Recasting the concrete volume increment and the formwork contact-area increment after section-size changes to concrete members, why the two move out of step (volume is quadratic in size, formwork linear), the layered order of computation for linked rebar costs, and the tie-in with the 15% quantity-deviation clauses
Concrete is measured by design volume (m3) and formwork by contact area with the concrete (m2) - two independent BOQ items and two geometric functions, so they cannot move in step. With length unchanged, the concrete increment dV = (A_c1 - A_c0) x L; the formwork increment dA = (C1 - C0) x L + (A_b1 - A_b0). The section area b.h is homogeneous of degree 2 in the sizes while the section perimeter 2(b+h) is degree 1: scale the section by k on both sides and volume grows by k^2 but formwork by k - a column with both sides enlarged 5% gains about 10.25% volume but only 5% formwork. After the change, measurement = original BOQ quantity plus or minus the increment; whether the quantity change triggers rate renegotiation follows the 15% bands of GB/T 50500-2024 clauses 8.9.1/8.9.2.
Applicable Codes
- GB/T 50854-2024 · Standard for measurement of building construction and fitting out works App. E Table E.5.1、E.7.1
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第7.2.1、7.4.1~7.4.4、8.2.1、8.9.1、8.9.2条
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第4.6节、第5.4节、第5.10节及Table 5.10.6
- 江苏省建筑与装饰工程消耗量 模板工程量计算说明
- 湖南市政工程消耗量标准 模板工程量计算说明
Scope and purpose
After design variation changes the section sizes of concrete members (b, h, slab thickness t): how to recast the concrete volume and the formwork contact area under two independent BOQ bases, why the two increments necessarily diverge, in what order linked costs such as rebar are computed, and how the varied quantities tie into the original BOQ quantities and the 15% boundary clauses.
Core conclusions
1. First lock the two measurement bases
- Concrete is volume (m3). GB/T 50854-2024 Appendix E.7.1, general notes on cast-in-place concrete members, item 2: 'cast reinforced concrete members make no deduction for the volume occupied by rebar, bolts, embedded plates and prestressing ducts, but the volume of structural steel forming rigid skeletons shall be deducted.' Member-level rules (DB11/T 2382-2024 clause 5.4.4): columns measured by the design section area multiplied by the column height, the height running from the upper surface of the column base or floor slab to the column top or the upper surface of a floor slab, corbels attached to the column merged into the column volume; beams by the design section multiplied by length, beams between columns measured over the net length between column faces; slabs by the design area multiplied by thickness, with no deduction for lightweight partitions, wall piers, columns and holes up to 0.30 m2.
- Formwork is contact area (m2). GB/T 50854-2024 table E.5.1 (concrete formwork, code 010505) is an independent BOQ item. DB11/T 2382-2024 clause 5.10.4: 'apart from staircases, formwork is measured on the contact area between the formwork and the concrete as shown on the design, with no deduction for the overlap at column-beam and beam-beam connections nor for holes up to 0.30 m2'; column formwork is the design column perimeter multiplied by the column height, the height running from the upper surface of the column base to the upper surface of the floor slab above, corbel formwork merged into the column; beams on the developed area of the design side and soffit faces. The Jiangsu building and decoration consumption standard states that 'overlapping parts at member connections are not measured as formwork'; the Hunan municipal consumption standard matches: 'cast concrete formwork is measured on the area of formwork in contact with the concrete. Single holes up to 0.3 m2 in concrete walls, columns, slabs, caisson walls and pool walls are not deducted, and the hole side walls are not measured either; single holes above 0.3 m2 are deducted, and the hole side-wall formwork is added into the formwork quantity.'
- Conclusion: concrete (01050 series, m3) and formwork (010505 series, m2) are two independent BOQ items with two geometric functions - the lack of synchronism is the normal outcome of the measurement bases, not an arithmetic error.
