Concrete quantity calculation rules: cast-in-place and precast members measured by volume per design-drawn dimensions
Concrete quantities are calculated by volume (m3) per design-drawn dimensions: for cast-in-place members, the volumes of rebar, steel wire, iron parts, bolts, and reserved grouting ducts are not deducted, and for walls and slabs, holes with individual area <= 0.3 sqm are not deducted (> 0.3 sqm shall be deducted); precast members are measured by solid volume (excluding hollow parts), without deducting rebar, iron parts, or prestressing reserved ducts. Columns, beams, walls, slabs, foundations, and stairs each have interface-attribution and deduction rules; all specialty quota norms apply the same measurement basis.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- GB/T 50861-2024 城市轨道交通工程工程量计算标准
- SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准 Vol. 2
- T/ZS 0461-2023 房屋建筑工程造价BIM计量应用规范
Topic Positioning
General concrete quantity calculation rules and member-specific details, covering cast-in-place and precast members, applicable to building, railway, municipal bridge and culvert, utility tunnel, and rail transit specialties.
Core Conclusions
General principle: measure by volume (m3) per design-drawn dimensions; for cast-in-place members, the volumes of rebar, steel wire, iron parts, bolts, and reserved grouting ducts are not deducted; for walls and slabs, holes with individual area <= 0.3 sqm are not deducted (> 0.3 sqm shall be deducted); solid volume excludes the hollow parts of beams and slabs. Columns: cross-section x column height; for beam-supported slabs the column height runs from the top of the column foundation to the top surface of the floor slab above; for flat-slab construction, to the underside of the column capital; corbels and column capitals are merged into the column body; where beam and column overlap, count as beam. Beams: beam length runs to the side face of the column; secondary beams run to the side face of the main beam. Walls: centerline length x height x thickness, deducting door/window openings and holes > 0.3 sqm; wall pilasters, concealed columns and concealed beams are merged. Slabs: beam-supported slabs by the sum of beam and slab volumes; flat slabs by slab + column capitals. Foundations: pile heads extending into pile caps are not deducted; reserved holes in equipment foundations shall be deducted. Stairs are measured by horizontal projected area, without deducting stair wells narrower than 0.5 m. Precast members: for installation and transport, measure by solid volume (excluding hollows), without deducting rebar, iron parts, or prestressing reserved ducts; the railway measurement basis additionally deducts the voids of hollow slabs.
Applicable Boundaries
Applies to measurement of the concrete itself; the 0.3 sqm threshold and interface rules are governed by the applicable quota norms; formwork, rebar, and preliminary items are calculated separately; BOQ net dimensions and quota measurement bases must be distinguished.
Further Reading
See TB/T 10831-2024 Volume 10 book notes '10. Quantity calculation rules'; GB/T 50861-2024 Appendix C.8.4; SJG 181.2-2024 Clauses 2.2.1/3.2.2; SJG 111.2-2022 Clause 3.2.1.
Keywords
- 混凝土工程量
- 现浇混凝土
- 预制混凝土
- method of measurement
- 混凝土构件
- 不扣除钢筋铁件
- 0.3平方米孔洞
- 按设计图示尺寸
Related Cards
- →
Preventing double counting of decoration quantities: deduction and inclusion rules for floors, wall/column faces, and ceilings
In decoration quantity takeoff, first draw the interfaces, then apply the "deduct/include" rules so each surface is computed on its own: openings are uniformly deducted at the single-opening 0.30 m2 threshold; the side faces of door/window openings are not added; the side faces of attached columns/beams/piers are merged into the wall face; for beamed ceilings the beam sides merge into the ceiling; plaster on the soffit of slab staircases at horizontal projection x 1.15, zigzag x 1.37; ceiling furring by the clear area between main walls, the finish layer by the room net area minus freestanding columns — the furring and finish layers differ in caliber and must not be mixed. BOQ caliber per GB/T 50854-2024 Appendices L/M/N; quota caliber per TB/T 10831-2024 Volume 10 Building Works.
- →
Earthwork excavation quantity take-off (measurement): working space width, slope coefficients, and haulage (disposal of surplus excavated material) quantities
Earthwork excavation quantity take-off (measurement) follows the three-level priority "design → project execution plan (construction methodology and site organization) → default values in standard appendix tables"; excavation and haulage are measured in the natural in-situ (undisturbed) volume before excavation, backfill in the as-completed volume; working space widths and slope coefficients are taken from tables by foundation material, soil class, and machine working position, and no slope is calculated where shoring boards are placed; the quantity for disposal of surplus (excavated) material = excavated volume − backfill reuse volume, haulage being measured in the natural-state volume with no additional bulking factor.
