Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Evidence preservation where the works are about to be demolished, backfilled or concealed (including contractor demobilisation from site) and site evidence may be lost: application conditions, three jurisdictional routes, application requirements, security and costs, preservation measures, time limits and reconsideration relief, and the procedural landscape of combining it with conduct preservation

Demolition, backfilling, concealment and site clearance of the works all fall within the statutory situation of 'evidence being liable to be lost or difficult to obtain later' under Article 84 of the Civil Procedure Law (2023 revision): in litigation the party applies in writing before the time limit for producing evidence expires; in urgent circumstances an interested party may apply before suing or applying for arbitration to the people's court at the place where the evidence is located, the respondent's domicile or the court with jurisdiction over the case for pre-suit preservation; in arbitration the arbitration institution forwards the application to the basic-level people's court at the place where the evidence is located (Arbitration Law (2025 revision) Article 58). Where preservation may cause losses to others, the court shall order security to be provided; where a wrongful evidence preservation application causes property loss, the applicant must compensate (Fa Shi [2019] No. 19 Articles 26 and 28); a party dissatisfied with a preservation ruling may apply once for reconsideration, filed within 5 days, with the court reviewing within 10 days (Civil Procedure Law Article 111; SPC Interpretation on the Civil Procedure Law Article 171). Demolition/covering are continuing acts; a simultaneous conduct preservation application (Civil Procedure Law Articles 103 and 104; pre-suit conduct preservation requires security, ruling within 48 hours) is needed to get ahead of the loss.

Applicable Codes

  • 《中华人民共和国民事诉讼法》(2023修正)第七十二条、第八十四条、第一百零三条、第一百零四条、第一百一十一条
  • 《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(法释〔2015〕5号,2022修正)第九十八条、第一百七十一条
  • 《最高人民法院关于民事诉讼证据的若干规定》(法释〔2019〕19号)第二十三条、第二十五条至第二十九条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十五条、第二十三条(2026年6月30日施行)
  • 《中华人民共和国仲裁法》(2025修订)第五十八条(2026年3月1日施行),官方原文:https://policy.mofcom.gov.cn/claw/clawContent.shtml?id=103718
  • 《中华人民共和国民法典》第七百九十八条
  • 《建设工程质量管理条例》(2019修订)第三十条
  • GF-2017-0201《建设工程施工合同(示范文本)》第5.3.3、5.3.4项
  • GB/T 51262-2017 · Code for Construction Cost Appraisal 第4.6.5、4.6.6条
  • 《保障中小企业款项支付条例》(2025修订)第十条
  • 《中华人民共和国行政诉讼法》(2017修正)第四十二条

Scope and Positioning

When the physical works are about to be demolished, backfilled, concealed or handed over (including contractor demobilisation and concealed parts about to be covered), the site condition may vanish at any moment. This card gives the application requirements and procedural routes of three parallel tracks - evidence preservation + conduct preservation + notarial fixation of evidence: application conditions, competent authorities, application requirements, security and costs, preservation measures, rulings and reconsideration relief, and, after demolition or covering, the degraded fallback of on-site inspection in construction cost expert assessment.

Core Conclusion

1. Application is possible; the window exists only before the destructive act occurs.

Article 84 of the Civil Procedure Law (2023 revision): 'Where evidence may be lost or difficult to obtain later, a party may, during litigation, apply to the people's court for evidence preservation, and the people's court may also take preservation measures on its own initiative. In urgent circumstances where evidence may be lost or difficult to obtain later, an interested party may, before instituting litigation or applying for arbitration, apply to the people's court at the place where the evidence is located, at the respondent's domicile, or which has jurisdiction over the case, for evidence preservation. Other procedures for evidence preservation apply by reference to the relevant preservation provisions of Chapter IX of this Law.'

The construction-sector entry point - Article 15 of Fa Shi [2026] No. 12 (SPC Interpretation (II) on construction contract disputes): 'Where a construction contract is rescinded and the employer requests the contractor to hand over the site and construction documents, the people's court shall support it in accordance with law. Where a party applies for evidence preservation before the contractor demobilises from site, the people's court shall handle it under Article 84 of the Civil Procedure Law.' Hence before demobilisation or demolition is the complete window; once covered or demolished, only the fallback of on-site inspection in cost expert assessment remains, with a cliff-edge drop in probative force.

