Beijing DB11/T 2382-2024 ceiling works quantity and consumption calibers: differences vs national GB/T 50854-2024 and railway TB/T 10831-2024 (anti-mixing)

Beijing DB11/T 2382-2024 Section 4.14 differs from national/railway calibers — mixing them guarantees errors: (1) ceiling plastering: Beijing by horizontal projection (no deduction of walls <= 120 mm thick, pilasters, columns, attached chimneys, inspection openings, pipes), while GB/T 50854-2024 Appendix N and TB/T 10831-2024 use developed area; (2) slab-stair soffit plastering: Beijing by sloped area of the stair (incl. flights, landings, landing beams, connecting beams, and stairwells <= 500 mm), national/railway by horizontal projection x 1.15 (sawtooth x 1.37); (3) suspended ceilings: Beijing — runners by horizontal projection, base and finish both by developed area (three calibers); railway — runners by net area between main walls, finish by room net area (deducting isolated columns, ceiling-linked cove cornices, holes > 0.30 m2, recessed light troughs); (4) interior wall plastering with suspended ceiling: Beijing repair caliber DB11/T 638-2016 Table A.13.1 note "the part plastered above the suspended ceiling is considered in the all-in unit rate"; railway — to the ceiling soffit plus 100 mm.

Applicable Codes

  • DB11/T 2382-2024 建设工程施工消耗量标准 第4.14节 天棚工程
  • DB11/T 638-2016 房屋修缮工程工程量计算规范 Table A.13.1
  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. L/M/N
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 册说明

Topic Positioning

The construction consumption rules and quantity calibers of Section 4.14 "Ceiling works" of Beijing's local DB11/T 2382-2024, and the differences vs national GB/T 50854-2024 and railway TB/T 10831-2024 — govern when compiling Beijing tender price ceilings/tender consumption; prevents cross-standard mixing causing double counting or omission.

Core Conclusions

DB11/T 2382-2024 Section 4.14 ceiling works (key clauses):

  1. Consumption setting rules: 4.14.1 precast-slab soffit plastering shall include joint pointing; 4.14.2 soffit plastering of eaves, canopies, balconies, and stairs may follow ceiling plastering items; 4.14.3 where beam and slab soffits use different materials, set and measure the items separately; 4.14.4 except open-grid, cylinder, and suspended decorative ceilings, suspended ceilings shall be set and measured separately for runners and finishes; wood runners include fire-retardant coating; runner hanger starter lengths are preferably synthesized within 0.80 m, beyond which per each added 0.10 m; finishes preferably single-layer; two or more layers execute single-layer items with labour consumption x 0.85; aluminum panels with upturned edges preferably measured with 25 mm edges. 4.14.7 cove cornices of the same material as the ceiling finish may follow ceiling items, base and finish labour x 1.15. 4.14.8 light strips set by added runners and finishes; air-outlet consumption includes ceiling cutting and added runners, preferably excluding outlet panels; cutting light/maintenance holes in gypsum and wood finishes preferably included; in metal, glass, and stone finishes preferably excluded.
  2. Quantity take-off (4.14.11-4.14.14): ceiling plastering by horizontal projection per design, without deducting walls <= 120 mm thick, pilasters, columns, attached chimneys, inspection openings, and pipes; beam-side plastering of beam ceilings merges into ceiling area; slab-stair soffit plastering by the stair's sloped area (incl. flights, landings, landing and connecting beams, stairwells <= 500 mm), without beam connection the stair edge counts to the top tread plus 300 mm, and equal-width platform parts of single-run stairs merge in. Ceiling runners by horizontal projection, no deduction of walls/pilasters/columns <= 120 mm or holes <= 0.30 m2 each; extra-long hangers by the horizontal projection of the exceeding height; base and finish both by developed area per design; open-grid, cylinder, suspended, and assembled ceilings by horizontal projection (same non-deductions). Light-strip added runners by length; light-strip glass finishes by frame periphery; staggered-level metal added runners by length per design; air-outlet/maintenance-hole ceiling cuts by count; canopy-hung finishes by horizontal projection.
  3. Key differences vs national/railway (anti-mixing):
  • Ceiling plastering: Beijing horizontal projection; GB/T 50854-2024 Appendix N and TB/T 10831-2024 developed area (both without deducting partition walls, pilasters, columns, attached chimneys, inspection openings, pipes; beam sides merge — same deduction objects, different measurement face).
  • Slab-stair soffit: Beijing sloped area; national/railway horizontal projection x 1.15 (slab) / 1.37 (sawtooth).
  • Suspended ceilings: Beijing — runners horizontal projection, base and finish developed area; railway — runners by net area between main walls (folded, dropped, curved, and light-trough areas not developed), finish by room net area (deduct isolated columns, ceiling-linked cove cornices, holes > 0.30 m2, and recessed light troughs) — two calibers for runners and finish; neither may mix with plastering.
  • Interior wall plastering with suspended ceiling: Beijing repair caliber DB11/T 638-2016 Table A.13.1 note "the part above the suspended ceiling is considered in the all-in unit rate"; railway TB/T 10831-2024 — height to the ceiling soffit plus 100 mm — different treatments; apply per the governing basis.

Applicable Boundaries

Applies to Beijing building and decoration consumption measurement (tender price ceilings, tenders, consumption review) per DB11/T 2382-2024. Note: GB/T 50854-2024 is the BOQ measurement standard (list quantities); local consumption standards are quota norms calibers (quota quantities) — dual-track, differences arising from rules, not errors; railway works use TB/T 10831-2024, not Beijing calibers; cross-province compilation follows the project location's current quota norms. Wood-runner fire coating and finish labour-reduction rules apply only to the Beijing standard.

Further Reading

DB11/T 2382-2024 Section 4.14 (4.14.1-4.14.14; cf. 4.13 plastering, 4.15 putty/paint, 4.16 finished trim); DB11/T 638-2016 Table A.13.1 wall plastering note; national: GB/T 50854-2024 Appendix N (N.1.1 ceiling plastering 011301) and Appendix M (M.1.1 wall/column plastering 011201); railway: TB/T 10831-2024 Volume 10 (building works), Part 3 ceilings and Part 2 wall/column faces.