- →
Distinguishing the quantity calculation of cable trays (bridges), wireways, and conduits (GB/T 50856-2024 electrical installation measurement)
Cable trays (the collective term for ladder racks, trays, and channel boxes) carry cables, wireways carry insulated wires, conduits protect wiring; the bodies of all three are measured by length (m) per the design dimensions, without deducting the lengths occupied by intermediate junction boxes (outlet boxes), lamp boxes, switch boxes, socket boxes, or fittings — the boxes are counted separately by "count"; conduits add junction/pull boxes when exceeding 40 m without bends, 30 m with 1 bend, 20 m with 2 bends, or 10 m with 3 bends.
Cited By
- ←
Steel cover plates for trenches (channel troughs): quota-system attribution of steel grating covers versus chequer-plate covers, line item selection, measurement-unit conventions, whether the main material is priced separately, separate billing against the trench body, and the distinction from manhole-cover items at inspection chambers
For steel cover plates, first identify the applicable system, then pick the line item: steel covers laid continuously along a trench follow the metal-structures basis - self-fabricated covers (steel included) are measured in t for fabrication plus erection, while proprietary grating covers are measured in m2 for erection only with the main material priced separately; cast iron or composite covers at inspection chamber openings are counted per piece or per set, and the two systems must not be cross-applied. The structures BOQ bills trench base slabs, walls and cover slabs separately (the cover is a stand-alone item); masonry trench line items carry only blockwork plus joint pointing, so the cover must be billed separately, whereas the all-in trench item measured by m already includes 'trench cover fabrication and erection' in its work content and must not be re-billed. Section-steel edge frames and angle stiffening frames of covers are merged into the cover quantity in t by theoretical mass, and grating apertures with a single-opening area of no more than 0.30 m2 are not deducted.
- ←
Determining disputes over the supplied quantity of commercial (ready-mixed) concrete: measurement by total delivery of mixer trucks, per-truck delivery-note sign-off and the quantity objection period, drawing-based take-off as cross-check, and the paths of burden of proof and expert assessment
Ready-mixed concrete supply is measured by volume (m3) and calculated as the total delivered by mixer trucks (per-truck volume = actual truckload divided by the apparent density of the fresh concrete mix). In disputes the first-rank basis is the total of the per-truck delivery notes signed by the purchaser; drawing-based take-off serves only as a cross-check and must not outright replace the total-delivery basis (DB/T 29-184-2017 Clauses 6.4.1-6.4.3). Where the purchaser signs a delivery note stating quantity, type and specification, it is presumed to have inspected quantity and apparent defects (Civil Code Article 623); non-conforming quantity must be notified within the inspection period, and failure to notify in time is deemed conformity of quantity (Article 621). Where no signed evidence exists, the party may apply for an order that the other party produce documents under its control (Interpretation Article 112) or for judicial expert assessment (Civil Procedure Law Article 79); where an assessor refuses to attend the hearing despite notice, the opinion must not serve as the basis for finding facts (Article 81).
- ←
The dual measurement boundary of composite slabs and composite beams: the precast soffit plank itemised as a precast concrete component for prefabricated construction (010504), the post-cast composite topping merged into post-cast concrete of composite beams and slabs, and the attribution of its rebar (010506) and formwork (010505)
Composite members must be measured on two sides: the precast soffit plank is measured in m3 as a precast concrete component for prefabricated construction (010504), with no deduction for grout sleeves, post-cast keyways or plank joints, and the joint grouting layer and bedding mortar layer are merged into the component volume; the post-cast concrete strips between precast planks are, per item 4 of GB/T 50854-2024 Annex E.7.7, 'measured within post-cast concrete of composite beams and slabs' and are not added to the plank volume; rebar of the post-cast layer goes to 010506 and formwork to 010505 (by contact area), and none of the three may duplicate the measurement of the precast plank.
