The role of as-built drawings in construction payment settlement: statutory basis status and graphical benchmark for audit quantity checks
As-built drawings are a statutory basis for the final account and the graphical benchmark for audit quantity checks: GB/T 50326-2017 Clause 18.3.3 lists them among the foremost bases for the final account; GB/T 51095-2015 8.2.4/8.3.4 require checking against them in both preparation and audit; DB37/T 5130-2018 8.3.8 requires checking 'whether the final account contents agree with the as-built drawings and site instruction / variation record contents'. Quantities not reflected in the drawings (especially concealed works) may be reduced in the final account; each variation and site instruction / variation record must be drawn into the as-built drawings and confirmed by the four parties; the drawings must bear a compliant as-built drawing certification stamp (50 x 80 mm) to be a valid basis.
Applicable Codes
- GB/T 50326-2017
- GB/T 51095-2015
- GB/T 50328-2014
- GB/T 50500-2024
- DB37/T 5130-2018
- DB42/T 823-2021
- T/ZBD 100.5-2023
- 建设部令第107号
Topic Positioning
The statutory basis status and practical role of as-built drawings in final account preparation and audit: for the contractor, the evidentiary base of 'actually completed quantities'; for auditors/appraisers, the graphical benchmark for quantity checks and reductions.
Core Conclusions
As-built drawings rank foremost among the statutory bases for the final account: GB/T 50326-2017 Clause 18.3.3 lists 'as-built drawings and variation documents' as the second item in the bases for the final account; GB/T 51095-2015 Clauses 8.2.4, 8.3.4 and DB42/T 823-2021 Clause 8.2.3 include the as-built drawings among the bases for preparing and auditing the final account. When checking quantities on audit, DB37/T 5130-2018 Clause 8.3.8 requires checking 'whether the final account contents are consistent with the as-built drawings and site instruction / variation record contents, and whether the quantities are accurate' — quantities not reflected in the drawings (especially concealed works) may be reduced in the final account. Each variation and site instruction / variation record must be drawn into the as-built drawings (compiled on the basis of the construction drawings, drawing review records, design change (designer-issued variation) orders, and concealed work acceptance records, in accordance with DBJ50/T-306-2018 Clause 5.6.1); the final account drawings shall be jointly confirmed by the employer, contractor, designer, and supervision, with a final account drawing directory formed by discipline (T/ZBD 100.5-2023 Clause 2.2.4); lump-sum contracts must also provide the tender-stage construction drawings for comparison. Formal elements: the as-built drawings must bear the as-built drawing certification stamp (bearing the words 'as-built', the contractor, the compiler, the checker, the technical director, the date of preparation, the supervision unit, the site supervisor, and the chief supervision engineer; 50 mm x 80 mm, in indelible ink, stamped in the blank space above the title block, GB/T 50328-2014 Clause 4.2.8) — any missing item may cause the final account to be rejected on audit.
Applicable Boundaries
This card addresses the role, evidentiary status, and formal elements of as-built drawings at the final account stage. Not covered: conflict adjudication where the as-built drawings and site instruction / variation record conflict; technical rules for redrawing as-built drawings; computation and itemisation of the final account price (GB/T 50500-2024 Clause 10.3.2). Where the contract provides otherwise on the basis for settlement, the agreed terms prevail.
Further Reading
GB/T 50326-2017 Clause 18.3.3; GB/T 51095-2015 Clauses 8.2.4, 8.3.4; GB/T 50328-2014 Clause 4.2.8; GB/T 50500-2024 Clauses 7.1.8, 10.1.4, 10.3.1, 10.3.2, 10.3.4; DB37/T 5130-2018 Clauses 8.2.4, 8.3.8; DB42/T 823-2021 Clauses 8.2.3, 8.2.4; T/ZBD 100.5-2023 Clauses 2.1.8, 2.2.4; Ministry of Construction Order No. 107 Article 16.