After termination of a construction contract: the contractor's duties to hand over the construction site and construction records, the pre-evacuation evidence preservation procedure, and proving the date of evacuation as the anchor for the start of the retention money return period
Fa Shi [2026] No. 12, Article 15: after a construction contract is terminated, where the employer requests the contractor to hand over the construction site, construction records and the like, the people's court supports the request according to law; before the contractor evacuates, a party applying for evidence preservation is handled by the people's court under Article 84 of the Civil Procedure Law (preservation may be sought where evidence may be lost or become hard to obtain later; in urgent circumstances it may be sought before filing suit or applying for arbitration). After termination the retention money return period runs from the contractor's evacuation (where termination occurs after evacuation, from the date of termination), so the date of evacuation and the written records of handover of site and records are the key evidence for fixing that starting point.
Applicable Codes
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十五条、第十四条、第二十三条
- 《中华人民共和国民事诉讼法》第八十四条
- 《中华人民共和国民法典》第五百六十五条
- https://www.gov.cn/zhengce/202504/content_7021701.htm
Positioning
Three layers of the fact of 'evacuation' after termination of a construction contract: the contractor's duties of site and records handover (enforceable by suit), the procedural window for evidence preservation before evacuation, and why the evacuation date becomes the statutory anchor for the start of the retention money return period, and how to prove it.
Core Conclusions
1. Handover duty (Fa Shi [2026] No. 12, Article 15, paragraph 1, verbatim)
'After a construction contract is terminated, where the employer requests the contractor to hand over the construction site, construction records and the like, the people's court shall support the request according to law.' Key points: (1) the right holder is the employer, and the object is handover of the construction site, construction records and the like; (2) the duty arises upon termination itself, without any further agreement and not conditioned on settlement of the price - the employer may not refuse acceptance on a 'settle first, hand over later' basis, and the contractor may not refuse handover on the ground of unpaid price (price disputes go to settlement or litigation remedies); (3) if the contractor refuses to vacate, the employer may sue for handover and thereby fix the date of evacuation.
2. Evidence preservation before evacuation (Article 15, paragraph 2, verbatim)
'Before the contractor evacuates, where a party applies for evidence preservation, the people's court shall handle it in accordance with Article 84 of the Civil Procedure Law.' Basic frame of Civil Procedure Law Article 84: where evidence may be lost or become difficult to obtain later, a party may apply for preservation during the proceedings; in urgent circumstances, the application may be made before filing suit or applying for arbitration. The interval from termination to evacuation is a high-risk window in which the state of the site is about to change: completed quantities, defects in the completed works, the state of on-site materials and plant, and the construction interfaces can hardly be restored after demobilisation; fixing evidence before evacuation avoids later inability to prove 'whether the completed part is of acceptable quality' and 'which party caused the defects'.
3. Why the evacuation date matters: link to the start of the retention money return period
Fa Shi [2026] No. 12, Article 14, paragraph 1: 'Where a construction contract is terminated and the contractor claims that the retained work quality retention money be calculated on the base of the price payable to the contractor, the people's court shall support the claim. The return period of the retention money runs from the date the contractor evacuates; where the contract is terminated after the contractor's evacuation, it runs from the date of termination.' Paragraph 2: 'Where the construction contract is void and the works are incomplete, and the contractor claims that the retained work quality retention money be calculated on the base of the compensation payable to the contractor for the works at discounted value, the people's court shall support the claim. The return period of the retention money runs from the date the contractor evacuates.' Hence the 'date of evacuation' is the statutory starting fact for the retention money return period upon termination; its determination usually relies on site handover records, acknowledgment of receipt of records, demobilisation records signed by the employer or the supervising engineer, and correspondence, corroborated by preserved evidence; where termination occurs after evacuation, the starting point shifts to the date of termination, which is fixed under Civil Code Article 565 (terminated when the notice reaches the other party; where termination is asserted directly by suit or application for arbitration and confirmed, from service of a copy of the statement of claim or the arbitration application on the other party).
Scope and Limits
- The handover duty is confined to post-termination situations; where the contract is not terminated, site management and delivery of records are governed by the contract and the construction management rules, and Article 15 cannot be invoked directly.
- 'Evacuation' is a factual state, not a legal act: even without written handover, where personnel and plant have actually withdrawn and the employer has taken actual control of the site, evacuation may still be found; whether evacuation unit by unit or section by section can start the period separately is not addressed by the interpretation and adjudication diverges.
- Evidence preservation must meet the conditions of 'possible loss or later difficulty of obtaining', and usually requires security; the probative force of the preserved evidence remains subject to court review and does not substitute for quality expert assessment.
- Performance of the handover duty does not discharge the contractor's quality liability and repair duties for the completed works, nor affect its right to claim the unpaid price.
- Temporal effect: Fa Shi [2026] No. 12 takes effect on 30 June 2026 and applies to first-instance construction contract disputes newly accepted by the people's courts after effectiveness.
Further Reading
- SPC Interpretation (II) on Construction Contract Disputes (Fa Shi [2026] No. 12), Article 15 (post-termination site handover and pre-evacuation evidence preservation), Article 14 (retention money return period running from the evacuation date / termination date), Article 23 (effective date and scope of application to newly accepted cases).
- Civil Procedure Law of the PRC, Article 84 (conditions and timing of evidence preservation, and pre-suit preservation in urgent circumstances).
- Civil Code of the PRC, Article 565 (termination effective on service of the notice; termination on the date of service of a copy of the statement of claim), for fixing the termination date where termination follows evacuation.
- Official release pages (for verifying the original text): https://www.gov.cn/zhengce/202504/content_7021701.htm and https://www.gov.cn/gongbao/2025/issue_12006/202504/content_7021458.html
Keywords
- 法释〔2026〕12号
- 第十五条
- 移交施工现场
- 施工资料移交
- 证据保全
- 退场之日
- 民事诉讼法第八十四条