Price adjustment for quantity increases caused by the contractor's construction-stage design development under an EPC lump-sum contract: no adjustment in principle; adjustment only where the difference constitutes an employer-required variation or arises from employer causes
No adjustment in principle; adjustment only by exception. Where the contractor, as required by the contract, carries out construction-stage design development of the contract drawings and the design development drawings differ from the contract drawings, the contract price shall not be adjusted unless otherwise agreed in the contract or otherwise required by the employer (GB/T 50500-2024 Clause 3.3.9); however, where the difference constitutes a variation required by the employer, the additional costs affected shall be calculated and adjusted under Clauses 7 to 9 of the standard. The construction cost expert assessment position is consistent: where the contractor carries out design development and requests adjustment of the all-in unit rate, the expert assessor generally will not adjust it, unless the contract provides that the contractor's design development drawings serve as the basis for construction payment settlement (T/ZBD 100.4-2023 Clause 4.4.6). Where the difference arises from employer causes (errors in the Employer's Requirements or in base data, changes in laws, regulations and policies, or employer-approved variations) or constitutes additional works outside the contract scope, the price may be adjusted as prescribed.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.25条、第1.0.2条、第3.3.1~3.3.3条、第3.3.9条、第8.2.3条、第8.10.1条
- T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.4.6条、第4.6节
- 建市〔2020〕96号 建设项目工程总承包合同(示范文本)GF-2020-0216 通用合同条件 第5.1.3款、第5.2.1款、第5.6款、第13.1.1款、第13.3.3款
- 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二) 第九条、第二十三条 https://www.court.gov.cn/fabu/xiangqing/504221.html
- 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一) 第十九条
- 中华人民共和国主席令第45号 中华人民共和国民法典 第五百四十三条、第五百三十三条
Scope and Positioning
This card defines the decision rules and exception gateways for whether the contract price can be adjusted when, during performance of a fixed lump-sum (including EPC general contracting) contract, the contractor completes construction-stage design development as required by the contract, differences arise between the design development drawings and the contract drawings, and quantities increase as a result. It applies to settlement, variation and claim, and construction cost expert assessment scenarios.
Core Conclusion
1. No adjustment in principle: design development is a contractual obligation of the contractor, and the quantity difference falls within its lump-sum risk.
GB/T 50500-2024 Clause 3.3.9 provides: where the works contracted need re-measurement and re-pricing before payment, the contract price shall be calculated and adjusted under Clauses 7, 8 and 9 of the standard. However, where the contractor, as required by the contract, carries out construction-stage design development of the contract drawings and this causes differences between the design development drawings and the contract drawings, the contract price shall not be adjusted unless otherwise agreed in the contract or otherwise required by the employer. The second paragraph further provides that the total contract price shall not be adjusted on account of differences between the design development drawings completed by the contractor as required by the contract and the contract drawings, but where the relevant difference constitutes a variation required by the employer, the additional costs affected shall be calculated and adjusted under the relevant provisions of Clauses 7 to 9 of the standard.
The rationale lies in the definition of construction design development (GB/T 50500-2024 Clause 2.0.25): design development is 'the design activity for which the contractor is responsible under the contract after contract award, refining, supplementing and completing the contract drawings on the premise of not changing the scope of works, functional use, technical standards and codes required by the contract drawings and contract specifications'. Design development is thus meant to be completed without changing scope, function or technical standards, and the quantity increases or decreases it causes by itself do not constitute a change in the fundamental contractual conditions.
2. Negative scenarios (no price adjustment)
Refinement, supplementation and completion solely for construction feasibility, joint details, rebar adjustment or substitution of materials of equivalent grade, without changing the scope of works/functional use/technical standards but with increased quantities - no adjustment (GB/T 50500-2024 Clause 3.3.9 paragraph 1; Clause 2.0.25).