2. Concrete volume increment formula
Exact: dV = A_c1 x L1 - A_c0 x L0; with length unchanged (L1 = L0 = L) it reduces to dV = (A_c1 - A_c0) x L.
| Variable | Definition | Unit |
|---|---|---|
| A_c0 / A_c1 | section area before / after the change (not surface area) | m2 |
| L | computed length of the member (per the measurement rule's 'measured up to', not the axis length) | m |
| dV | volume increment, positive for increase, negative for decrease | m3 |
Member forms: rectangular column dV = (b1.h1 - b0.h0) x H (H the column height); rectangular beam dV = (b1.h1 - b0.h0) x Lnet (secondary beams measured to the faces of primary beams); slab dV = (t1 - t0) x Sproj, the section change appearing as a thickness change. Red line: the increment is geometric only - the concrete quota consumption must not be adjusted because the section grew; nor is any deduction made for rebar, embedded items, bolts or prestressing ducts, only for the structural steel of rigid skeletons.
3. Formwork area increment formula
General: dA = (C1 - C0) x L + (A_b1 - A_b0)
| Variable | Definition | Unit |
|---|---|---|
| C0 / C1 | developed section width before / after the change (perimeter-type, first-order), faces not counted as formwork already excluded | m |
| L | computed height / length of side formwork (matching the 'measured up to' rules for column height and beam net length) | m |
| A_b0 / A_b1 | soffit formwork (horizontal projection) contact area before / after the change | m2 |
| dA | formwork contact-area increment | m2 |
Member forms:
- Rectangular column (four sides): dA = 2[(b1+h1) - (b0+h0)] x H
- Rectangular beam (soffit plus two sides): dA = (b1-b0) x Lnet + 2(h1-h0) x Lnet
- Slab: the soffit projection does not change with thickness, the A_b term is 0, only the perimeter side forms dA = (t1-t0) x P (P the exposed perimeter of the slab edge)
- Wall (both faces): dA = 2(t1-t0) x H x L
4. Why they diverge: volume is quadratic in size, formwork area linear
- Mathematics: the section area A_c = b.h is homogeneous of degree 2 in the sizes; the section perimeter C = 2(b+h) (beams b+2h) is degree 1. Scale both sides of the section by k - volume x k^2, formwork (perimeter x length) x k.
- Rule-of-thumb statements (directly quotable): both sides of a column section +5% (k=1.05) - volume +1.05^2 - 1 = 10.25% (about 10%), formwork only +5%; one side +5% - volume +5%, column formwork +2.5%. Both sides of a beam section +5% - volume about +10.3%, formwork (b+2h basis) +5%. Slab thickness +5% - volume +5%, formwork barely moves (soffit projection unchanged, only the edge side forms grow with thickness, on the order of 0.2%).
- Measurement-basis layer: soffit formwork is measured on horizontal projection, independent of member thickness/height; only side forms follow the section sizes, while the whole concrete volume follows them. On top of that, the formwork rules 'no deduction for column-beam overlap or holes up to 0.30 m2' leave a small gap between actual contact area and 'perimeter x length'.
5. Layered order of computation for linked costs
(1) Fix the variation boundary: the variation instruction issued or confirmed by the employer plus the actual construction drawings; (2) compute the concrete volume increment (linking with the original BOQ quantity by plus/minus); (3) compute the formwork contact-area increment by its independent geometric function; (4) rebar by mass from design-drawn dimensions on the post-change drawings (DB11/T 2382-2024 clause 4.6.9: cast-in-place rebar, mesh and cages are all measured by design-drawn mass; laps per drawing notes or code requirements, and where the drawings are silent, up to d10 one lap per 12m length, beyond d10 one lap per 9m length, cast reinforced concrete walls lapped per storey height) - estimating rebar from reinforcement ratios is for estimates and preliminary estimates only (approx. dG = rho x dA_c x L x 7850 kg/m3); settlement must not back-calculate from it but recompute from drawings; (5) preliminaries changes follow GB/T 50500-2024 clause 7.4.4: new temporary works, plant machine-shifts and the like are measured per the employer-approved implementation plan prepared specifically for the variation or per the actual content, while the extra costs of prolonged use of existing preliminaries and supervisory staff caused by variations off the critical path need not be measured; (6) only then fix the rate (below).
6. Measurement of variations as original quantity plus or minus increments, and the 15% tie-in
- GB/T 50500-2024 clause 7.4.2: variations under unit-rate contracts recompute the divisional and sub-divisional BOQ items and quantities from the variation instruction issued or confirmed by the employer and the actual construction drawings, and compare them against the BOQ items and quantities after BOQ errors have been corrected, to fix the varied items and their quantities.
