Ceiling (suspended ceiling) quantity calculation: four-layer rules for plastering/keels/surface courses/other ceilings and BOQ item listing (GB/T 50854-2024 Appendix N)
Ceiling quantities are calculated in four layers — ceiling plastering -> keels -> surface course -> other ceilings — each with a different caliber that must not be mixed: plastering by developed area (stair soffits x 1.15 / x 1.37), keels by net clear area between main walls (arches and domes by horizontal projection, light troughs by number, light strips by length), surface course by room net area (deducting independent columns, curtain boxes, holes above 0.3 sqm, and recessed light troughs), art-form ceilings by developed area. BOQ codes: ceiling plastering 011301, suspended ceilings 011302, other ceiling decorations 011303; suspended ceilings are divided into flat/drop (height difference <= 400 mm and <= 3 levels) and artistic forms (height difference > 400 mm or > 3 levels, curved or arched).
Applicable Codes
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. N
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准 Vol. 2
Topic Positioning
Layered quantity calculation and BOQ item-listing rules for ceilings (suspended ceilings) (building decoration takeoff).
Core Conclusions
Ceilings are calculated in four layers — plastering -> keel -> surface course -> other ceilings — each with a different caliber, not to be mixed. (1) Plastering: by design-drawn developed area, not deducting partition walls, pilasters, columns, attached chimneys, inspection openings, and pipes; for beam-covered ceilings the beam sides merge; plank stair soffits x 1.15, saw-tooth stair soffits x 1.37. (2) Keels: by net clear area between main walls, not deducting partition walls, inspection openings, columns, pilasters, and pipes; arches and domes by horizontal projection; high-low steps merged; vertical closing boards by vertical projection; additional keels for light troughs by number, light strips by length. (3) Surface course: by room net area, deducting independent columns, curtain boxes, holes above 0.3 sqm, and recessed light troughs; art forms by developed area. (4) Others: grid suspended ceilings by horizontal projection, glass skylight ceilings by developed area, caisson light strips by outer-edge-line length. BOQ codes: 011301 ceiling plastering, 011302 suspended ceilings, 011303 other ceiling decorations.
Applicable Boundaries
A surface course at the same level is a flat ceiling; a height difference <= 400 mm with <= 3 drop levels is a drop ceiling; a height difference > 400 mm or > 3 drop levels, curved or arched forms, etc. are artistic ceilings. Cutting for equipment installation inside the ceiling is included in the work content; independent beams without ceilings are listed as ceiling plastering. Local quota details differ — the local quota governs.
Further Reading
GB/T 50854-2024 Appendix N (N.1.1 ceiling plastering, N.2.1 suspended ceilings, N.3.1 other ceiling decorations, N.4.1-N.4.6 type division); TB/T 10831-2024 Volume 10 volume notes, ceiling works section; SJG 111.2-2022 Volume 2, ceiling section.