Steel cover plates for trenches (channel troughs): quota-system attribution of steel grating covers versus chequer-plate covers, line item selection, measurement-unit conventions, whether the main material is priced separately, separate billing against the trench body, and the distinction from manhole-cover items at inspection chambers

For steel cover plates, first identify the applicable system, then pick the line item: steel covers laid continuously along a trench follow the metal-structures basis - self-fabricated covers (steel included) are measured in t for fabrication plus erection, while proprietary grating covers are measured in m2 for erection only with the main material priced separately; cast iron or composite covers at inspection chamber openings are counted per piece or per set, and the two systems must not be cross-applied. The structures BOQ bills trench base slabs, walls and cover slabs separately (the cover is a stand-alone item); masonry trench line items carry only blockwork plus joint pointing, so the cover must be billed separately, whereas the all-in trench item measured by m already includes 'trench cover fabrication and erection' in its work content and must not be re-billed. Section-steel edge frames and angle stiffening frames of covers are merged into the cover quantity in t by theoretical mass, and grating apertures with a single-opening area of no more than 0.30 m2 are not deducted.

Applicable Codes

  • DB11/T 2382-2024 建设工程施工消耗量标准 App. D 市政工程(子目 D5-1-97、D5-1-132)
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(FY-733~FY-736 及册说明工程量计算规则)
  • TB/T 10833-2024 铁路工程预算定额 Vol. 12 机务车辆机械工程(JY-1653~JY-1658)
  • GB/T 50860-2024 构筑物工程工程量计算标准 Table B.5.1 井、沟盖板(编码 070205)
  • 天津市建筑工程工程量清单计价指引 DBD29-901-2025(表A.9 070109、表B.3 070203、表B.5 070205、表F.9 010609)
  • 天津市建筑工程预算基价 DBD29-101-2020
  • 天津市地铁及隧道工程工程量清单计价指引(2025)表A.6 路基排水(编码 080106)
  • 江苏省建筑与装饰工程消耗量(2026版)金属结构工程章节说明

Topic positioning

The two most common forms of steel cover plates for trenches (channel troughs) - chequer-plate covers (angle frame plus welded steel plate) and steel grating covers (grating panel plus edge frame) - and their attribution in the BOQ and budget quota systems, line item selection, measurement units, whether the main material is priced separately, the billing boundary against the trench body, and the dividing line against cast iron and composite covers at inspection chambers.

Core conclusions

1. First identify the system: two cover types, two quota systems

  1. Steel covers laid continuously along a trench -> metal-structures system: self-fabricated by mass in t; proprietary procurement by area in m2, erection only, main material priced separately.
  2. Covers set individually at inspection chamber openings (cast iron, composite and concrete covers and their seating rings) -> the manhole-cover product / manhole-cover installation system: counted per piece or per set, priced as finished products; the metal-structure tonnage items must not be applied.