2. Three routes and accepting authorities

Route When raised Accepting authority Security
In-litigation evidence preservation In writing before the time limit for producing evidence expires (SPC Interpretation on the Civil Procedure Law Article 98 paragraph 1); the court may also act on its own motion The court seised of the case Where loss to others may arise, the court shall order corresponding security (same article, paragraph 2)
Pre-suit evidence preservation 'Urgent circumstances', before instituting litigation or applying for arbitration The people's court at the place where the evidence is located, the respondent's domicile, or with jurisdiction over the case As Article 84 paragraph 2; by reference to the Chapter IX preservation provisions
In-arbitration evidence preservation During the arbitration proceedings The arbitration institution forwards the party's application to the basic-level people's court at the place where the evidence is located, which shall handle it promptly under law (Arbitration Law (2025 revision) Article 58 paragraph 1) As above

Arbitration Law (2025 revision) Article 58 paragraph 2: 'In urgent circumstances, a party to an arbitration agreement may, before applying for arbitration, apply to the people's court for evidence preservation in accordance with the relevant provisions of the Civil Procedure Law of the PRC. Where a party applies for evidence preservation, the people's court shall handle it promptly in accordance with law.'

3. Evidence preservation alone is often too slow; a conduct preservation application must run in parallel.

Article 103 of the Civil Procedure Law: 'For cases where, due to one party's acts or other causes, enforcement of a judgment may be frustrated or other harm caused to a party, the people's court may, on the other party's application, rule to preserve its property, order it to perform certain acts or prohibit it from performing certain acts; where no application is made, the court may where necessary also rule to take preservation measures. In taking preservation measures the court may order the applicant to provide security; if the applicant does not, the application is ruled dismissed. After accepting an application, in urgent circumstances the court must rule within 48 hours; where preservation is ruled, execution shall begin immediately.'

The pre-suit route is Article 104: an interested party who, in urgent circumstances, would suffer irreparable harm to its lawful rights without immediate preservation may, before suing or applying for arbitration, apply to the court at the place of the property to be preserved, the respondent's domicile or the court with jurisdiction over the case; the applicant shall provide security, failing which the application is ruled dismissed; after acceptance the court must rule within 48 hours, and where preservation is ruled, execution begins immediately; if the applicant does not sue or apply for arbitration within 30 days after preservation measures are taken, preservation shall be released.

That is: a request to 'prohibit demolition / prohibit covering / prohibit site clearance' requires security to be prepared in advance - the biggest difference from evidence preservation (evidence preservation requires security only where loss may arise; pre-suit conduct preservation always requires it).

4. What the application must state

Article 25 paragraph 1 of the SPC Provisions on Evidence in Civil Procedure (Fa Shi [2019] No. 19): 'Where a party or interested party applies for evidence preservation under Article 81 of the Civil Procedure Law, the application shall state the basic particulars of the evidence to be preserved, the reasons for preservation, and the preservation measures sought, among other content.' Paragraph 2: 'A party applying under Article 81 paragraph 1 of the Civil Procedure Law shall apply to the people's court before the time limit for producing evidence expires.' Paragraph 3: 'Where laws or judicial interpretations provide for pre-suit evidence preservation, those provisions govern.'

In practice the 'basic particulars' must be specific down to the part + axis/pile number/level + member number + items to be measured (section dimensions, thickness, length, material, on-site quantities of labour, materials and plant), otherwise the court cannot enforce it or match it to the facts to be proved.

5. Security and costs

SPC Interpretation on the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 revision) Article 98 paragraph 2: 'Where evidence preservation may cause loss to others, the people's court shall order the applicant to provide corresponding security.'

Fa Shi [2019] No. 19 Article 26: 'Where a party or interested party applies for measures such as sealing or seizing that restrict the use or circulation of the subject matter, or where preservation may cause loss to the holder of the evidence, the people's court shall order the applicant to provide corresponding security. The form or amount of security is determined by the court comprehensively on factors such as the impact of the measures on the holder, the value of the subject matter, and the amount in dispute between the parties.'

On costs: evidence preservation has no statutory application-fee tiers charged by the amount claimed; the real costs are the security outlay and the implementation costs (inspection, surveying, expert assessment, video recording, copying, storage), advanced by the applicant and ultimately borne per the outcome of the ruling and responsibility; where security is provided by preservation liability insurance or similar, the insurer must issue a letter of guarantee stating 'the insurer compensates the losses of the preserved party caused by a wrongful preservation application'.

