Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)

Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.

Applicable Codes

  • TB/T 10829-2024 铁路工程预算定额 Vol. 8 电力工程
  • TB/T 10826-2024 铁路工程预算定额 Vol. 5 通信工程
  • DB11/T 2382-2024 建设工程施工消耗量标准 App. F 构筑物工程
  • DB11/T 2382-2024 建设工程施工消耗量标准 App. G 城市轨道交通工程
  • DB11/T 2382-2024 建设工程施工消耗量标准 第7.4章 管网工程
  • SJG 181.7-2024 市政工程消耗量标准 Vol. 7 电力通道、通信管道及照明工程

Scope of the question

Cable working chambers (handholes, manholes) appear throughout power, lighting and telecommunications works. This card explains how to choose the pricing route, the item attribution of power cable chambers versus lighting / telecom handholes, and the precast versus cast-in-place test, across the three commonly used quota systems of railway, Beijing and Shenzhen.

Core conclusions

1. First choose the route: whole-chamber comprehensive items vs split combined items

  • Route A, whole-chamber items: unit per chamber; work content comprehensively covers the base, masonry or casting, rendered walls, waterproofing, covers and frames (even pit excavation and backfill outside); once applied, the sub-items covered by its work content must not be listed again - otherwise double counting.
  • Route B, split items: blinding, masonry (base), member formwork, rendering, concrete cover fabrication and installation, cover and seat installation listed separately in m3 / m2 / set.
  • A or B follows the local quota's compilation; the two must not be mixed in one project.

2. Power (electric cable) chambers - the power / cable line chapter

  • Railway TB/T 10829-2024 Volume 8 Power Works, Chapter 2 cable lines, Section 5 cable manhole fabrication uses whole-chamber items: DY-341 to DY-343 brick cable manholes (2700x1600x1800, 2600x1500x1800, 1800x1400x1800, unit per chamber), DY-344 brick cable manhole volume up/down 1 m3 (m3); DY-345 to DY-347 cast concrete cable manholes (same three sizes), DY-348 cast concrete manhole volume up/down 1 m3, DY-349 manhole rendering and waterproofing (area up/down 1 m2, m2).
  • Work content, source: excavation, reinforcing bar fabrication and fixing, concrete base pouring, brickwork, wall rendering, curing, cleaning, cable bracket fabrication and fixing, waterproof coating, cover precasting and installation, backfill outside and compaction. Earthworks, base, masonry, rendering, brackets, waterproofing, covers and backfill are all comprehensive - once applied, excavation, cable brackets and covers must not be listed again.

3. Telecom / lighting handholes - the telecommunications / ducting chapter

  • Railway TB/T 10826-2024 Volume 5 Telecommunications Works, Chapter 1 Section 2 optical (electric) cable duct laying, item 5 masonry manholes / handholes: TY-60 to TY-62 manholes up to 24 ducts (straight / 3-way / 4-way), TY-63 to TY-65 manholes up to 48 ducts (straight / 3-way / 4-way), TY-66 to TY-69 handholes (90x120, 120x170, 150x150, 200x200 cm), all per chamber - whole-chamber comprehensive items.
  • Work content, source: timber formwork making, fixing and removal, rebar cutting and binding, concrete mixing and pouring, brickwork, installing manhole frames and cable brackets, pointing and rendering, curing, washing, waterproof coating - formwork, rebar, concrete, brickwork, frames and brackets, pointing, rendering and waterproofing all included.

4. Whole-chamber items in local standards (Beijing DB11/T 2382-2024)

  • Appendix F structures works, Table F.1.5-2.3 standard concrete cable chambers banded by straight / 3-way / 4-way / corner type x small / medium / large x plan size x H=2.1 m (items F-1-33 to F-1-53, unit per chamber, comprehensive), with a depth per 0.10 m up/down item for depths other than 2.1 m.
  • Its work content is cast-in-place: rebar fabrication and fixing, concrete placing, vibrating and curing, waterproof and damp-proof rendering, cover installation etc. Earthworks are not listed; pit earthworks are usually charged separately under rock and earthworks items. Bands marked with traffic loading exist - check the design loading when selecting.
  • Appendix G urban rail transit G3-1-63 masonry manhole up to 24 ducts 1200x1700 (per chamber) follows masonry workmanship, work content including timber formwork making / fixing / removal, rebar cutting and binding, pouring, brickwork, installing manhole frames and cable brackets, pointing, rendering, curing, washing, waterproof coating.