- ←
Recasting the concrete volume increment and the formwork contact-area increment after section-size changes to concrete members, why the two move out of step (volume is quadratic in size, formwork linear), the layered order of computation for linked rebar costs, and the tie-in with the 15% quantity-deviation clauses
Concrete is measured by design volume (m3) and formwork by contact area with the concrete (m2) - two independent BOQ items and two geometric functions, so they cannot move in step. With length unchanged, the concrete increment dV = (A_c1 - A_c0) x L; the formwork increment dA = (C1 - C0) x L + (A_b1 - A_b0). The section area b.h is homogeneous of degree 2 in the sizes while the section perimeter 2(b+h) is degree 1: scale the section by k on both sides and volume grows by k^2 but formwork by k - a column with both sides enlarged 5% gains about 10.25% volume but only 5% formwork. After the change, measurement = original BOQ quantity plus or minus the increment; whether the quantity change triggers rate renegotiation follows the 15% bands of GB/T 50500-2024 clauses 8.9.1/8.9.2.
- ←
Member boundary rules for measuring cast-in-place concrete columns, beams, slabs and walls: the levels to which column height and beam length run, the merge and split boundaries for slabs, the deduction thresholds for walls, the attribution of crossover nodes such as column caps, corbels, concealed beams and wall columns, and the differences among three parallel scopes - the BOQ measurement standard (GB/T 50854-2024), local consumption standards and traditional quota manuals
Cast-in-place concrete columns, beams, slabs and walls are all measured by volume (m3) on the dimensions shown on the design drawings, but the 'member boundaries' differ by governing scope. Building quota scope - with ribbed-slab (beam-and-slab) floors, column height runs from the top of the column base (or the top of the floor slab) to the top of the floor slab above; with beamless (flat-slab) floors, to the underside of the column cap; frame columns run to the column top; constructional columns run from the top of the member they root in to the underside of the member they anchor into, the wall-embedded toothing portions being merged into the column body. Beam length runs to the side face of columns; secondary beams run to the side face of primary beams; ribbed slabs take the sum of beam and slab volumes, beamless slabs take slab + column caps, plain slabs take the solid slab volume (this three-way split applies only to local consumption standards and traditional quota scopes). GB/T 50854-2024 Appendix E shows no merged 'ribbed / beamless / plain slab' items in its BOQ scope: slabs are itemised separately as solid floor slabs, sloped roof slabs, hollow floor slabs and other slabs, beams and slabs carry separate codes, and it expressly provides that 'where a wall meets a column, the wall is measured to the column face; where a wall meets a beam, the wall is measured to the beam underside; where a wall meets a slab, the slab is measured to the wall side'; special-shaped columns (section height-to-thickness ratio over 4 in every direction) are itemised as 'reinforced concrete walls'; walls deduct door and window openings and individual holes over 0.3m2, with wall pilasters and projections merged in. The rail-transit underground scope is the opposite: columns run to the underside of beams / slabs, beam-column overlaps go to the beam, and column caps merge into the column body.
- ←
What to deduct and what not to deduct in concrete quantities: rebar / bolts / embedded steel items / tensioning ducts not deducted, rigid-skeleton structural steel deducted, the 0.3m2 single-opening threshold and the distinction from door and window openings (criteria compared across building GB/T 50854, municipal GB/T 50857, rail transit GB/T 50861, railway TB/T 10831 and local consumption standards)
Concrete quantities are measured by design-shown dimensions in volume (m3): the volumes occupied by rebar, bolts, embedded steel items and tensioning ducts in cast-in-place members are never deducted; openings of no more than 0.3m2 each are not deducted (over 0.3m2 is deducted); but the volume of rigid-skeleton structural steel is deducted. The 0.3m2 test is on the area of each single (single-hole) opening, not on cumulative area; door and window openings are always deducted from walls, and the concept does not apply to slabs.
- ←
How to look up 'no deduction / deduction' threshold clauses in the measurement rules (enumerated item by item in the appendix rule column, judged by the area of a single opening at 0.3m2), with a threshold comparison table for concrete, formwork, masonry and flooring
'No deduction' clauses are written item by item in the 'quantity measurement rule' column of the appendix tables of the measurement standards, and the determination rests on three elements: the comparison object is the area of a single opening (not the total opening area, not the share of member volume); the direction is 'no more than 0.30m2 (within) - no deduction, above 0.30m2 (beyond) - deduct' (equal to the threshold counts as no deduction); and the measurement form distinguishes volume from area (formwork by contact area). Reinforcement, bolts, embedded plates and grouting ducts inside members are never deducted, but the structural steel of steel skeletons is deducted; cast-in-place walls and slabs and cast-in-place members of municipal bridges, culverts and pipeline networks all take the single opening of 0.3m2 as the boundary; in masonry, beam heads, slab ends and the like and other single openings no more than 0.30m2 are not deducted, and waistbands, cantilevered eaves and door and window linings projecting from the wall face are not added; monolithic flooring does not deduct partition walls, columns and pilasters no more than 0.3m2, attached chimney flues and openings, and openings at doorways and voids are not added, while for tile and stone finishes the openings are merged in. Net quantity = quantity by drawn dimensions - deductible items + items to be merged in; missing the companion sentence 'the sides of openings are likewise not added / the projecting part is merged in' makes the quantity wrong.
