concealed works
- 01
Whether the employer may withhold payment when acceptance records of concealed works are missing: whether missing records constitute a defence to payment of the works price, a comparison of refusable and non-refusable scenarios, and the legal bases (Civil Code, Articles 798, 799 and 801; Fa Shi [2020] No. 25, Article 20; Fa Shi [2026] No. 12, Article 16)
The employer cannot refuse payment of the corresponding works price sole…
《中华人民共和国民法典》(主席令第四十五号)第七百九十八条、第七百九十九条、第八百零一条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十二条、第十四条、第二十条法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十六条、第二十三条(2026年6月30日起施行)2026-10-29 - 02
Concealed works covered without acceptance: rules for determining quality, quantity and liability
Before concealment the contractor must give notice for acceptance, and t…
中华人民共和国民法典(主席令第45号)第七百九十八条、第七百九十九条、第七百九十三条建设工程质量管理条例(国务院令第714号,2019修订)第三十条最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第二十条2026-10-29 - 03
Recording and retention of photographic records of concealed works and critical processes and of construction logs: what to shoot, original resolution of no less than 10 megapixels, filing by unit work, prohibition of editing or altering file properties, no supplementary or back-dated entries
Photographic records of concealed works form part of the acceptance docu…
TB 10754-2018 高速铁路轨道工程施工质量验收标准 附录AGB 55032-2022 建筑与市政工程施工质量控制通用规范 第3.3.4条GB 50300-2013 建筑工程施工质量验收统一标准 第3.0.6条2026-10-29 - 04
Routes for claiming final account quantities of concealed works where no measurement records exist: the pre-concealment measurement confirmation procedure, who bears the exposure costs after covering without notice, the ranking of supplementary evidence, the requirements for retrospectively certified quantity sheets, and the interface with measurement from drawings
The absence of measurement records does not mean quantities cannot be cl…
GF-2017-0201 建设工程施工合同(示范文本)第4.4款、第5.3款(5.3.1~5.3.4)、第5.4款、第5.5款GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.5、7.1.6、7.1.8、7.2.1、12.2.1条GB/T 50319-2013 建设工程监理规范 第5.2.14条及Table B.0.7、Table B.0.82026-10-25 - 05
The role of as-built drawings in construction payment settlement: statutory basis status and graphical benchmark for audit quantity checks
As-built drawings are a statutory basis for the final account and the gr…
GB/T 50326-2017GB/T 51095-2015GB/T 50328-20142026-09-25 - 06
Key contents and procedure requirements of concealed-works acceptance records
A concealed-works acceptance record shall contain: ① acceptance basis (c…
GB 50210-2018 建筑装饰装修工程质量验收标准GB/T 50252-2018 工业安装工程施工质量验收统一标准DB12/T 935-2020 水运工程资料管理技术规程2026-09-25