Rework or quantity increases caused by the design development documents' own errors, omissions, ambiguities, contradictions, insufficiencies or other defects - the contractor corrects them at its own cost, and the resulting delay and necessary increased costs are borne by the contractor. Model Contract for Construction Project General Contracting GF-2020-0216 Clause 5.6: 'Where the contractor's documents contain errors, omissions, ambiguities, contradictions, insufficiencies or other defects, the contractor shall, whether or not consent was obtained under this clause, at its own cost rectify the defects and works problems arising from the foregoing ... Delay of the works and necessary increased costs caused by re-submitting documents for review under this clause are borne by the contractor, except where errors in the Employer's Requirements cause errors in the contractor's documents ...'
The employer has 'reviewed and consented' to the design development drawings but has not issued a variation instruction - review and consent do not amount to a variation. GF-2020-0216 Clause 5.2.1 final paragraph: 'The employer's review of and consent to the contractor's documents shall not be construed as a modification or alteration of the contract, nor do they relieve or exempt the contractor from any of its duties and obligations.' Clause 13.1.1: 'The contractor may implement a variation only after receiving a variation instruction. Without permission, the contractor shall not vary any part of the works on its own initiative.'
Under a lump-sum contract, defects in the priced bill of quantities and deviations between billed quantities and the contract drawings (except unit-rate priced items with provisional quantities) - no adjustment. GB/T 50500-2024 Clause 8.2.3: for works under a lump-sum contract, the contract price and time for completion shall not be adjusted for defects in the contract bill; where the contract provides divisional and sub-divisional works items whose billed quantities are provisional and priced at unit rates, adjustment may follow Clauses 7.2.1 and 8.2.1. Clause 3.3.3 item (2) likewise lists 'defects in the priced bill of quantities of works under a lump-sum contract (except provisional-quantity bill items priced at unit rates) ...' among the risks borne by the contractor.
Increased costs or quantities caused by the contractor changing for its own reasons its implementation scheme, construction plant, construction techniques or organisational management (GB/T 50500-2024 Clause 3.3.3 items (4) and (5)), and market price movements within the agreed scope and band (item (7)) - no adjustment.
3. Positive scenarios (price adjustable)
A difference caused by design development for which the Engineer issues a variation instruction signed off by the employer, constituting a variation required by the employer - valued as a variation. Basis: GB/T 50500-2024 Clause 3.3.9 paragraph 2; Clause 3.3.2 item 3 lists 'variations approved by the employer' among employer-borne risks, requiring 'timely adjustment of the corresponding contract price under the relevant provisions of Clause 8 of the standard'. Variation valuation follows GF-2020-0216 Clause 13.3.3.1: where the contract contains a schedule of prices, (1) where the schedule contains items applicable to the varied works, the rates and prices of those items apply; (2) where there are no applicable but similar items, the rates or prices of similar items may be referenced within a reasonable range; (3) where there are neither applicable nor similar items, new rates or prices shall be derived and applied on a cost-plus-profit basis.
The difference arises from employer causes - errors in the Employer's Requirements or in the project's original data and base data (GF-2020-0216 Clause 5.6 final sentence; GB/T 50500-2024 Clause 3.3.2 item 2); changes in laws, regulations and policies (Clause 3.3.2 item 5; GF-2020-0216 Clause 5.1.3: where after the base date the state promulgates new mandatory codes or standards causing changes in the contractor's costs, the employer shall reasonably adjust the contract price, and where delay results the time for completion shall be reasonably extended); employer-required acceleration, suspension or deferral of works (Clause 3.3.2 item 4).
Additional works outside the contract scope - under GB/T 50500-2024 Clause 8.10.1: where the contractor completes additional works outside the contract scope at the employer's request, the parties may price them per the bill itemisation requirements, measurement rules and supplementary measurement rules of the national and industry quantity take-off standards agreed in the contract, together with the contract unit rates and tender pricing level, or may renegotiate measurement and pricing rules for the additional works, and sign an additional-works contract or supplementary agreement.
The contract provides that the contractor's design development drawings are the basis for construction payment settlement - adjustment then follows the contract (the proviso of T/ZBD 100.4-2023 Clause 4.4.6).