- ←
Deduction basis for cast-in-place concrete of steel-reinforced concrete (SRC) columns: embedded steel sections (rigid skeletons) deducted, shear studs and other bolt-type connectors not, with two algorithms - by drawn volume and by tonne conversion
The cast concrete quantity of SRC columns deducts the volume of the embedded steel sections (rigid skeleton) and does not deduct shear studs and other bolt-type connectors. Basis: GB/T 50854-2024 Appendix E general notes on cast components - cast reinforced concrete does not deduct rebar, bolts, embedments or post-tensioning ducts, but does deduct the steel sections of rigid skeletons - the sole exception to the no-deduction list. Deduction, one of two ways: 1 by the actual drawn volume of the sections; 2 by the simplified 0.127 m3 per tonne of sections (i.e. converted at 7850 kg/m3, expressly per Beijing DB11/T 2382-2024 Article 4.6.6). The sections themselves itemise separately in t under Appendix F metal structure works; shear studs neither join the concrete deduction nor the steel quantities, itemised separately per piece / set.
- ←
Choosing the pricing route and item attribution for electrical handholes / manholes under quotas (power cable chambers, street-lighting pull pits, telecom manholes / handholes, precast vs cast-in-place)
Pricing a cable working chamber first chooses between two routes: (1) whole-chamber comprehensive items (unit per chamber, work content covering the base, masonry or casting, rendered and waterproofed walls, covers and frames, even pit excavation and backfill outside - no further sub-items covered by them); (2) split combined items (blinding / masonry base / formwork / rendering / cover fabrication and installation / cover and seat listed separately, units m3 / m2 / set). Power (electric cable) chambers go to the power / cable line chapters (e.g. TB/T 10829-2024 Volume 8 DY-341 to DY-349 cable manhole fabrication); street-lighting pull pits and telecom manholes / handholes go to the telecommunications / ducting chapters (e.g. TB/T 10826-2024 Volume 5 TY-60 to TY-69 masonry manholes / handholes). Whether precast concrete chambers can be applied depends on the item's workmanship: DB11/T 2382-2024 Table F.1.5-2.3 standard concrete cable chambers is a cast-in-place work content and cannot be applied as precast; precast members and shafts are measured by volume / length per Articles 7.4.15 / 7.4.16, and where no precast chamber item exists it is a gap requiring a supplementary quota and approval.
- ←
Formwork quantity measurement basis for concrete inspection chambers and structures: by formwork-to-concrete contact area in m2, counting both inner and outer faces of chamber walls, with base side forms and the base flow channel calculated separately; standardised chambers are comprehensively priced per chamber with formwork included and not separately charged, while non-standardised concrete chambers use water-treatment structure tank base slab / wall / cover slab items (labour x 1.1); single holes up to 0.3 m2 are not deducted with no hole side forms added, holes over 0.3 m2 are deducted and their side forms added
Formwork for concrete inspection chambers is invariably measured by the area of formwork in contact with concrete, in m2 (not by volume or projected area). First distinguish scenarios: standardised inspection chambers (per the 07MS101/06MS201 standard drawings) are comprehensively priced per chamber, the items already including formwork erection and removal, so the formwork contact area is not calculated separately; only non-standardised cast-in-place concrete chambers are measured by contact area across walls, base (base slab / flow channel), risers and cover slabs, using the water-treatment works Chapter 6 cast-in-place reinforced concrete tank base slab, wall and cover slab and the related preliminary items, with labour multiplied by 1.1. Chamber walls are formed on both inner and outer faces and both faces count; holes follow the 0.3 m2 single-hole threshold (up to 0.3 m2 not deducted and hole side forms not added; over 0.3 m2 deducted and hole side forms added); the base flow channel is measured separately by the contact area of the cast flow channel with the formwork.