2. Line item codes and measurement units compared (same name, different basis - read carefully)

  • Chequer-plate cover (angle frame plus plate, fabricated and welded on site): metal-structures 'fabrication plus erection', unit t; the material column of the item already includes the steel.
  • Municipal consumption standard DB11/T 2382-2024, Appendix D, item D5-1-97 'hot-dip galvanised steel cover plate, fabrication and erection': unit t; work content '1. hot-dip galvanised steel cover plate: fabrication, erection, etc.; 2. GRP cover plate: erection' (same table D.5.4-5 as GRP cover plate erection); consumption: comprehensive labour category II 7.5040 workdays/t, hot-dip galvanised section steel 1010.0000 kg/t, nylon grinding disc d100 9.6200%, AC welder 32 kV.A 15.4000 machine-shifts/t, other plant 2%. The material column contains about 1.01 t of steel per t -> a 'fabrication-erection integrated, main material included' basis; the steel plate or section steel main material must not be billed again.
  • Railway TB/T 10831-2024, Volume 10 Building Works, Section 6 Metal Structures (steel platforms and walkways): FY-733 fabrication, chequer plate (t); FY-734 fabrication, round steel (t); FY-735 fabrication, steel grating panel (t); FY-736 steel platform (walkway) erection (t) - fabrication and erection sit in two separate items, each measured in t.
  • Steel grating covers:
  • self-fabricated (grating panels procured, edge frame welded, assembled and welded on site) -> fabrication in t (same principle as FY-735 grating fabrication) plus erection in t (FY-736);
  • proprietary grating erected directly -> erection-only basis, by area in m2: DB11/T 2382-2024 D5-1-132 'hot-dip galvanised steel cover plate, fabrication and erection' likewise sits in table D.5.4-5 but its unit is m2, with consumption of only comprehensive labour category II 0.2580 workdays/m2 plus mild-steel electrodes 1.0200 kg/m2 plus other plant 2%, and no section-steel or grating material consumption -> an 'erection-led, main material separate' basis. When selecting an item, always check the unit and whether the main material is included; the name alone is not enough.
  • Concrete trench covers (basis comparison): structures BOQ 070109007 precast trench (trough) cover slab, in m3 (may combine 10-22 precast reinforced concrete cover slab erection and 10-23 precast reinforced concrete small-beam erection); 070109008 trench (trough) cover slab, in m3 (may combine 10-5 cast-in-place reinforced concrete trench roof); 070205001 manhole and trench cover slabs, per piece (may combine 4-107 precast concrete trench cover fabrication, 4-251 to 252 precast concrete small-member erection, 4-253/4-254 member transport).
  • Manhole covers (inspection chambers): metal manhole (trench) covers and seating rings, BOQ item 010609004 per set (combining 10-24 cast iron manhole cover erection with seating ring); structures 070205001 manhole and trench cover slabs per piece; railway TB/T 10833-2024 Volume 12 JY-1657 cast iron manhole cover and ring erection (10 sets) and JY-1658 embossed steel plate trench cover fabrication and erection (10 m2) - showing that area-measured proprietary steel cover items also exist in the municipal and depot machinery volumes.

3. Billing boundary between covers and the trench body

  1. Concrete trenches (structures trench/trough code 070109): base slab 070109001 (m3, 10-3 cast-in-place reinforced concrete trench base), wall slab 070109004 (m3, 10-4 cast-in-place reinforced concrete trench wall), cover slab 070109007/070109008 (m3) billed separately - the cover is a stand-alone item, not merged into the wall; the triangular volume where wall and base intersect is merged into the wall.
  2. Masonry trenches (070203001 trench (trough)): work content only '1. blockwork 2. joint pointing' (combining 3-89 to 91 shale standard-brick trenches and 3-108 to 109 wall joint pointing), cover slabs NOT included - the cover must be billed separately.
  3. Manhole and trench cover slabs (070205, same coding as GB/T 50860-2024 table B.5.1): per piece, work content 'cover fabrication, transport, erection'; where no ready combined quota item exists for steel covers, the pricing guide says items 'may be self-combined and supplemented', and pricing falls back to metal-structure t items or area-measured items.
  4. The all-in trench item is the exception: Metro and Tunnels, subgrade drainage, table A.6, 080106001 concrete trench and 080106002 masonry trench (measured by m) already include 'trench cover fabrication and erection' in their work content, and the item description states the cover material and specification - what is already included must not be re-billed as a cover, or the works are double counted.

