.1 (identical wording): 'orifice plates shall: (1) sit on horizontal straight pipe not less than 50 mm in diameter, with straight lengths on both sides not less than 5 times that diameter; (2) have orifice diameters not less than 30% of the pipe diameter and not less than 20 mm; (3) be made of stainless steel plate.' Commentary plate thicknesses: 50 to 80 mm diameter, 3 mm; 100 to 150 mm, 6 mm; 200 mm, 9 mm. Branches below DN50 cannot host a plate.
  3. Workmanship: DB11/T 1832.13-2022 clause 10.4.17: (1) centre the plate between two flanges, set the gaskets and tighten the bolts symmetrically at intervals; (2) set the plate on horizontal pipe not less than 50 mm, orifice diameter not less than 50% of the pipe diameter, preferably on the straight run downstream of a bend and not closer than twice the pipe diameter; (3) throttle pipes not shorter than 1 m.
  4. Acceptance: GB 50261-2017 clause 5.4.8: 'throttle pipes and orifice plates shall be installed as designed. Check: all items. Method: comparison with drawings, visual and tape measurement.'
  5. Hydraulics: GB 50084-2017 appendix D, the orifice-plate local loss coefficient 'computed by the formula or taken from table D', with dk the orifice diameter in metres.

6. Main-material specification versus pipe diameter

Items are graded by the nominal diameter of the host pipe run (DN50 / 65 / 80 / 100 / 150); first take the grade of the run's nominal diameter, then fix the plate specification by the design orifice diameter (constructive floors per the 30%/20 mm code rule and the 50% local craft rule). The main material 'pressure-reducing orifice plate' appears in the item at a parenthesised 1.0000 per piece as unpriced - price it separately by orifice diameter and plate thickness (stainless 3/6/9 mm); never price the item base alone.

Applicability boundaries

  • Item numbers herein: Tianjin installation pricing guide (2025) volume 7, 7-31 to 35; Jing Jian Fa [2021] No. 201 volume 9 chapter 1, 1-68 to 1-72; DB11/T 2382-2024 table C.9.4-2 (C9-1-68 to C9-1-72). Other regions or editions (Tianjin 2012/2016, Beijing 2012) carry different numbers - re-map to the local current basis; never transplant these numbers.
  • 'No separate flange item' rests on 'the pipe installation item already includes fitting and flange installation'; under the industrial piping volume (volume 8 / appendix H), 'flanged valves and companion flanges are measured separately' - the opposite rule; judge by the volume chosen.
  • Orifice plates do not apply where static pressure must be cut (zone or use reducing valves), on branches below DN50, or where the straight-length requirements are not met.
  • The national design code and the local craft procedure differ on the orifice-diameter floor (code: not less than 30% of pipe diameter; DB11/T 1832.13-2022: not less than 50%); Beijing review and acceptance follow the stricter local rule, other regions the national code; the straight lengths are two different constraints - 'not less than 5 diameters on both sides' and 'not less than 2 diameters from a bend' - both must be met.
  • Items exclude: flange bodies (added as design quantities), secondary galvanizing of pipe (volume 9 note 4: 'calculated separately'), steel bases and concrete foundations (under their own volumes).

Further reading

  • Tianjin installation pricing guide (2025): table J.1 (code 030901), item 03-09-01-007 and its combinable base-price column; table K.2 pipe accessories (code 031002): 031002009 flange (pair, 8-734 to 757), 031002004 pressure reducer (set, 8-705 to 720).
  • Beijing: Jing Jian Fa [2021] No. 201, volume 9, chapter 1: notes 3 (flanged connections include fitting and flange installation; quantities added; bolts plus 3%), 4 (secondary galvanizing separate), 5 (grooved fittings), 10 (same item regardless of position; flange quantities added); section 5, 1-68 to 1-72 consumption tables; DB11/T 2382-2024 appendix C, table C.9.4-2 and its notes.
  • Design: GB 50084-2017 clauses 4.3.2 (components and pressure reduction), 8.0.7 (0.40 MPa inlet limit), 9.3.1 (plate construction), 9.3.5 (valve setting), appendix D (loss coefficient and table D); GB 50974-2014 clause 10.3.1 (identical wording, hydrant systems).
  • Construction and acceptance: GB 50261-2017 clause 5.4.8 (all-item check); DB11/T 1832.13-2022 Building Construction Craft Procedures, part 13, clause 10.4.17 and table 10.4.17 (throttle-pipe diameter selection).
  • Performance comparison: GB/T 50668-2011 clause 4.4.5 and commentary (valve versus plate performance; reduction and flow-limiting measures).

Keywords

  • 减压孔板
  • 减压孔板安装
  • 7-31~35
  • 1-68~1-72
  • C9-1-68
  • 配套法兰
  • 减压阀组
  • GB 50084-2017