Hierarchy of effect and order of interpretation when tender documents, bid documents and the awarded contract conflict over material price adjustment (adjustment of the works price): substantive content follows the tendering and bidding documents; conflicts that are not substantive follow the priority order of contract documents (particular conditions first; later signing of the same class first) and the limits of those rules
A price-adjustment clause is part of the pricing and adjustment method of the 'works price' and so falls within the reach of substantive content: where the awarded contract differs from the tender documents, bid documents or letter of acceptance, those documents govern settlement of the works price (Bidding Law Art. 46; Implementation Regulations Art. 57; Fa Shi [2020] No. 25 Arts. 2 and 22). Internal conflicts not amounting to substantive departure are construed by the priority order of contract documents (GF-2017-0201 Clause 1.5: contract agreement > letter of acceptance > letter of tender with appendices > particular conditions > general conditions > technical standards > drawings > priced BOQ > other documents; for documents of the same class the latest signing prevails), that is 'particular over general, later over earlier within the same class'; but 'later over earlier' is a rule of interpretation, not a power of variation, and cannot give variation effect to a later agreement that departs from substantive content (Civil Code Art. 544: a variation whose content is unclear is deemed not varied). Where the position still cannot be fixed, construe comprehensively under Civil Code Arts. 142 and 466 and Fa Shi [2023] No. 13 Art. 1.
Applicable Codes
- 中华人民共和国招标投标法(主席令第21号,2017修正)第45条、第46条
- 中华人民共和国招标投标法实施条例(国务院令第676号,2017修订)第57条
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第2条、第22条
- 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第2条、第9条、第23条
- 最高人民法院关于适用《中华人民共和国民法典》合同编通则若干问题的解释(法释〔2023〕13号)第1条、第2条
- 中华人民共和国民法典第142条、第466条、第533条、第544条
- 建设工程施工合同(示范文本)GF-2017-0201 第1.4.3条、第1.5条、第11.1款、第12.1款
- 建设工程工程量清单计价标准 GB/T 50500-2024 第8.7.2条、附录A 第A.2.1条、附录G 表G.2.1-1
Topic positioning
This card answers a frequent dispute: where the tender documents, the bid documents and the awarded contract (including its particular conditions) conflict over material price adjustment - the scope of adjustable materials, the base price, the risk band, the adjustment formula - which document prevails. It gives a reusable three-step path: first characterise (does the conflict touch substantive content), then rank (between which layers of documents the conflict sits), and finally interpret (the priority order of contract documents plus the statutory interpretation rules), and it bounds the two everyday rules 'particular terms over general terms' and 'later over earlier'.
Core conclusions
Step 1 - characterise: an adjustment clause is substantive 'works price' content. Bidding Law Art. 46: 'The tenderer and the winning bidder shall, within 30 days from the issue of the letter of acceptance, conclude a written contract in accordance with the tender documents and the winning bidder's bid. The tenderer and the winning bidder shall not conclude any other agreement that departs from the substantive content of the contract. Where the tender documents require the winning bidder to submit performance security, the winning bidder shall submit it.' Implementation Regulations Art. 57: 'The tenderer and the winning bidder shall conclude a written contract in accordance with the Bidding Law and these Regulations; the main terms of the contract - subject matter, price, quality, period of performance - shall be consistent with the tender documents and the winning bidder's bid. They shall not conclude any other agreement departing from the substantive content of the contract. The tenderer shall refund the bid security of the winning and unsuccessful bidders plus bank interest on current deposits within 5 days after the written contract is signed.' The adjustment mechanism decides the pricing method and the adjustment method of the settlement price, so it is substantive content under 'price'; an awarded contract or particular conditions that differ from the tender and bid documents therefore cannot serve as the settlement basis.