4. Merging edge frames and stiffening frames into the cover mass

  • Railway TB/T 10831-2024 Volume 10 volume notes, 'IV. Measurement rules (1) fabrication, erection and transport of metal members': member mass is the design dimensions multiplied by the theoretical mass; holes of an individual area of no more than 0.30 m2 are not deducted, and welds, rivets and bolts add no mass; steel platform quantities include the mass of platform columns, beams, plates, diagonal bracing and platform steel railing; steel staircase quantities include the landing, stair beams and treads, with attached steel handrails and railing taken into the staircase.
  • Accordingly: the section-steel edge frames, angle stiffening frames and stiffeners of a cover are constituent parts of the member and are merged into the cover quantity in t by theoretical mass, not billed separately; grating apertures (single opening of no more than 0.30 m2) are not deducted.
  • Jiangsu metal-structures chapter notes: fabrication and erection of gratings over inlet intercepting trenches welded from angles and rounds follow the 'steel cover plate fabrication and erection' item at the design mass; sundry steel members are small stand-alone members not listed in the chapter, not attached to a primary steel member, of an individual mass within 50 kg - only members meeting that definition take the sundry-member item.
  • The same Jiangsu chapter notes also state: 'fabrication and erection integrated' steel cover items include erection but not off-site transport; off-site transport runs under the member transport items (the steel-member combinations also carry 'metal structure member transport (class I / class II)' items).

5. Distinction from cast iron and composite covers at inspection chambers

  • Criteria: position (whether set at an inspection chamber or rainwater inlet opening, whether furnished with a seating ring) plus product character. Covers at chamber openings are finished products counted per piece or per set, taking cast-iron-cover erection (with seating ring) type items with the main material at product price; steel covers laid continuously along the trench are measured as metal structures.
  • Pricing guide general notes (clauses 7 and 8): 'combinable budget base-price items' may be adjusted to the works; items marked 'may be self-combined and supplemented' may be supplemented in light of the works; for items not covered by the national measurement standards, the coding, naming, item description, unit of measurement and measurement rule shall follow the corresponding national-standard item.

Applicability boundaries

  • The measurement unit, work content and consumption of each item hold only within its own quota volume; they must not be mixed across volumes or regions. Under the one name 'hot-dip galvanised steel cover plate' the t item (D5-1-97) and the m2 item (D5-1-132) coexist - always check the unit and whether the main material is included before selecting.
  • 'Single opening of no more than 0.30 m2 not deducted' is the quota measurement rule of the railway building works volume; the BOQ basis has its own aperture-deduction threshold - apply the rule of the volume you rely on.
  • 'Main material separate' for proprietary grating presupposes that the item's material column shows no grating or section-steel consumption; if a fabrication-erection integrated item with steel included is applied, pricing the main material again is double counting.
  • The all-in trench (measured by m, work content including covers) and the split form (structures trench by m3, covers billed separately) are two BOQ bases; judge by the BOQ system chosen in the contract and never cross them.
  • This card gives no quota base prices or market rates; prices are taken from local base prices and published price information at the preparation date.

Further reading

  • DB11/T 2382-2024 Consumption Standard for Construction Works, Appendix D Municipal Works, table D.5.4-5 (items D5-1-97 by t and D5-1-132 by m2)
  • TB/T 10831-2024 Railway Works Budget Quota, Volume 10 Building Works, Section 6 Metal Structures (FY-733 to FY-736); volume notes 'IV. Measurement rules (1) fabrication, erection and transport of metal members', clauses 1 to 9
  • TB/T 10833-2024 Railway Works Budget Quota, Volume 12 Depot and Rolling Stock Machinery Works, Chapter 8 Section 1, III. Fabrication and erection of trench and manhole covers (JY-1653 to JY-1658)
  • GB/T 50860-2024 Measurement Standard for Structures Works, Appendix B table B.5.1 manhole and trench cover slabs (code 070205)
  • Tianjin Building Works BOQ Pricing Guide DBD29-901-2025: table A.9 trench (trough) 070109, table B.3 trench (trough) 070203, table B.5 manhole and trench cover slabs 070205, table F.9 metal products 010609; companion Tianjin Building Works Budget Base Prices DBD29-101-2020 (10-3 / 10-4 / 10-5, 10-22 to 10-24, 4-107, 4-251 to 252, 4-253 / 4-254)
  • Tianjin Metro and Tunnel Works BOQ Pricing Guide (2025), table A.6 subgrade drainage (code 080106)
  • Jiangsu Building and Decoration Works Consumption Standard (2026 edition), metal-structures chapter notes (fabrication-erection integrated steel cover items include erection but exclude off-site transport; gratings follow the steel cover item; sundry steel members defined at 50 kg)