Concealed works covered without acceptance: rules for determining quality, quantity and liability
Before concealment the contractor must give notice for acceptance, and the works may not be covered without acceptance (Regulations on Quality Management of Construction Works, Article 30; GB/T 50252-2018, Clause 3.0.9); where covered without authorization, the re-inspection and all adverse consequences rest with the contractor; where notice was given but the supervisor/employer failed to inspect in time, the cost and delay of a passing re-inspection are borne by the employer, which must also pay reasonable profit. Quantity determination follows the ladder 'valid joint sign-off - one-party sign-off - review and site survey - non-measurement' (T/ZBD 100.4-2023, Clause 4.3.6).
Applicable Codes
- 中华人民共和国民法典(主席令第45号)第七百九十八条、第七百九十九条、第七百九十三条
- 建设工程质量管理条例(国务院令第714号,2019修订)第三十条
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第二十条
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第二十三条 https://www.court.gov.cn/fabu/xiangqing/504221.html
- GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.1、7.1.2、7.1.5、7.1.6、7.1.7、7.1.8、7.2.1、10.3.8条
- GF-2017-0201 建设工程施工合同(示范文本)第5.3.1~5.3.4条
- GB/T 50319-2013 建设工程监理规范 第5.2.14条
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.3.6条
Topic Positioning
When concealed works (piling, reinforcement, piping, foundations, etc.) are covered before being accepted, how are quality, quantity and liability determined - this card gives the obligation framework, the liability rules, the judicial standards for re-inspection and the measurement determination ladder.
Core Conclusions
- Obligation framework: before concealment the contractor must notify the employer and the quality supervision authority and keep inspection records (Regulations on Quality Management of Construction Works, Article 30); without inspection and acceptance, or where the inspection fails, the next process may not proceed (GB/T 50252-2018, Clause 3.0.9). Supervision practice: after self-inspection passes, written notice is given about 48 hours in advance (stating content, time and place); if the supervising engineer cannot attend, a written deferral is applied for at least 24 hours in advance and for no more than 48 hours (e.g., DB13(J)/T 8161-2019, Clause 12.0.8; similar provisions locally).
- Liability split: the contractor covers the works without notice - the re-inspection and all adverse consequences rest with the contractor; the contractor notified but the employer/supervisor failed to inspect in time - the contractor may claim extension of time and costs, and the cost and delay of a passing re-inspection are borne by the employer, which must also pay reasonable profit; where the re-inspection fails - the cost and delay rest with the contractor regardless of who ordered it.
- Quality determination: per the results of re-inspection (core drilling, stripping or other methods); where re-inspection is no longer possible, determined comprehensively from concealment acceptance records, test reports, specimens and cubes, photographic records and completion documents.
- Quantity determination ladder: valid joint sign-off - measure per the sign-off; only one party signed (plus supervisor/designer) and the other party has no effective rebuttal evidence - measure per that sign-off; the other party objects with evidence - measure after review or site survey; no sign-off and the drawings cannot show it - measure by site survey; survey still inconclusive and no valid evidence - non-measurement, stated as a 'non-determinable item' (T/ZBD 100.4-2023, Clause 4.3.6).
Applicable Boundaries
Applies to general rules of supervision-acceptance compliance and settlement disputes during the construction stage. Where the re-inspection passes, employer liability presupposes 'compliance with the contract requirements'; local supervision standards may set different notice periods; for parts already delivered into use and no longer openable for inspection, determination relies on the evidence chain rather than test results.
Further Reading
Regulations on Quality Management of Construction Works (2019 revision), Article 30; GB/T 50252-2018, Unified Standard for Constructional Quality Acceptance of Industrial Installation Engineering, Clause 3.0.9; GB/T 50319-2013, Code for Construction Project Management, Clause 5.2.14 and Forms B.0.7/B.0.8; T/ZBD 100.4-2023, Guideline for Cost Expert Determination of Construction Works, Clause 4.3.6; DB13(J)/T 8161-2019, Standard for Supervision Work of Construction Engineering, Clause 12.0.8; compare also the SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25), Article 20, on certified site records and evidence rules.
Keywords
- concealed works
- 私自覆盖
- 工程量争议
- 隐蔽验收记录
- 签证
- 重新检验
- 计量成果
- 工程价款结算