5. Split items in local standards (Shenzhen SJG 181.7-2024 Volume 7)

  • Volume 7 Power Channels, Communication Ducts and Lighting Works, Chapter 1 covers duct bank laying, power cable chambers, lighting pull pits, telecom manholes / handholes, cable brackets, cable trench cover edging and seats - i.e. power chambers, lighting pull pits and telecom manholes / handholes are compiled as split items (route B).
  • Chapter rules: blinding by volume shown in m3; masonry and bases by volume shown in m3 deducting duct volumes; rendering by area shown in m2 deducting duct areas; member formwork by contact area in m2; concrete cover fabrication and installation by size shown in m3; covers and seats by quantity shown per set.
  • Cast iron covers and seats are compiled on light cast iron; where the design differs, adjust the cover material per the design, other contents unchanged; the brick wall rendering items suit internal rendering (compiled at 20 mm); external rendering applies them with labour x 0.80.

6. Can a precast concrete cable chamber be applied?

  • The key is the local item's workmanship: Beijing DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers has cast-in-place work content (rebar + placing, vibrating, curing + waterproof / damp-proof rendering + cover installation) - a cast-in-place item, not to be applied as precast.
  • For precast assembled members, quantities follow Chapter 7.4 network works of DB11/T 2382-2024: precast concrete member installation (other than shafts) by volume shown (7.4.15), precast concrete shafts by length shown (7.4.16); steel brackets etc. by mass (7.4.17).
  • Where the local quota has no precast chamber item it is a gap: compile a supplementary unit-rate build-up schedule per quota compilation principles or borrow a similar-workmanship item, with approval - never directly apply cast-in-place chamber items.

Applicability limits

  • This card addresses the pricing route and item attribution for cable working chambers (handholes / manholes); base prices and labour / material / plant consumptions follow the quota version and current local prices.
  • The railway quotas (TB/T 10826-2024, TB/T 10829-2024) suit railway works; DB11/T 2382-2024 suits Beijing; SJG 181.7-2024 suits Shenzhen; projects elsewhere use the corresponding local quotas.
  • Whole-chamber and split items must not be mixed; when applying whole-chamber items, check whether earthworks, brackets and covers are already included - included ones must not be listed again.
  • Whether precast chamber items exist, depth and loading bands, and cover material adjustments follow the local quota notes.

Further reading

  • Railway: TB/T 10829-2024 Volume 8 Power Works, Chapter 2 Section 5 cable manhole fabrication (DY-341 to DY-349); TB/T 10826-2024 Volume 5 Telecommunications Works, Chapter 1 Section 2 duct laying, item 5 masonry manholes / handholes (TY-60 to TY-69).
  • Beijing: DB11/T 2382-2024 Appendix F structures works, Table F.1.5-2.3 standard concrete cable chambers (F-1-33 to F-1-53 and the depth up/down items); Appendix G urban rail transit, Table G.3.9 masonry manholes / handholes (G3-1-63); main text Chapter 7.4 network works concrete works (7.4.12 to 7.4.18).
  • Shenzhen: SJG 181.7-2024 Volume 7 Power Channels, Communication Ducts and Lighting Works, Chapter 1 (chapter notes, quantity rules, cover and rendering adjustment clauses) and general provisions Article 0.3.4 on cross-volume division and borrowing.

Keywords

  • 电缆人井
  • 手孔井
  • 人孔井
  • 砌筑人孔
  • 电力电缆井
  • 照明拉线井
  • 套定额子目
  • 预制混凝土电缆井