Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Handling inconsistencies between the content of site instructions and certified records and as-built drawings: written clarification -> adjustment to facts -> report record -> construction cost expert assessment (judicial appraisal) per facts / site survey

An inconsistency between a site instruction / variation record and the as-built drawing cannot be settled by a blanket 'drawing prevails' or 'site instruction / variation record prevails': at final account review the employer and contractor clarify the facts in writing and adjust accordingly (GB/T 51095-2015 8.3.6); if written clarification fails, the construction cost consultancy judges and records the issues in the final account review report; once in construction cost expert assessment (judicial appraisal), quantities are calculated on the basis of actually completed amounts (GB/T 51262-2017 5.9.1); where quantities cannot be confirmed, the expert assessor asks the client to organize a site survey and assesses per the survey results (5.10.2, 4.6). Validity is judged by evidence strength: a site instruction / variation record fully certified and signed off by both parties and the supervisor, with the drawing merely omitting the work — the site instruction / variation record prevails and the as-built drawing should be corrected; a drawing jointly confirmed with a site instruction / variation record suspected of inflated quantities — reduce per actual quantities; documents reflecting different points in time — the final actual state prevails.

Applicable Codes

  • 法释〔2020〕25号 第二十条
  • 法释〔2026〕12号 第二十三条(2026-06-30施行)
  • GB/T 51095-2015 第8.3.6条
  • GB/T 51262-2017 第5.9.1、5.9.2、5.10.1、5.10.2条
  • GB/T 50326-2017 第18.3.3条
  • GB/T 50500-2024 第10.2.1、12.2.1条
  • T/ZBD 100.4-2023 第4.3.5、4.3.6、4.6.3条
  • T/ZBD 100.5-2023 第2.1.11条
  • 中华人民共和国仲裁法(2025修订)第五十六条、第五十七条
  • JGJ/T 408-2017 第14.3节
  • DB37/T 5073-2016 第7.0.2条
  • https://www.court.gov.cn/zixun/xiangqing/504221.html
  • http://gongbao.court.gov.cn/Details/6b4b7633fc2aac95bccf5e58516ab7.html
  • https://splcgk.court.gov.cn/gzfwww/sfjs/details?id=ff8080816c22fc85016cd0c1e41e0d9c
  • https://www.court.gov.cn/zixun/xiangqing/504201.html

Topic Positioning

When the content of site instructions and certified records (site instruction / variation record) conflicts with the as-built drawing (quantities, scope, workmanship): how to determine it at final account review and construction cost expert assessment (judicial appraisal) — first find which document is closer to site reality, then follow the path 'written clarification by both parties -> adjust to facts -> record in the report'; after escalation to construction cost expert assessment (judicial appraisal), determine per actually completed quantities and, if necessary, by site survey.

Core Conclusions

  1. The inconsistency cannot be decided unilaterally by the reviewer: when the final account review finds drawings, site instructions / variation records, etc. inconsistent with facts, the employer and contractor shall clarify the facts in writing and adjust accordingly; where written clarification is not obtained, the construction cost consultancy shall judge and record the issues in the final account review report (GB/T 51095-2015 8.3.6; DB37/T 5130-2018 to the same effect).
  2. In construction cost expert assessment (judicial appraisal): where the miscellaneous minor-work quantities in a site instruction / variation record differ from the actually completed quantities, calculate on the basis of the actually completed quantities (GB/T 51262-2017 5.9.1); where the parties cannot agree on completed quantities and the expert assessor's on-site check also fails to confirm them, request the client to entrust a third party with a site survey and assess per the survey results (5.10.2); the survey is organized by the client and the records are signed by those present (4.6).
  3. Validity judgment: a site instruction / variation record fully certified and signed off by both parties and the supervisor, with the as-built drawing omitting/misdrawing the work — the site instruction / variation record prevails and the as-built drawings should be corrected accordingly; an as-built drawing jointly confirmed by all parties, with a site instruction / variation record suspected of inflated quantities — reduce per actually completed quantities; two documents reflecting different points in time — the final actual state prevails.
  4. As-built drawings shall truly reflect the actual as-built conditions: where records do not match the site, compile from measured data (JGJ/T 408-2017 14.3); if changed drawing content exceeds 1/3, redraw (DB37/T 5073-2016 7.0.2); concealed works are corroborated by concealed work acceptance records plus imagery.

Applicable Boundaries

Applies to final account review, final account dispute handling, and construction cost expert assessment (judicial appraisal); not to bid-stage inconsistencies between tender documents and drawings (separate clarification-objection rules apply). With only verbal instructions (to be confirmed in writing) and no written or physical evidence, the expert assessor issues a negative determination for lack of legal evidence; site instructions / variation records with signature/procedural defects are graded separately by evidence strength.

Further Reading

GB/T 51095-2015 'Code for construction cost consultancy' 8.3.6; GB/T 51262-2017 'Code for construction cost expert assessment (judicial appraisal)' 5.9.1, 5.10.2, 4.6; GB/T 50500-2024 'China national pricing standard for BOQ (GB/T 50500)' 12.2.1 (signed documents within site management personnel's duty scope are valid pricing vouchers); JGJ/T 408-2017 'Standard for construction surveying' 14.3; DB37/T 5073-2016 'Specification for management of construction works documents' 7.0.2.