- ←
Pricing the core filling of hollow blocks (core-column concrete): never merged into the block-wall items - apply the cast-in-place concrete column "core column" item, quantities on hole section area times design-shown height
Block-wall items cover only "mixing mortar, cutting, laying and the like" - core filling is outside; apply the "core column" item among the cast-in-place concrete columns (Beijing DB11/T 2382-2024 A-5-13; 2021 edition 5-13), unit m3; quantities on the hole cross-section area times the design-shown height by volume. Plain and reinforced core columns take the same item; the bars, ties and inserts within them execute under the concrete and reinforced concrete rules. Regions differ (Shaanxi, e.g., already counts the core mortar of vertically laid blocks at opening jambs inside the walling mortar) - apply per the local quota notes.
- ←
Waterproofing quantity calculation rules: part-by-part measurement and deduction/merge rules for foundation base slabs, floors, walls, and roofs
Waterproofing (membrane/coating/rigid) quantities are calculated by area (sqm) per design-drawn dimensions, with part-specific deductions/merges: base slabs do not deduct pile heads; side faces and top surfaces merge into the foundation; retaining walls above the raft are treated as wall waterproofing; floors/roofs do not deduct holes <= 0.3 sqm, upturns <= 300 mm merge into the plane, > 300 mm are listed as wall/vertical waterproofing; walls deduct holes > 0.3 sqm, and the side faces of attached columns and pilasters merge; division joints by length (m); pile-head waterproofing by piece for pile diameter <= 500 mm, by developed area for > 500 mm; anchor heads by piece.
- ←
Norm items and measurement for shear-wall concealed columns, concealed beams, and coupling beams (Beijing DB11/T 2382-2024: concealed members merge into the wall; shear walls route by section height-to-thickness ratio into short-leg walls/columns/straight walls)
Per Beijing DB11/T 2382-2024: concealed columns and beams integral with the wall execute the wall items (quantities merge into the wall, no separate column/beam items); shear walls route by section form — thickness <= 300mm with max limb height/thickness ratio > 4 and <= 8 take short-leg wall items, <= 4 may take column items, the rest straight walls (e.g., A-5-24); Beijing sets no separate coupling-beam entry — practice merges them into the wall. Wall-beam interface: beam length to the wall face, wall height to the beam soffit.
- ←
Measurement boundaries and bill split of profiled-sheet composite floors (floor decking / rebar-truss decking): the steel sheet floor by horizontal projected area, the concrete above as solid slabs less the sheet volume
The profiled sheet / rebar-truss decking itself takes Annex F "steel sheet floors" (010605001) in m2 on the design-shown laid horizontal projection (no deduction for single columns, piers or holes of 0.3 m2 or less); the cast-in-place concrete above lists separately under Annex E "solid slabs" in m3, deducting the volume occupied by the sheeting and computing the concrete volume changes caused by the sheet profile; slab rebars take the Annex E rebar items in t; shear studs and high-strength bolts stay out of the steel member quantities and list under separate codes.
- ←
Deciding deductions for reserved bolt holes under the two measurement bases of concrete and formwork (including raft / foundation member classification, the 0.30 m2 hole threshold, and the equipment-foundation pocket exception)
Reserved bolt holes in cast-in-place reinforced concrete members are generally deducted under neither basis: concrete per "no deduction for the volume of rebar, bolts, embedded parts or ducts within the member" (GB/T 50854-2024 Annex E E.7.1); formwork per "holes of individual area 0.30 m2 or less in walls and slabs are not deducted, and the formwork to the hole reveals is not added". Reserved bolt hole diameters usually sit far below 0.30 m2, so nothing is deducted. Exceptions: where the individual hole area exceeds 0.30 m2, concrete (on the slab / wall basis) deducts the hole volume and formwork deducts the hole area while adding the reveal formwork; the reserved pockets of equipment foundations (railway and like systems) are deducted in volume.
- ←
Beijing DB11/T 2382-2024 consumption standard: quantity rules for cast-in-place concrete columns and the setting of column heights (including constructional columns, corbels, concrete-filled steel tube columns, raking columns and core columns)
Per DB11/T 2382-2024 Construction Works Consumption Quota Standard, clause 4.6.6 item 3: cast-in-place concrete columns are computed by volume (m3) at design-shown dimensions, without deducting the volume of rebar and embedded parts. Column heights - beam-and-slab columns from the column base top (or slab top) to the next floor slab top; flat-slab (beamless) columns to the column capital soffit; frame columns from base top to column top; constructional columns from the top of their rooting member to the soffit of their anchoring member, with the wall-toothing part merged into the column body. Corbels attached to columns merge into the column volume; concrete-filled steel tube columns are computed on the internal section area of the tube times the design-shown tube height; raking columns on the column section area times the design-shown inclined centreline length; core columns on the hole section area times the design-shown height.
