Preventing double counting of decoration quantities: deduction and inclusion rules for floors, wall/column faces, and ceilings

In decoration quantity takeoff, first draw the interfaces, then apply the "deduct/include" rules so each surface is computed on its own: openings are uniformly deducted at the single-opening 0.30 m2 threshold; the side faces of door/window openings are not added; the side faces of attached columns/beams/piers are merged into the wall face; for beamed ceilings the beam sides merge into the ceiling; plaster on the soffit of slab staircases at horizontal projection x 1.15, zigzag x 1.37; ceiling furring by the clear area between main walls, the finish layer by the room net area minus freestanding columns — the furring and finish layers differ in caliber and must not be mixed. BOQ caliber per GB/T 50854-2024 Appendices L/M/N; quota caliber per TB/T 10831-2024 Volume 10 Building Works.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. L/M/N
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程

Topic Positioning

This card covers the "deduct and include" rules of quantity takeoff for the three major decoration interfaces of buildings — floors, wall/column faces, and ceilings — for preventing double counting and omissions when preparing BOQs/budgets, compatible with both the national standard and the railway industry quota calibers.

Core Conclusions

Unified threshold: openings are uniformly delimited by single-opening area 0.30 m2 — larger openings are deducted, smaller or equal are not (the same for floors, wall faces, and ceiling finish layers). Floors: room net area deducting channels, structures protruding from the floor, and equipment foundations, without deducting columns/piers, partition walls, attached chimneys, air ducts, and openings <=0.30 m2; stone patterns counted by the maximum peripheral rectangle, the paving area deducting the pattern rectangle, accents counted by count without deducting paving area. Wall faces: interior plaster deducts door/window openings and openings >0.30 m2; the side faces of door/window openings are not added; the sides of attached columns merge into the wall face; when the dado and wall plaster are of the same type they are computed together; with a suspended ceiling the interior plaster height is measured to the ceiling soffit plus 100 mm; column plaster at structural section perimeter x height. Ceilings: plaster by developed area, the beam sides of beamed ceilings merging in; soffit plaster of slab staircases at horizontal projection x 1.15, zigzag x 1.37; furring by the clear area between main walls (no deduction for columns/piers/pipes), the finish layer by room net area (deducting freestanding columns, curtain boxes connected to the ceiling, openings >0.30 m2, and recessed ceiling light troughs) — the two differ in deduction caliber. Stair finish horizontal projection includes treads, landings, and stair wells <=500 mm; where connected to the floor, measured to the inner side of the stair landing beam; without a landing beam, to the edge of the top tread plus 300 mm; steps likewise.

Applicable Boundaries

Applies to decoration quantity takeoff and BOQ/quota preparation for buildings (including railway buildings). Plaster, tiling, and curtain walls on irregular wall faces (arcs, zigzags) take labor and machinery x 1.15. Not applicable to structures, tunnels, bridges and other specialist works; GB/T 50854 BOQ caliber differs from local/industry quotas in details such as "whether door opening mouths merge in" — the pricing basis executed by the project prevails; the 0.30 m2 threshold applies only to decoration interfaces; formwork and other works have their own rules.

Further Reading

BOQ caliber: GB/T 50854-2024 Standard for Measurement of Building and Decoration Works Quantities, Appendix L (L.1.1 monolithic finishes and screeds 011101, L.2.1 stone and block paving 011102), Appendix M (M.1.1 wall/column plaster 011201), Appendix N (N.1.1 ceiling plaster 011301). Quota caliber: TB/T 10831-2024 Railway Engineering Budget Quota, Volume 10, Building Works — volume explanation quantity calculation rules for floors, wall/column faces, ceilings, and doors/windows (including curtain wall specifications, door/window hardware scope and other supporting notes).