Formwork measurement rules: contact-area basis, overlap deduction and the 0.3 m² opening threshold, special algorithms for each element type, and BOQ item characterization
Cast-in-place and precast concrete formwork is measured in m² of contact area between the concrete and the formwork (called formwork erection area in water works), with overlapping parts at connections deducted; openings in walls/slabs >0.3 m² are deducted with their reveals added, ≤0.3 m² not deducted; monolithic stairs by horizontal projected area, small elements by projected area, special-shaped precast elements by volume; precast excludes ground moulds, core moulds for hollow slab beams are included in the item, and non-removable box-girder inner forms add 0.03 m³ per m²; constructional columns count only exposed faces = (column width + toothing width) × height; BOQ characterization adds surface/customization requirements, formwork types are straight/inclined/curved/arched, and aprons/ramps are listed under blinding formwork.
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
- SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
- SJG 84-2020 市政维修工程消耗量标准
- SJG 181.3-2024 市政工程消耗量标准 Vol. 3 隧道工程
- SJG 181.5-2024 市政工程消耗量标准 Vol. 5 水处理工程
- GB 50501-2007 水利工程工程量清单计价规范
- DB11/T 638-2016 房屋修缮工程工程量计算规范
Topic Positioning
General rules of formwork quantity measurement: the contact-area basis, overlap deduction, the 0.3 m² opening threshold, and algorithms for special elements.
Core Conclusions
- Formwork is measured in m² of contact area between concrete and formwork (formwork erection area in water works); overlapping parts at connections are deducted (walls to column faces/beam soffits, slabs to wall sides); faces not in contact with concrete are not counted.
- Single openings ≤0.3 m² in walls/slabs are not deducted and their reveals not added; >0.3 m² are deducted with the reveals included.
- Monolithic stairs by horizontal projected area (where no landing beam exists, bounded by the last tread edge +300 mm); small elements by plan projected area; special-shaped precast elements etc. by volume in m³.
- Precast non-prestressed elements exclude ground moulds; core moulds of hollow slab beams are included in the item; where box-girder inner forms cannot be removed, add 0.03 m³ per m².
- Constructional columns count only exposed faces = (column width + toothing width) × height.
- Fair-faced/patterned finishes add "concrete surface requirements", customization adds "formwork customization requirements"; formwork types are straight, inclined (≥20%), curved (≤12 m), and arched; aprons and ramps are listed under blinding formwork.
Applicable Boundaries
Applies to measurement and BOQ preparation for cast-in-place and precast formwork (building/municipal/water/renovation standards share the same basis). The 0.3 m² threshold addresses reserved openings in walls and slabs; openings in columns and beams and provincial detail differences follow the local quota.
Further Reading
GB/T 50854-2024 Appendix E.7.8; SJG 181.2-2024 Clause 8.2.1; GB 50501-2007 Appendix A.10.2; DB11/T 638-2016 Table A.4.6.