6. Preservation measures the court may take

Fa Shi [2019] No. 19 Article 27: 'In preserving evidence the people's court may require the parties or their agents ad litem to be present. Based on the party's application and the circumstances, the court may preserve evidence by sealing, seizing, audio or video recording, copying, expert assessment, inspection and other methods, and shall make a written record. Where consistent with the purpose of evidence preservation, the court shall choose the measure least affecting the interests of the holder.'

For audio-visual material and electronic data (site surveillance, imagery), the person investigated shall be required to produce the original carrier; where that is genuinely difficult, a copy may be produced, and the court shall state in the investigation record its source and manner of production (Article 23 of the same provisions).

7. After preservation and the consequences of wrongful preservation

Where after pre-suit preservation the party sues in another court with jurisdiction, the court that took the measures shall, on the party's application, promptly transfer the preserved evidence to the seised court (Article 29 of the same provisions).

Article 28 of the same provisions: 'Where a wrongful application for evidence preservation causes property loss and the party requests the applicant to bear compensation liability, the people's court shall support it.'

8. Time limits and relief

Civil Procedure Law Article 111: 'A party dissatisfied with a preservation or advance enforcement ruling may apply for reconsideration once. Reconsideration does not stay execution of the ruling.'

SPC Interpretation on the Civil Procedure Law Article 171: 'A party dissatisfied with a preservation or advance enforcement ruling may apply to the ruling court for reconsideration within 5 days of receiving the written ruling. The court shall review within 10 days of receiving the application. Where the ruling is correct, the application is dismissed; where improper, the ruling is varied or revoked.' Hence a respondent blocking by reconsideration and an applicant correcting a dismissal both face '5 days to apply, 10 days to review', and reconsideration does not stay execution.

9. Three things to do in parallel before and after demolition or covering (without waiting for the court)

(1) Pre-concealment notice and inspection: before concealing concealed works the contractor shall notify the employer to inspect; where the employer fails to inspect in time, the contractor may extend the works date and claim compensation for suspension, idle and other losses (Civil Code Article 798). Construction units must establish and improve construction quality inspection systems, strictly manage work processes, and keep quality checks and records for concealed works; before concealment the construction unit shall notify the employer and the construction quality supervision authority (Regulations on Construction Quality Management Article 30).

(2) Post-covering re-inspection and consequences of unauthorised covering (GF-2017-0201 model contract): after the contractor covers a concealed part, the employer or the supervising engineer, doubting the quality, may require core drilling or uncovering for re-inspection; where inspection proves the quality conforms to the contract, the employer bears the added costs and/or delay so caused and pays reasonable profit; where it does not conform, the contractor bears them. Where the contractor covers a concealed part without notifying the supervising engineer to inspect, the supervising engineer may instruct drilling or uncovering, and whatever the quality, the added costs and/or delay so caused are borne by the contractor (Clauses 5.3.3, 5.3.4).

(3) Notarial fixation: Article 72 of the Civil Procedure Law: 'Notarised legal facts and documents shall be the basis on which the people's court finds facts, unless contrary evidence suffices to overturn the notarisation.' Notarisation and court preservation run in parallel without conflict - the court may not attend the same day, while notarisation guarantees 'evidence that same day'.

The degraded route after demolition or covering is completed: on-site inspection in construction cost expert assessment - an inspection record or chart must be made recording the time, place, inspectors, persons present, process and results, signed or sealed by the inspectors and those present; site charts drawn must note the drawing time, orientation and the surveyor's name and identity, with photos or video retained where necessary (GB/T 51262-2017 Clause 4.6.5); where a party's representative attends the inspection but neither signs nor raises specific written opinions, this does not prevent the assessor using the inspection results in the assessment (Clause 4.6.6).

