Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage

Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.

Applicable Codes

  • SJG 84-2020 市政维修工程消耗量标准 总则0.3.9
  • DL/T 5465-2013 火力发电工程施工图预算编制导则 4.1.13
  • DL/T 5468-2013 输变电工程施工图预算编制导则 4.1.11
  • GB 50861-2013 城市轨道交通工程工程量计算规范 4.2.5
  • DB11/T 638-2016 房屋修缮工程工程量计算规范 App. A.2.1
  • GB/T 50326-2017 建设工程项目管理规范 18.3.3
  • GB/T 51095-2015 建设工程造价咨询规范 8.2.4

Topic Positioning

This card answers the most common principle question in measurement of the works: should dimensions come from the design drawings or from actual site measurements? It gives the general basis of "measurement per drawings", the two classes of exceptions, and the final account linkage.

Core Conclusions

Quantities are in principle calculated from design-drawn dimensions, not as-built site dimensions: (1) several consumption standards state the same general provision, e.g., SJG 84-2020 "Consumption standard for municipal maintenance works", general provisions: "unless otherwise provided in this standard, quantities are calculated per design-drawn dimensions"; (2) power industry DL/T 5465-2013 Clause 4.1.13 and DL/T 5468-2013 Clause 4.1.11 both require calculation based on the construction drawings under the method of measurement prescribed by the quota norms (prescribed resource consumption standards), coordinated with the equipment and material schedules; (3) GB 50861-2013 "Code for measurement of urban rail transit works" Clause 4.2.5 (mandatory provisions of codes) requires the quantities in the bill of quantities (BOQ) to be calculated per the method of measurement in its appendix — dimension determination follows the method of measurement, not the as-built site. Two exception classes: first, items where the method of measurement "provides otherwise" (earthwork by natural in-situ (undisturbed) volume before excavation, excavation depth as the average depth from the surveyed natural ground level to the design ground level) — here the elevation is a surveyed value, but it is still rule-based calculation, not measuring the actual excavation outline; second, flowing sand and silt not specified in the design (DB11/T 638-2016 Appendix A.2.1 note 6) may be provisionally estimated in the BOQ and settled in the final account per the parties' site instruction / variation record confirmation. Practical implication: parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account; earthwork and concealed works should proactively follow the site instruction / variation record process to put site facts in writing.

Applicable Boundaries

Applies to routine measurement of the works in preparation of the bill of quantities, preparation of the construction-drawing based budget (pre-tender estimate), and final account; not applicable to "measure-as-built" items such as demolition, items governed by site instruction / variation record or measurement sheets, and sub-items whose method of measurement explicitly requires actual or surveyed measurement. Specific bases of each discipline still follow that discipline's quota norms (prescribed resource consumption standards) / measurement code appendix.

Further Reading

SJG 84-2020 general provisions Clause 0.3.9; DL/T 5465-2013 Clause 4.1.13, DL/T 5468-2013 Clause 4.1.11; GB 50861-2013 Clause 4.2.5 (mandatory provisions of codes); DB11/T 638-2016 Appendix A Table A.2.1 (earthwork rules and site instruction / variation record treatment); final account linkage: GB/T 50326-2017 Clause 18.3.3, GB/T 51095-2015 Clause 8.2.4.