Settlement of works variations without signed instructions (qianzheng): five-tier determination rules, substitute evidence chains, and variation pricing principles

Signed instructions are not the only settlement basis. Whether an un-instructed variation can be settled depends on "who proposed the variation and whether traces of employer/supervisor approval exist": if not proposed by the contractor and instructions/drawings exist, or proposed by the contractor with either the employer's or the supervisor's consent → a determinate opinion can be issued and the amount settled; proposed by the contractor with drawings only and no confirmation → only an elective opinion, with risk; no confirmation and no drawings → costs should not be adjusted. Substitute evidence — design variation sheets, meeting minutes, supervisor records, photos/videos, etc. — can be collected; the deemed-acceptance rule for late verification and variation pricing principles can also be invoked.

Applicable Codes

  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • GB/T 51262-2017 建设工程造价鉴定规范
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引

Topic Positioning

The works variation was actually constructed but no signed instruction was processed — can the payment be settled? This card gives the judgment framework: the five-tier determination rules centered on "who proposed the variation and whether traces of employer/supervisor approval exist", combined with substitute evidence chains and variation pricing principles, for settlement audit and cost expert-determination practice.

Core Conclusions

Signed instructions are not the only settlement basis; the key is who proposed the variation and whether approval traces exist:

  • Not proposed by the contractor, with employer or supervisor instructions + design drawings → determinate opinion, normal settlement; instructions only or drawings only also support a determinate opinion with explanation.
  • Proposed by the contractor, with the consent of either the employer or the supervisor → determinate opinion with explanation.
  • Proposed by the contractor, with design drawings only and no employer/supervisor confirmation → elective opinion only; settlement at risk.
  • Proposed by the contractor, no confirmation and no drawings → costs should not be adjusted; no settlement. Where instructions are missing, a substitute evidence chain can be collected: design variation notices, drawing review minutes, written instructions or meeting minutes, supervisor logs and concealed-works acceptance records, photos and videos, material purchase orders, as-built drawing annotations, etc. (GB/T 51262-2017 Clause 5.9 lists various instruction situations: verbal instructions, written notices, BOQ inconsistencies, employer-caused suspension, etc.). Fallback rule: where the employer fails to verify or comment on the final account documents within the agreed time after receipt, they are deemed accepted (GB/T 50500-2024 Clause 10.3.8). Variation pricing itself does not depend on instructions: identical contract items take their all-in unit rates, similar items by reference, and where neither exists a new rate is set at reasonable cost + the agreed management and profit rates (T/ZBD 100.5-2023 Clause 3.1.8).

Applicable Boundaries

Applies to settlement audit and cost expert determination between employer and contractor. Contracts stipulating "no price adjustment without signed instructions" remain binding, but where employer consent to the works can be proven, judicial practice may still settle on actuals — only with stricter proof. Contractor-unilateral variations without any approval traces are not adjusted. Where both parties have jointly signed and confirmed totals, quantities, or labor/plant/material numbers, the signed content governs; only arithmetic or computational errors may be recalculated.

Further Reading

See T/ZBD 100.4-2023, Guideline for Cost Expert Determination of Construction Works, Clauses 4.6.3, 4.6.6; GB/T 51262-2017, Code for Cost Expert Determination of Construction Works, Clause 5.9; GB/T 50500-2024 Clause 10.3.8; T/ZBD 100.5-2023, Guideline for Settlement Audit of Construction Works, Clause 3.1.8; see also the Supreme People's Court, Interpretation (I) on Construction Contract Disputes, Article 19 (actual quantities may be confirmed by other evidence absent signed instructions).