Key contents and procedure requirements of concealed-works acceptance records
A concealed-works acceptance record shall contain: ① acceptance basis (conformity with design, citing drawing numbers and test/inspection report numbers); ② description of quality condition (text + sketches fully reflecting the concealed content, by discipline, layer, segment, and part); ③ photographs of the concealed parts (GB 50210-2018, Clause 3.3.12, mandatory); ④ a conclusive opinion (whether the next process may proceed) with signatures of the participating units and responsible persons;⑤ timely summarization after acceptance, and re-inspection with a re-inspection conclusion after rework. Procedurally, inspection must be requested before covering, and the next process may start only after acceptance passes.
Applicable Codes
- GB 50210-2018 建筑装饰装修工程质量验收标准
- GB/T 50252-2018 工业安装工程施工质量验收统一标准
- DB12/T 935-2020 水运工程资料管理技术规程
- DB62/T 25-3016-2016 建筑工程资料管理规程
- DB11/T 382-2017 建设工程监理规程
Topic Positioning
The preparation elements and accompanying procedure of concealed-works acceptance records — for preparing and reviewing such records or checking the completeness of construction documentation.
Core Conclusions
A concealed-works acceptance record shall contain five kinds of key content:
- Acceptance basis: the concealed content shall satisfy the design and current national standards, citing the specific construction drawing numbers and relevant test/inspection report numbers;
- Quality description: filled in by discipline, layer, segment, and part, describing the main acceptance contents and findings in words, with sketches that fully reflect the concealed content;
- Photographic documentation: the record must contain photographs of the concealed parts (mandatory); inspection-lot acceptance also requires original on-site inspection records;
- Conclusion and signatures: the opinion column states the conclusive opinion on whether the next process may proceed, signed by the participating units and responsible persons;
- Summarization and re-inspection: records are summarized promptly after acceptance; where rework is needed, re-inspect after rework and issue a re-inspection conclusion. Procedurally: the contractor's project technical responsible person requests inspection in writing; the discipline supervising engineer organizes acceptance and signs the acceptance document; work not inspected or failing inspection must not proceed to the next process; where work is covered without inspection, the supervisor may require drilling probing, stripping, or re-testing.
Applicable Boundaries
Applies to preparing and checking concealed-works acceptance records across decoration, industrial installation, municipal, and waterway disciplines; non-physical items affecting quality and safety such as earthworks of foundations, pit support, and formwork should also be listed. Concealed acceptance is process control, distinct from post-completion sub-item/sub-divisional acceptance. Form formats and sampling quantities follow the discipline acceptance codes and local documentation rules — local form styles prevail.
Further Reading
See GB 50210-2018, Clause 3.3.12 (mandatory photographs of concealed parts); GB/T 50252-2018, Clause 3.0.9 (acceptance before covering; failures must not proceed); DB12/T 935-2020, Clause 5.4.2 (record contents); DB62/T 25-3016-2016, Clause 5.6.1 (inspection request and re-inspection); DB11/T 382-2017, Clause 4.4.5 (supervisor's acceptance organization and treatment of unauthorized covering).
Keywords
- 隐蔽工程验收记录
- concealed works
- 隐蔽验收
- 验收记录填写
- 报验
- 下道工序
- 隐蔽部位照片