Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-01

Routing cast-in-situ and precast terrazzo floors under the quota: monolithic finishes (cast, ground and waxed on site - railway FY-1209 to 1213, Beijing A-11-24 to A-11-27) versus tile (precast slab) finishes laid on a bed with the main material swapped - banding and adjustment rules

Terrazzo routing ignores the word "terrazzo" and reads the construction form: site-mixed casting with grinding and waxing is a MONOLITHIC finish taking the terrazzo monolithic items (TB/T 10831-2024 Volume 10 FY-1209 to FY-1213: 15 mm with divider strips / 15 mm with strips, colour-split / mirror 20 mm with strips / mirror 20 mm with strips, colour-split / per 1 mm up or down, all per 10 m2); factory-precast slabs laid on a bed are a TILE finish - GB 50209-2010 clause 6.4.1 "precast slab finishes of cement concrete, terrazzo and artificial stone slabs shall be laid on a bed" - taking tile items with the main material swapped to precast terrazzo slabs (mainstream quotas set no precast terrazzo floor item). Banding follows divider material and grade: ordinary terrazzo takes glass strips, artistic (coloured) takes brass strips; coloured / artistic and mirror stand as separate items, never coefficient-converted.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • DB11/T 2382-2024 建设工程施工消耗量标准
  • GB 50209-2010 建筑地面工程施工质量验收规范 第6.4.1条
  • GB 50037-2013 建筑地面设计规范

Topic Positioning

Routing, banding and adjustment of terrazzo floors (cast and precast) under budget quotas - for floor decoration pricing and review; railway basis per TB/T 10831-2024 Volume 10 chapter 2 section 1 (floors), with like banding from local standards.

Core Conclusions

1. First test: route by construction form, not material name

  • Cast-in-situ terrazzo = cement-aggregate paste mixed, laid, ground and waxed on site - a monolithic finish, under the floor chapter's monolithic terrazzo items.
  • Precast terrazzo = factory slabs laid on a bed - a tile (slab) finish. Basis, GB 50209-2010 (acceptance of building floor works) clause 6.4.1: "precast slab finishes of cement concrete slabs, terrazzo slabs and artificial stone slabs shall be laid on a bed." Jade-crystal and micro-crystal slabs are artificial stone slabs.
  • Mainstream quotas generally set no separate precast terrazzo floor item - apply the tile items and swap the tile main material to precast terrazzo slabs.

2. Cast terrazzo: monolithic items banded by thickness + strips / colour / mirror TB/T 10831-2024 Volume 10, chapter 2, section 1, item 3 (monolithic finishes), all per 10 m2:

  • FY-1209 terrazzo floor finish, 15 mm, with divider strips
  • FY-1210 terrazzo floor finish, 15 mm, with strips, colour-split
  • FY-1211 mirror terrazzo floor finish, 20 mm, with strips
  • FY-1212 mirror terrazzo floor finish, 20 mm, with strips, colour-split
  • FY-1213 terrazzo floor finish, per 1 mm up or down The same item group holds cement-mortar finishes (FY-1194 to 1196), concrete finishes (FY-1197 to 1198), carborundum wear course, epoxy coloured sand and self-levelling items. Work content: substrate cleaning, mortar hauling, finishing (or concrete casting, spreading, trowelling).

3. Local banding (Beijing DB11/T 2382-2024, Annex A, A.11 floors, A.11.1-2 monolithic finishes)

  • A-11-24 cast terrazzo floor, ordinary, with strips (m2): all-in labour Grade I 0.3770 workday/m2; terrazzo grey-cement aggregate paste 1:2.5 0.0159 m3/m2; glass strips 3.4000 m/m2; hard wax 0.0270 kg/m2; oxalic acid 0.0100 kg/m2; kerosene 0.0400 kg/m2; carborundum stones 0.3300 pieces/m2; thinner and boiled oil 0.0050 kg/m2 each; other materials 1.5%; other plant 2%. Work content: "clean the substrate, lay the finish, grind, wax etc.".
  • A-11-26 cast terrazzo floor, artistic, with strips (m2): labour 0.4030 workday/m2; terrazzo ARTISTIC aggregate paste 1:2.5 0.0159 m3/m2; BRASS strips 3.4000 m/m2 (materials otherwise as the ordinary band).
  • Banding: strip material follows the grade - ordinary terrazzo takes glass strips, artistic (coloured) takes brass; the artistic band carries higher labour.
  • Caution: band names and consumption must be verified against the printed local quota - item names sometimes mismatch their material bands; check name and material column line by line before applying.