Step 2 - rank: the three documents in layers. The tender documents set the conditions, the bid responds to them, and the letter of acceptance is an acceptance carrying immediate legal effect. Bidding Law Art. 45: 'After the winning bidder is determined, the tenderer shall issue the letter of acceptance to it and notify all unsuccessful bidders of the award result. The letter of acceptance is legally binding on the tenderer and the winning bidder. Where, after the letter of acceptance is issued, the tenderer alters the award result or the winning bidder abandons the winning project, it shall bear legal liability under the law.' A bid's deviation from the substantive requirements of the tender documents does not gain a rank above the tender documents by winning.
Step 3 - resolve: two layers of rules.
(1) Statutory layer (inconsistency on substantive content): Fa Shi [2020] No. 25 Art. 22: 'Where the construction contract signed by the parties differs from the tender documents, bid documents or letter of acceptance as to works scope, construction duration, quality or price, and a party requests that the tender documents, bid documents and letter of acceptance be taken as the basis for settling the works price, the court shall support it.' Art. 2(1) of the same interpretation: 'Where the works scope, construction duration, quality, price or other substantive content agreed in another construction contract signed by the tenderer and the winning bidder is inconsistent with the awarded contract, and a party requests that rights and obligations be determined by the awarded contract, the court shall support it.' Art. 2(2): 'Where the tenderer and the winning bidder sign contracts outside the awarded contract - purchasing the works being built at prices clearly above market, building housing support facilities without charge, allowing rebates, donating property to the employer - thereby covertly reducing the works price, and a party requests confirmation that such contract is invalid on the ground that it departs from the substantive content of the awarded contract, the court shall support it.'
(2) Contractual layer (internal conflicts not amounting to substantive departure): GF-2017-0201 Model Construction Contract, Clause 1.5 [priority order of contract documents]: 'The documents forming the contract are mutually explanatory and mutually illustrative. Unless otherwise agreed in the particular conditions, the priority order for interpreting the contract documents is: (1) the contract agreement; (2) the letter of acceptance (if any); (3) the letter of tender and its appendices (if any); (4) the particular conditions and their attachments; (5) the general conditions; (6) technical standards and requirements; (7) drawings; (8) the priced bill of quantities or the budget; (9) other contract documents. The supplements and revisions made by the parties to each document form part of that document; for documents belonging to the same class of content, the latest signing prevails. Documents formed in the course of concluding and performing the contract that relate to it all form part of the contract documents and are given their priority order according to their nature.'
The limits of the two everyday rules (easily misapplied)
- 'Particular terms over general terms' (particular conditions over general conditions): Clause 1.5 itself is premised on 'unless otherwise agreed in the particular conditions', so the particular conditions do prevail on conflict; but that priority is internal to the contract - the particular conditions must not violate mandatory provisions of law, nor depart from the substantive content of the tender and bid documents; a particular condition that itself constitutes such a departing side agreement still cannot serve as the settlement basis. Note also Model Clause 1.4.3: where the employer's technical standards or functional requirements for the works are higher or stricter than current national, industry or local standards, they must be specified in the particular conditions; unless otherwise agreed there, the contractor is deemed to have fully foreseen the complexity of those standards and requirements before signing, and the contract price includes the resulting costs.
- 'Later over earlier': applies only to 'documents belonging to the same class of content' and is a rule of interpretation, not a rule conferring power to vary. It cannot be used to give variation effect to a later agreement that departs from the substantive content of the awarded contract; in practice it must also be checked against Civil Code Art. 544 - 'Where the content agreed by the parties for a variation of the contract is unclear, the contract is deemed not varied.'