4. Construction cost expert assessment and judicial positions
T/ZBD 100.4-2023 Clause 4.4.6: where the parties conclude a unit-rate contract and the employer carries out design development, and the contractor requests adjustment of the all-in unit rate, the expert assessor finding a variation constituted shall assess the relevant content under Section 4.6 of the guideline (assessment of variation disputes) and under the variation clauses agreed in the contract and the variation records; where the contractor carries out design development and requests adjustment of the all-in unit rate, the expert assessor will generally not adjust it, unless the contract provides that the contractor's design development drawings are the basis for construction payment settlement.
Judicially, for contracts to be settled at fixed prices, a party's request to adjust the project price for significant changes in labour costs or the prices of principal building materials during the construction period is not supported, unless the parties agreed otherwise or the change of circumstances provision of the Civil Code Article 533 applies (Fa Shi [2026] No. 12 Article 9). Where the contract stipulates pricing standards or methods, the agreement prevails; where a design change causes changes in quantities or quality standards and the price of that part cannot be agreed, settlement may be made by reference to the pricing methods or standards published by the local construction administrative authority at the place of the works at the time of contracting (Fa Shi [2020] No. 25 Article 19).
Applicable Boundaries
- Applies to projects under fixed lump-sum or general contracting (EPC) contracts where the contractor is responsible for construction drawings or design development; GB/T 50500-2024 Clause 1.0.2 provides that the standard applies to pricing activities in the tendering, contracting and implementation stages of construction works, and works adopting EPC and similar delivery modes may apply it by reference where they comply with the relevant provisions.
- 'No adjustment' presupposes that the difference has not changed the scope of works, functional use or technical standards and codes, and does not arise from employer causes; once the difference substantially changes those contents and is confirmed by the employer, the matter must pass through the variation procedure and cannot still be refused on lump-sum grounds.
- A variation is formally constituted by a variation instruction or variation records signed off by the employer; the employer's mere review and consent to the design development drawings does not constitute a variation.
- Exemption for errors in the contractor's documents is limited to cases caused by errors in the Employer's Requirements themselves; all other defects are corrected at the contractor's cost.
- Under a unit-rate contract where the employer carries out design development constituting a variation, variation valuation applies rather than this card's principle; this card targets design development carried out by the contractor itself.
- Claims to adjust price for significant changes in labour cost or principal material prices under fixed pricing are unsupported unless otherwise agreed or qualifying as change of circumstances; do not conflate them with quantity differences from design development.
Further Reading
- GB/T 50500-2024, China national pricing standard for BOQ: Clause 2.0.25 (definition of construction design development), Clause 1.0.2 (scope), Clauses 3.3.1-3.3.3 (pricing risk allocation), Clause 3.3.9 (design development differences and contract price adjustment), Clause 7, Clause 8 (incl. 8.2.3 lump-sum BOQ defects; 8.10.1 additional works), Clause 9.
- T/ZBD 100.4-2023 Guideline for Construction Cost Expert Assessment Practice: Clause 4.4.6 (assessment position on design development price adjustment), Section 4.6 (assessment of variation disputes).
- Model Contract for Construction Project General Contracting GF-2020-0216 (Jian Shi [2020] No. 96), general conditions: Clause 5.1.3 (changes in laws and standards), Clause 5.2.1 (review of contractor's documents), Clause 5.6 (errors in contractor's documents), Clause 13.1.1 (employer's right to vary), Clause 13.3.3 (valuation of variations).
- Fa Shi [2026] No. 12, SPC Interpretation (II) on construction contract disputes, Articles 9 and 23, original text at https://www.court.gov.cn/fabu/xiangqing/504221.html ; Fa Shi [2020] No. 25, Interpretation (I), Article 19.
- Civil Code Article 543 (contract may be varied by mutual agreement).
Keywords
- 施工深化设计
- 固定总价合同
- variation
- adjustment of the contract price
- GB/T 50500-2024 第3.3.9条
- 承包人文件错误
- additional works
- construction cost expert assessment (judicial appraisal)