4. Tile items (the route for precast terrazzo), railway basis TB/T 10831-2024 Volume 10, floors, item 4 (tile finishes), work content "clean the substrate, trial-lay and snap, soak, saw and trim, spread the bed, lay the finish, point joints, clean", per 10 m2:

  • FY-1214 to 1217 ceramic floor tiles (piece area 0.1 / 0.36 / 0.64 / over 0.64 m2)
  • FY-1218 to 1219 granite floors (0.64 / over); FY-1220 patterns; FY-1221 rubble; FY-1222 accents (10 pieces); FY-1223 border strips
  • FY-1224 to 1225 ceramic mosaics (patterned / plain); FY-1226 to 1227 quarry tiles (pointed / unpointed)
  • FY-1228 to 1232 stone surface treatments (base seal polished / honed, face protector, crystallisation, fine grinding); FY-1233 floors acid-wash and wax; FY-1234 stairs and steps acid-wash and wax
  • FY-1235 tile floor pointing; FY-1236 silicone (10 m); FY-1237 brass divider strips (10 m)
  • FY-1238 to 1241 laser single / laminated toughened glass tiles (8 / 8+5 thick, 0.36 / over) Beijing DB11/T 2382-2024 tile tables band alike by "stone / ceramic / other tile x piece area" (e.g. A-11-44 stone floor, piece area within 0.36 m2, with natural stone panels, adhesive and DTA mortar) - precast terrazzo slabs apply the matching "tile" items with the material swapped.

5. Volume-note adjustment rules directly in play (railway)

  • Terrazzo cement-aggregate paste proportions adjust where the design differs from the quota.
  • Terrazzo floors already include acid-wash and wax; other finishes taking acid-wash and wax execute the acid-wash items (floors FY-1233, stairs and steps FY-1234).
  • Underfloor-heating beds execute the matching items by material with labour x 1.30 and materials x 0.95.
  • Tile finishes: stone inlays 100 x 100 or smaller execute the accent items; vitrified tiles execute the ceramic items; stone floors needing division or colour split take labour x 1.10 on the matching items.
  • Curved skirtings and stair-flight skirtings take labour and plant x 1.15; curved and irregular floors take labour x 1.15; curved stairs take labour x 1.25.

6. Companion measurement rules (same volume notes)

  • Room clear areas deduct trenches, projections, equipment foundations - not columns, piers, partitions, attached flues and ducts, or holes of 0.30 m2 or less.
  • Stone patterns compute on the maximum bounding rectangle; patterned stone floors deduct the pattern's bounding rectangle; accents count by the piece, their area not deducted from the laid area.
  • Base sealing includes the sides, computed on the base area; face protector and pointing on the stone area.
  • Stairs compute on the horizontal projection (treads, landings and wells within 500 mm); joined to floors, to the stringer inner edge; absent a stringer, the last tread edge plus 300.
  • Steps, ramps and aprons include finish and bed, not blinding; step finishes compute on horizontal projection (top tread edge plus 300); step platforms (wall to the top riser edge) within 2.50 m execute the step items, beyond 2.50 m the floor items.

Applicability Boundaries

  • Cast terrazzo bands by design thickness, strips / colour / mirror; differing thickness adjusts via the per-1 mm item (railway FY-1213), never by coefficient.
  • Coloured / artistic and mirror terrazzo (polishing included) stand as separate items with no coefficient conversion; the ordinary / artistic divide shows in the strip material (glass / brass) and paste class.
  • The concrete swap basis for precast terrazzo (main material name, wastage, whether the bed mortar swaps too) follows the local quota notes and the cost authority's reading; gaps never borrow at will - compile a supplementary unit-rate build-up schedule per the quota principles.
  • Railway (TB/T 10831-2024) and local (DB11/T 2382-2024) consumption and companion on-costs differ - never mix; cross-sector / cross-region reference only for analogous process on gaps.
  • No base prices (yuan) here - they move with edition, region and period; consult the current printed quota or the pricing software's current library.

Further Reading

  • TB/T 10831-2024 Volume 10, chapter 2 section 1: volume notes (monolithic and tile adjustment rules, measurement), item 3 FY-1194 to FY-1213, item 4 FY-1214 to FY-1241.
  • DB11/T 2382-2024, Annex A, A.11: A.11.1-2 monolithic finishes (A-11-24 to A-11-27 cast terrazzo bands), A.11.2 tile finishes (A-11-44 etc.).
  • GB 50209-2010, section 6.4 slab finishes, clause 6.4.1.
  • Terrazzo thickness and division details per GB 50037-2013.

Keywords

  • 水磨石地面
  • 整体面层
  • tile and stone finishes
  • 预制水磨石板块
  • 定额子目套用
  • FY-1209
  • A-11-24
  • 楼地面工程量计算规则