Residual interpretation rules (where the path above still cannot fix the meaning) Civil Code Art. 466: 'Where the parties dispute the understanding of a contract clause, the meaning of the disputed clause shall be determined under Art. 142(1) of this Code. Where the contract text is made in two or more languages and agreed to have equal effect, the words of each text are presumed to have the same meaning; where the words used differ, the clause is interpreted according to the related clauses of the contract, its nature and purpose, usage and the principle of good faith.' Civil Code Art. 142(1): 'The interpretation of an expression of intent made to another person shall follow the words used, read together with the related clauses, the nature and purpose of the act, usage and the principle of good faith, to determine the meaning of the expression of intent.' Fa Shi [2023] No. 13 Art. 1: when the court interprets a contract clause under Arts. 142(1) and 466(1), it takes the ordinary meaning of the words as the basis, combines the related clauses, the nature and purpose of the contract, usage and good faith, and refers to the contracting background, the negotiation process and performance conduct; where evidence proves that the parties shared an understanding different from the ordinary meaning of the words, a plea by one party to understand the clause by the ordinary meaning is unsupported; where a clause admits two or more interpretations that may affect its validity, the court chooses the one favourable to validity; for gratuitous contracts it chooses the interpretation lighter for the debtor. Art. 2 of the same interpretation: usage covers (1) the habitual practice between the parties in their dealings and (2) practice usually adopted in the locality, the field or the trade and known or ought to be known to the counterparty when contracting; the party asserting the usage bears the burden of proof.
Substantive consequences where the conflict cannot be dissolved by 'which prevails'
- Fixed-price contract with no adjustment agreed: Fa Shi [2026] No. 12 Art. 9: 'Where the construction contract agrees to settle the works price on a fixed basis and a party requests adjustment of the works price on the ground of major changes in labour costs or key material prices during the agreed construction duration, the court will not support it, unless the parties agreed otherwise or Civil Code Art. 533 on change of circumstances applies.'
- Default where nothing or nothing clear is agreed: GB/T 50500-2024 Clause 8.7.2 - 'Where the market prices of the labour, materials, or fuel and power within the plant and tool costs that the contract agrees to adjust fluctuate beyond the band agreed in the contract, and no band is agreed or the agreement is unclear, then where the market price fluctuation exceeds 5%, the contract price may be adjusted by one of the methods in Annex A of this standard.' Annex A Clause A.2.1 gives the published-price-information adjustment formula and the base price C0 (the market price level 28 days before the tender deadline, or 28 days before contract signing for works not tendered; the source may be the market price adopted for the tender price ceiling, the quarterly or monthly published price information issued by the cost administration body, or the winning prices of similar works under the same conditions in the same period from trading centres), and provides that the price method, source and risk-band coefficient are assessed and determined by the employer and stated in the tender documents, and that a contractor objecting shall request clarification or correction within the set time before bidding.
- The model text's own adjustment arrangement (GF-2017-0201 Clause 11.1): labour unit rates adjust per the documents on labour costs issued by the provincial or industry construction authority or its authorised cost administration body (except where the rate quoted exceeds the published rate); material and equipment prices adjust against the base price in three cases, with a 5% risk band, only the part beyond the band being adjusted in fact; the contractor must submit the quantities and the new unit rates to the employer for verification before purchase, no reply within 5 days of receipt is deemed approval, and materials purchased without prior verification may be refused adjustment; the base price means the price given by the employer in the tender documents or the particular conditions, in principle compiled from published price information. Clause 12.1: both unit-rate contracts and lump-sum contracts shall agree in the particular conditions the risk scope, the method of pricing the risk cost, and the price-adjustment method beyond the risk scope.
- The awarded contract itself may be invalid: Fa Shi [2026] No. 12 Art. 2 - 'Where, before the winning bidder is determined, the tenderer and a bidder negotiate on substantive content such as works scope or price in the form of letters of intent, minutes or supplementary agreements and that bidder wins, or the employer and the contractor agree a construction contract and then conclude a construction contract with the contractor through a tendering procedure, the court shall find the awarded contract invalid under the Bidding Law's prohibitions on collusive bidding and on negotiating substantive content in advance.' The question is then no longer 'which prevails' but the route of compensation for an invalid contract.
