Quantity-price risk boundaries compared across lump-sum, unit-rate (re-measurable) and cost-plus contracts

The three contract types form a gradient of quantity and price risk transferred from contractor to employer: lump sum = both quantity and price fixed (the contractor bears quantity variances and cost fluctuations within the agreed range, except variations, changes in laws and regulations, and force majeure); unit-rate (re-measurable) = unit rate fixed, quantities measured as executed (BOQ errors / omissions and quantity variances lie with the employer); cost-plus = costs reimbursed as actually incurred (nearly all quantity and price risk lies with the employer). Basis: MOC Decree No. 107, Article 12; GB/T 50500-2024, Clauses 3.3.1-3.3.8; GB/T 50875-2013, Clauses 3.3.6-3.3.8.

Applicable Codes

  • 建设部令第107号《建筑工程施工发包与承包计价管理办法》
  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 50875-2013 建设工程造价术语标准

Topic Positioning

Compares the 'transfer boundary of quantity and price risk between employer and contractor' across lump-sum, unit-rate (re-measurable) and cost-plus contracts, answering 'which risks lie with whom and under what conditions adjustment is allowed', for selecting the contract pricing method and judging settlement disputes.

Core Conclusions

The three types form a risk-transfer gradient: lump-sum, unit-rate (re-measurable), cost-plus, with risk shifting progressively from contractor to employer.

  • Lump sum (quantity and price both fixed): the contractor quantifies from the construction drawings itself and fixes the total price; the BOQ quantities are the final quantities, and no adjustment is made for variances except variations; cost fluctuations within the agreed range and the accuracy of the bill of preliminaries lie with the contractor. But this is not a contract with uncapped risk allocation to one party - GB/T 50500-2024, Clause 3.3.1, prohibits clauses imposing 'uncapped risk allocation to one party' or 'all risks'; cost fluctuations in labour, principal materials, fuel and power beyond the agreed range (5% if not agreed) are adjusted per Annex A, with the difference subject to VAT only, with no management fee or profit (Clause 8.7.6).
  • Unit-rate (re-measurable) contract (unit rate fixed, quantities as executed): the all-in unit rate is fixed within the agreed scope and is adjusted beyond the agreed conditions; quantities are measured as executed. The essential difference from lump sum lies in BOQ errors / omissions (including incomplete item descriptions, i.e. work item specifications): under unit-rate contracts they lie with the employer, and the all-in unit rate is re-rated against the actual item descriptions to adjust the price; under lump-sum contracts they lie with the contractor and no adjustment is made (except items with provisional quantities). Price adjustments for cost fluctuations beyond the range lie with the employer.
  • Cost-plus (reimbursed as incurred): the contractor bears no risk of quantity or price changes; costs are determined per the agreed measurement and pricing basis plus remuneration per the agreed method; nearly all quantity, price and market risk lies with the employer. Suitable only for exceptionally complex works whose technical solutions cannot be predetermined, where competitive tendering is impossible or the schedule is extremely tight; the definable cost scope and remuneration form (fixed fee, fixed percentage, or bonus) must be strictly defined.

Common baseline (unchanged by pricing form): changes in laws, regulations and policy; variations, acceleration or suspension approved by the employer; and errors in employer-furnished source data are all employer-side adjustable items; force majeure is allocated per Clause 8.11.14.

Applicable Boundaries

Applies to pricing and settlement disputes in works contracting, premised on a clear contractual allocation of risk; more specific contractual provisions prevail. Not applicable to: single-item cost fluctuation adjustment details (see the dedicated price adjustment card), rules for adjustment of provisional prices after procurement, or engineering, procurement and construction (EPC/Turnkey) pricing modes.

Further Reading

  • MOC Decree No. 107, Measures for the Administration of Pricing in Contracting and Subcontracting of Building Works, Article 12 (fixed price / adjustable price / cost-plus classification)
  • GB/T 50500-2024, China national pricing standard for BOQ (Standard for Valuation of Construction Works with Bills of Quantities), Clauses 3.3.1-3.3.8 (overall allocation of risk framework), Clause 8.7.6 and Annex A (price adjustment rules for fluctuation), Clause 8.11.14 (force majeure allocation)
  • GB/T 50875-2013, Standard for Construction Cost Terminology, Clauses 3.3.6-3.3.8 (definitions of the three contract types)