- ←
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
- ←
Prestressed rebar (wire strand) quantity calculation: pre-tensioning vs post-tensioning calibers, curved segments by true length not projection, anchorage adjustments, and railway/highway/municipal differences
Prestressed rebar mass = design length x theoretical unit mass (t): pre-tensioning by member-dimension length; post-tensioning by design duct length adjusted per anchorage type (screw anchors -0.35m; bearing-plate bars +0.15/+0.30m; self-anchoring +0.35m; conical and JM/XM/OVM/QM anchors <=20m +1.0m, >20m +1.8m); curved segments by true arc length, not projection; field cutting length generally does not enter quantities (railway uses design cutting length; highway estimate caliber includes working lengths) — apply each sector's caliber separately.
- ←
Why post-cast strip quantity takeoff deducts wall thickness: member-by-member assignment and interface division rules
Where a post-cast strip passes through walls, beams, and slabs, quota items must be applied by member category (e.g., Beijing DB11/T 2382-2024 Table A.5.1-9 splits four items: base slab / beam / floor slab / wall); the length of post-cast strips in slabs, beams, and other horizontal members is measured only to the wall face — hence the centerline length deducts the wall thickness; the wall-thickness segment is charged separately under the "wall post-cast strip" item, avoiding duplicate measurement and misapplied items. Same origin as the member-interface rules of Clause 4.6.6: "beams measured to the wall side face; flat slabs by the clear area between main walls".
- ←
GB/T 50854-2024 removes "beam-and-slab": beams and slabs are coded and listed separately (combined application for solid slabs)
GB/T 50854-2024 has removed the "beam-and-slab" BOQ item (the 2013 edition's 010505001, by the sum of beam and slab volumes, repealed); beams list under "cast-in-place concrete beams" and ordinary floor slabs under "solid slabs", coded separately; at beam-slab intersections the slab counts to the beam's side face and the beam at full depth — the total is unchanged but the BOQ structure is split.
- ←
Applying TB/T 10823-2024 for double-wall steel cofferdam wall infill and bottom-seal concrete (QY-64) and the quantity boundary against pile-cap concrete
Double-wall steel cofferdam (floating steel caisson) wall infill and bottom-seal concrete uses item QY-64 (unit 10 m3, work content: concreting), belonging to cofferdam and island-building auxiliary works; the volume notes state the double-wall cofferdam sinking quota excludes wall-infill concrete, which must be booked separately. Wall infill (cofferdam cavity), bottom seal (below the cap underside), and the pile cap (above the seal top) occupy non-overlapping spaces; the cap volume is measured from the seal top — no double counting.
- ←
TB/T 10831-2024 railway housing works quota: classification of cast-in-place slabs into beam-slab / flat-slab / plain-slab and the pricing rule of monolithic beams and slabs (FY-503~516)
Per TB/T 10831-2024 "Railway works budget quota, Volume 10: housing works", volume notes "10. Quantity calculation rules" item (7): beam-slab = slab cast integrally with primary and secondary beams, "computed as the sum of beam and slab volumes" — with monolithic casting the beam volume is merged into the beam-slab item and the beam is not applied separately; flat-slab = slab bearing directly on columns (with drop panels), "computed as the sum of slab and drop-panel volumes"; plain slab = slab bearing on walls (or ring beams), "computed as the solid volume of the slab". Corresponding items: FY-503~507 beam-slab, FY-508~512 flat-slab (both in five thickness steps <=100/<=150/<=200/<=300/>300 mm, unit 10 m3), FY-513 plain slab, FY-514/515 sloped roof slabs (with beams / without beams), FY-516 arch slab.
- ←
Work-item BOQ listing for pools/chimneys in structures works: GB 50860-2013 Table A.1 pools (070101) and Table A.6 chimneys (070106) — codes, characteristics, and measurement boundary rules
Pools per GB 50860-2013 Appendix A Table A.1 (code 070101) have 5 BOQ items (floor slab/wall/roof slab/internal columns/partition walls); chimneys per Table A.6 (070106) have 4 items (foundation/shaft/insulation/lining); concrete parts measured in m3 by design dimensions, without deducting reinforcement, embedded parts, and holes <= 0.3 m2 each; table-note boundary rules (wall-base-beam boundary, splayed footing, column capital/pedestal merging, shaft-seat attribution) must be executed verbatim; reinforcement borrows GB 50854 items; formwork per 4.2.7 chooses once per bid section between merging into concrete unit prices and separate preliminary items (m2).