Versions and effective dates (must be verified when citing)
- Bidding Law: Presidential Decree No. 21; the current text is the 2017 amendment; Arts. 45 and 46 as quoted above.
- Implementation Regulations: State Council Decree No. 676, 2017 revision; Art. 57 as quoted above.
- Construction Interpretation (I): Fa Shi [2020] No. 25; Arts. 2 and 22.
- Contract General Provisions Interpretation: Fa Shi [2023] No. 13; Arts. 1 and 2.
- Construction Interpretation (II): Fa Shi [2026] No. 12; Art. 23: 'This interpretation takes effect on 30 June 2026. For first-instance construction contract dispute cases newly accepted by courts after this interpretation takes effect, this interpretation applies. Where SPC interpretations issued before this interpretation are inconsistent with it, this interpretation prevails.'
- Model Construction Contract GF-2017-0201: Clauses 1.4.3, 1.5, 11.1 and 12.1.
- BOQ Pricing Standard GB/T 50500-2024: Clause 8.7.2; Annex A Clause A.2.1.
Scope and limits
- Applies only to works awarded through a tendering procedure (mandatory and voluntary tendering alike); for directly awarded projects there is no baseline of 'awarded contract versus tender and bid documents' - the contract is the final meeting of minds, and the first layer of rules in this card does not apply.
- 'The tender and bid documents prevail' addresses substantive content only (works scope, construction duration, quality, works price); conflicts over communications and dispute-resolution procedure are still handled by the priority order of contract documents and the interpretation rules.
- Particular conditions prevail over general conditions on the premise that the particular conditions contain an express agreement that neither departs from substantive content nor violates mandatory provisions.
- 'Later signing of the same class prevails' requires the same class of content (for instance two revisions of the same kind of clause); across different classes the Clause 1.5 ranking governs and later signing alone does not prevail.
- Fa Shi [2026] No. 12 applies only to first-instance cases newly accepted by courts on or after 30 June 2026; cases accepted earlier are handled under the rules then in force; where the newer interpretation is inconsistent with an older one, the newer prevails.
- The rule refusing adjustment for fixed-price contracts without an adjustment clause admits two exceptions - contrary agreement, or meeting Civil Code Art. 533 on change of circumstances - and cannot be broken through by 'material prices rose sharply' alone.
- Where the parties later reach a lawful and valid variation agreement (content clear, no departure from substantive content, statutory procedures followed), the varied agreement governs and the ranking rules in this card no longer apply directly.
Further reading
- Bidding Law of the PRC (Presidential Decree No. 21, 2017 amendment) Arts. 45 and 46; Implementation Regulations (State Council Decree No. 676, 2017 revision) Art. 57.
- SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25) Arts. 2 and 22; Interpretation (II) (Fa Shi [2026] No. 12) Arts. 2, 9 and 23; SPC Interpretation on the General Provisions of the Contract Part (Fa Shi [2023] No. 13) Arts. 1 and 2.
- Civil Code Arts. 142, 466, 533 and 544.
- Model Construction Contract (GF-2017-0201): Clause 1.4.3, Clause 1.5 (priority order of contract documents), Clause 11.1 (adjustment for market price fluctuation), Clause 12.1 (contract price form).
- BOQ Pricing Standard (GB/T 50500-2024): Clause 8.7.2 (adjustment of the contract price), Annex A Clause A.2.1 (the published-price-information adjustment method and the base price C0), Annex G Table G.2.1-1 (schedule of price-adjustable key materials provided by the contractor).
- Practice point: when writing the adjustment mechanism into the particular conditions, say everything in one pass - the adjustable material list and quantity rules, the source, issuing body and specific quarter or month of the base price C0, the risk band r, the adjustment formula and the chosen method, the adjustment periods and the claim and confirmation deadlines - and keep it consistent with what the tender and bid documents state; otherwise on conflict the tender and bid documents prevail and the side arrangements in the particular conditions fall away.