- Clause 7.4.1: under both unit-rate and lump-sum contracts, comparing the variation instruction and the actual construction drawings with the contract drawings, the differing divisional and sub-divisional items are the variation items; differences between contract drawings and the contract BOQ are BOQ errors - corrected under unit-rate contracts, not adjusted under lump-sum contracts.
- Clause 8.2.1: where BOQ errors move a BOQ quantity by up to 15% of the quantity in the contract BOQ for the item (15% inclusive), clause 8.9.1 applies; beyond 15% (exclusive), clause 8.9.2 adjusts the contract price.
- Clause 8.9.1: with item additions/deletions or quantity changes up to 15% (inclusive), the all-in unit rate is fixed by the 'item description x construction condition' matrix - the same description under the same conditions takes the corresponding contract rate; a similar description under the same conditions, or the same description under similar conditions, takes the converted and adjusted rate of similar items' contract rates; different descriptions or conditions mean negotiating a market-reasonable rate with reference to similar items' pricing rules and the bid level.
- Clause 8.9.2: beyond 15% (exclusive), for added items and quantities the contract rate and the new rates are reasonably reduced to reflect labour and material purchase discounts from the added volume; for reductions they are reasonably increased to reflect lost discounts.
- Summary: post-variation measurement = original BOQ quantity plus or minus the increment (dV, dA by the formulas above); 'how the quantity is computed' and 'whether the rate is renegotiated' are two different questions, the latter banded by the 15% threshold.
Applicability limits
- dV = (A1 - A0) x L is exact only with member length unchanged; if length changes too, the exact form A1 x L1 - A0 x L0 must be used - it must not be split into 'area difference x length' plus 'original area x length difference' (a cross term exists).
- The formulas are on the building and decoration works basis; heritage-style buildings have their own rules: formwork for ornamental brackets (queti), corner clouds, hanging columns, ornament blocks and members up to 0.05 m3 each follows the heritage-component and other heritage-member items; where design dimensions are insufficient, convert from the formwork contact-area reference table (purlin three-piece sets 16.460 m2/m3, rafter-and-boarding and upturned flying boards 29.150 m2/m3, pavilion roofing 18.000 m2/m3, heritage components and other heritage members 21.930 m2/m3).
- Formwork support height increments do not enter the contact-area increment: heights up to 3.60m are priced without height distinction; the part above 3.60m is priced per extra 1m and measured on the whole excess area, any excess under 1m taking the per-extra-1m item.
- Consumption (quota labour, materials, plant) is not adjusted for section changes - adjust quantity only, not consumption; BOQ errors under lump-sum contracts are not adjusted.
- Fair-face, coloured and waterproof concrete affect item descriptions and all-in unit rates only, not the measurement geometry.
Further reading
- GB/T 50854-2024, quantity take-off standard for building and decoration works, Appendix E: table E.5.1 concrete formwork (code 010505), E.7.1 general notes for cast-in-place concrete members
- DB11/T 2382-2024, Consumption Standard for Construction Works, section 4.6 concrete and reinforced concrete works (4.6.7~4.6.9), section 5.4 concrete in heritage-style works (5.4.4~5.4.6), section 5.10 preliminaries (5.10.1~5.10.6, table 5.10.6 formwork contact-area reference table for concrete)
- Jiangsu building and decoration consumption standard, formwork measurement notes 1~19 (contact-area basis, no deduction for overlaps, exposed width of constructional columns, 0.3 m2 hole rule for walls and slabs)
- Hunan municipal consumption standard, formwork measurement notes (cast work by contact area, 0.3 m2 hole deduction and hole side-wall addition, precast floor moulds)
- GB/T 50500-2024, the China national pricing standard for BOQ: clause 7.2.1 (remeasurement under unit-rate contracts), 7.4.1~7.4.4 (variation measurement), 8.2.1 (BOQ errors), 8.9.1~8.9.2 (15% boundary and all-in unit rate adjustment)
Keywords
- 截面尺寸变化
- 混凝土体积增量
- 模板接触面积增量
- 模板工程量
- 截面周长
- 工程量偏差15%
- 工程变更计量
- 钢筋量联动