Floor quantity calculation rules: layered calibers and deduction/merge rules for cushion courses, surface courses, skirting, stairs, and steps

Floors are calculated by structural layer: cushion courses by net area between main walls x design thickness in m3; monolithic surface courses and leveling courses by net area between main walls in sqm (door openings not added); tiled surface courses by the laid area (openings merged); skirting by linear meters; stairs and steps by horizontal projected area (stair wells <= 500 mm not deducted; without landing beams, measured to the edge of the top tread plus 300 mm). BOQ items are listed per the tables of GB/T 50854-2024 Appendix L.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. L
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准 Vol. 2

Topic Positioning

Floor quantities are calculated by structural layer: cushion courses, monolithic surface courses, tiled surface courses, skirting, stairs and steps — each layer has a different caliber and they must not be mixed.

Core Conclusions

Cushion courses by net area between main walls x design thickness in m3; monolithic surface courses and leveling courses by net area between main walls in sqm — both deduct structures and equipment foundations protruding from the floor, do not deduct columns, pilasters, partition walls, or holes <= 0.3 sqm, and do not add door openings and void rings. Tiled surface courses by the laid (actually paved) area, deducting positions without a surface course and merging openings — the opposite of monolithic courses. Skirting by linear meters (mortar-type: openings not deducted; tile-type: door openings deducted with side walls added). Stairs by horizontal projected area including treads, landings, and stair wells <= 500 mm; where connected to floors, measured to the inner side of the landing beam; without a landing beam, to the tread edge plus 300 mm; steps likewise plus 300 mm. BOQ items are listed per the tables of GB/T 50854-2024 Appendix L (011101/011105/011106).

Applicable Boundaries

Applies to floor quantity takeoff for building works; quota calibers vary by region (Jiangsu/Shaanxi quotas, SJG 111.2-2022, TB/T 10831-2024) — the current local quota governs; road structural layers, walls, and ceilings are not covered.

Further Reading

GB/T 50854-2024 Appendix L (L.1.1/L.5.1/L.6.1/L.10.3/L.10.8); quota calibers: TB/T 10831-2024 Volume 10, SJG 111.2-2022 Volume 2, and the current consumption quotas of the provinces.