The contractor's obligation to hand over the construction site and construction documents after termination of a construction contract (Fa Shi [2026] No. 12, Article 15), and evidence preservation before the contractor leaves the site (Article 84 of the Civil Procedure Law): legal routes, the commencement threshold and practical points
Fa Shi [2026] No. 12, Article 15, paragraph 1: after termination of a construction contract, where the employer requests the contractor to hand over the construction site, the construction documents and the like, the people's court shall support the request in accordance with law - handover is a statutory obligation upon termination, not conditioned on settlement of the works payment, and the contractor may not resist settlement by refusing to hand over. Paragraph 2: where a party applies for evidence preservation before the contractor leaves the site, the people's court shall handle it under Article 84 of the Civil Procedure Law (application during the proceedings; in urgent circumstances a pre-suit application may be made before instituting proceedings or applying for arbitration to the court at the place where the evidence is located, the place where the respondent is domiciled or the court having jurisdiction; the court may also preserve evidence on its own initiative). The interpretation takes effect on 30 June 2026 and applies to first-instance cases newly accepted after that date (Article 23).
Applicable Codes
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十五条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第二十三条
- 《中华人民共和国民事诉讼法》(2023修正)第八十四条
- 《中华人民共和国民法典》第五百六十五条
- 《中华人民共和国民法典》第五百六十六条
- https://www.court.gov.cn/fabu/xiangqing/504221.html
Topic Positioning
After termination of a construction contract (including termination following prolonged suspension and forced clearance), the contractor's obligation to hand over the construction site and construction documents to the employer, its legal basis, and the route and procedure for the contractor to apply for evidence preservation before leaving the site to fix the quantity of work performed and the condition of the site.
Core Conclusions
I. Handover of the construction site and construction documents: the court supports the claim as of right
Fa Shi [2026] No. 12, Interpretation (II) of the Supreme People's Court on Issues Concerning the Application of Law in the Trial of Cases Involving Disputes over Construction Contracts of Construction Projects, Article 15, reads: 'After a construction contract is terminated, where the employer requests the contractor to hand over the construction site, the construction documents and the like, the people's court shall support the request in accordance with law. Where a party applies for evidence preservation before the contractor leaves the site, the people's court shall handle the matter in accordance with Article 84 of the Civil Procedure Law.' Key points:
- Handover is a statutory obligation arising upon termination of the contract, on the precondition that the contract has been terminated (including statutory termination, agreed termination and termination by adjudication);
- The request covers the 'construction site' and 'construction documents'; the clause is open-ended with the words 'and the like', which can extend to delivery of the state of occupation of the site and inventoried handover of materials and equipment on site;
- Handover is not conditioned on settlement of the works payment - the contractor may not refuse handover on the ground that the works payment remains unsettled; price disputes are resolved through the settlement route and do not constitute a justified defence for refusing handover;
- Handover is a claim that may be brought independently, and may be combined with termination (or confirmation of the effect of termination), settlement of the price of the work performed and claims for damages, without waiting for the settlement to be completed before suing;
- Commencement threshold: under Article 23 of the same interpretation, the interpretation takes effect on 30 June 2026 and applies to first-instance cases involving construction contract disputes newly accepted after that date; cases accepted earlier do not apply it, and handover claims in previously accepted cases were usually pursued as restitution or ancillary obligations after termination, with inconsistent adjudication standards.
II. Evidence preservation before leaving the site (Article 84 of the Civil Procedure Law)
Original text: 'Where evidence may be lost or would be difficult to obtain later, a party may, in the course of proceedings, apply to the people's court for preservation of evidence, and the people's court may also take preservation measures on its own initiative. Where, in urgent circumstances, evidence may be lost or would be difficult to obtain later, an interested party may, before instituting proceedings or applying for arbitration, apply to the people's court at the place where the evidence is located, the place where the respondent is domiciled or the people's court having jurisdiction over the case for preservation of evidence. Other procedures for evidence preservation shall be governed, by reference, by the relevant provisions on preservation in Chapter IX of this Law.' Key points:
- The full preservation window exists only 'before the contractor leaves the site' - once it has left, the quantity of work performed, the condition of concealed works, the materials and equipment on site and the site conditions are highly likely to be lost or difficult to prove afterwards;
- The application may be made in the course of proceedings, or before instituting proceedings or applying for arbitration as an interested party for pre-suit evidence preservation; jurisdiction lies with the court at the place where the evidence is located, the place where the respondent is domiciled or the court having jurisdiction over the case;
- The people's court may also take preservation measures on its own initiative, without waiting for an application by a party;
- Other procedures (security, rulings, reconsideration, etc.) are governed by reference to the preservation provisions of Chapter IX of the Civil Procedure Law.
III. Sequence of practical operations
- Fix the evidence before leaving: notarise, or apply to the court for evidence preservation of, the quantity of work performed, the concealed parts, the materials and equipment on site and the state of occupation of the site, while forming bilateral site handover records, photographic material and sign-off of quantities;
- Serve the termination notice and the handover demand in parallel: termination takes effect when the notice reaches the other party under Article 565 of the Civil Code; immediately after termination, demand handover in writing, and if the demand fails, sue on both together;
- Design of claims: termination (or confirmation of the effect of termination) + handover of the construction site and construction documents + settlement of the price of the work performed + damages may be claimed together; the scope of the documents should be listed specifically (construction technical documents, quality acceptance and inspection documents, as-built drawings, site instruction records and variation documents, seals, certificates and dedicated equipment, etc.).
Applicable Boundaries
- This card deals only with 'the handover obligation and evidence preservation', and not with whether a right to terminate has arisen, the settlement basis for the price of the work performed, the starting point for release of the retention money, or the scope of the priority right of payment.
- Article 15 is a new judicial interpretation provision and applies only to first-instance cases newly accepted after 30 June 2026; cases accepted earlier are handled under the judicial interpretations then in force and the general rules of the Civil Procedure Law.
- Evidence preservation requires the precondition that 'evidence may be lost or would be difficult to obtain later'; quantities already signed off by the other party need no further preservation.
- Pre-suit evidence preservation may require security (by reference to the preservation provisions), and an applicant whose wrongful application causes loss to the respondent is liable to compensate.
- Enforcement of the handover obligation presupposes that the site is still in the possession of the contractor, its subcontractors or the actual builder; where a third party has taken possession or the site no longer exists, the matter turns to the damages route.
Further Reading
- Fa Shi [2026] No. 12, Interpretation (II) on Construction Contract Disputes, Article 15 (handover of the construction site and documents; evidence preservation before leaving the site) and Article 23 (effect from 30 June 2026 and the old/new transition).
- Civil Procedure Law of the PRC (2023 revision), Article 84 (evidence preservation) and Chapter IX (preservation).
- Civil Code, Article 565 (termination notice effective upon arrival) and Article 566 (consequences of termination: restitution and other remedies).
- Supreme People's Court official text: https://www.court.gov.cn/fabu/xiangqing/504221.html
- For settlement of the price after termination and the starting point of the retention money release period, see the cards on 'settlement of the works price after termination of the construction contract' and 'starting point of the retention money release period after termination'; for determination of the quantity and price of work performed and the preservation procedure, see the card on 'evidence preservation and quantity-price determination of work performed'.