Applicable Boundaries

  • Article numbering: under the current Civil Procedure Law (2023 revision), evidence preservation is Article 84 and notarial evidentiary force is Article 72; the 'Article 81 of the Civil Procedure Law' written in Fa Shi [2019] No. 19 is the 2017-revision numbering, corresponding to the current Article 84 - do not mix them when citing.
  • Interpretation (II) time boundary: Fa Shi [2026] No. 12 Article 23: 'This interpretation takes effect on 30 June 2026. It applies to first-instance construction contract dispute cases newly accepted by the people's courts after it takes effect. After it takes effect, earlier SPC judicial interpretations inconsistent with it are superseded by it.' So Article 15 applies only to first-instance cases newly accepted after 30 June 2026; cases accepted earlier follow the previous rules (the Article 84 route itself is unaffected).
  • Arbitration Law time boundary: the Arbitration Law was revised on 12 September 2025 and takes effect on 1 March 2026; arbitration cases straddling that date must check which version and which evidence-preservation article numbering applies.
  • Pre-suit preservation presupposes 'urgent circumstances'; matters not urgent should be raised within litigation/arbitration; in-litigation applications must be in writing before the time limit for producing evidence expires.
  • Evidence preservation only addresses 'how the site condition is fixed', not substantive rights: whether rescission rights exist, whether completed works quality passes, and who bears breach liability must be judged under substantive rules.
  • If inspection or acceptance has been completed and signed before demolition/covering, evidence is fixed and the start point of the payment period is locked at the same time - where passing inspection or acceptance is the agreed payment condition, the payment period runs from the date of passing; where inspection or acceptance is delayed, it runs from expiry of the agreed inspection/acceptance period (Regulations on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision) Article 10).
  • In administrative litigation, litigation participants may likewise apply for evidence preservation and the court may act on its own motion (Administrative Procedure Law (2017 revision) Article 42); evidence fixation in administrative compulsory demolition scenarios must also follow administrative procedure rules.
  • GB/T 51262-2017 is a recommended standard, binding only when incorporated by contract; its inspection methods cannot replace a court evidence preservation ruling.

Further Reading

  • Civil Procedure Law (2023 revision): Article 72 (notarial evidentiary force), Article 84 (evidence preservation and pre-suit jurisdiction), Chapter IX preservation provisions, Article 103 (in-litigation conduct preservation and 48-hour ruling), Article 104 (pre-suit conduct preservation, security, 30-day suit deadline), Article 111 (reconsideration of preservation rulings).
  • Fa Shi [2015] No. 5 SPC Interpretation on the Civil Procedure Law (2022 revision): Article 98 (written application before the evidence-production limit; security), Article 171 (5-day application and 10-day review reconsideration procedure).
  • Fa Shi [2019] No. 19 SPC Provisions on Evidence in Civil Procedure, Chapter II 'Investigation, Collection and Preservation of Evidence', Articles 20-29: Article 25 (application content and timing), Article 26 (ordering security and the factors fixing its amount), Article 27 (sealing, seizure, recording, copying, expert assessment, inspection and the least-harm principle), Article 28 (liability for wrongful preservation), Article 29 (transfer of pre-suit preserved evidence); Article 23 (original carriers for audio-visual material and electronic data; the same rule applies to preservation).
  • Fa Shi [2026] No. 12 Interpretation (II) Article 15 (site handover and pre-demobilisation evidence preservation), Article 23 (effective date and the new/old boundary).
  • Arbitration Law of the PRC (2025 revision) Article 58 (in-arbitration applications forwarded by the institution to the basic court where the evidence is located; pre-arbitration urgent cases direct to the court), revised 12 September 2025, effective 1 March 2026; official text: https://policy.mofcom.gov.cn/claw/clawContent.shtml?id=103718
  • Civil Code Article 798 (pre-concealment notice and inspection obligation, extension of time, compensation for suspension and idle losses); Regulations on Construction Quality Management (2019 revision) Article 30 (pre-concealment notice to the employer and the quality supervision authority).
  • GF-2017-0201 Model Construction Contract: Clauses 5.3.3 (cost and time allocation for post-covering re-inspection), 5.3.4 (cost and time consequences of the contractor's unauthorised covering).
  • GB/T 51262-2017 Code for Construction Cost Expert Assessment: Clause 4.6.5 (six elements of inspection records/charts and image retention), Clause 4.6.6 (attending but refusing to sign without raising written opinions does not bar use of the inspection results).
  • Regulations on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision) Article 10 (payment period runs from passing inspection or acceptance; delayed acceptance runs from expiry of the agreed acceptance period).
  • Administrative Procedure Law (2017 revision) Article 42 (evidence preservation in administrative litigation).

Keywords

  • 证据保全
  • 诉前证据保全
  • 行为保全
  • 民事诉讼法第八十四条
  • 法释〔2026〕12号第十五条
  • 民事诉讼证据规定第二十五条
  • 仲裁中证据保全
  • 拆除覆盖证据灭失

Cited By