Incorporating design changes (designer-issued variations) into the final account: position of the final account price item, pricing ladder, and procedural requirements
Once a design change (designer-issued variation) is confirmed and established, its price is determined by the ladder 'identical contract item -> similar item -> negotiated rate build-up' and is included in the final account documents as item 9 of the final account price, 'increase/decrease due to variations'; the variation adjustment price certified and signed off by both parties is paid concurrently with progress payments and stage settlement payments during construction, and the certified and signed-off stage settlement price serves as the basis for the final account where the contract has no special agreement.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- 建设部令第107号 建筑工程施工发包与承包计价管理办法
- GB/T 50326-2017 建设工程项目管理规范
- GB/T 51095-2015 建设工程造价咨询规范
- DB42/T 823-2021 建设工程造价咨询质量控制规范
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- 财建〔2004〕369号 建设工程价款结算暂行办法
Topic Positioning
The path by which a design change (designer-issued variation), once confirmed and established, is incorporated into the final account: final account itemization, pricing ladder, procedural linkage, and documentation requirements.
Core Conclusions
(1) Itemization: the final account price is itemized per GB/T 50500-2024 Clause 10.3.2; design changes correspond to item 9, 'increase/decrease due to variations', listed alongside the contract BOQ total, provisional sums, provisional sums for specified materials / nominated works, and claims, with separate accounting per variation order. (2) Pricing ladder (agreed terms prevail, Clause 1.0.3): where the contract has an identical item, use the contract all-in unit rate; where no identical item exists but a similar one does, refer to the similar unit rate; where neither exists, carry out a rate build-up based on reasonable cost plus the agreed management fee and profit; where a lump-sum contract unit rate is applicable to the variation, adjust the price according to the variation quantities; otherwise negotiate. (3) Procedural linkage: certified variation prices are paid concurrently with progress payments and stage settlement payments during construction; certified prices for stage settlement during construction serve as the basis for the final account absent special agreement (10.3.1); if the employer fails to reply within the time limit, with no agreed limit, it is deemed accepted after 28 days (Decree No. 107, §16). (4) Documentation chain: the basis for settlement includes the contract, as-built drawings and variation documents, technical data, pricing documents, and site instruction / variation record and claim materials (GB/T 50326-2017 §18.3.3); the audit requires complete variation orders, ledgers, declaration documents, pre-variation drawings, and completion confirmation documents.
Applicable Boundaries
Applies to settlements of design changes (designer-issued variations) issued by the design unit via drawings or notices and confirmed as established, with contractual agreement taking precedence; variations without instruction/drawing/confirmation traces are not covered; settlements upon contract termination and judicial appraisals are subject to separate rules.
Further Reading
GB/T 50500-2024 §10.3.2, §10.3.1, §7.1.8, §1.0.3; Ministry of Construction Decree No. 107 §16; GB/T 50326-2017 §18.3.3; GB/T 51095-2015 §8.2.4; DB42/T 823-2021 §8.1.8; T/ZBD 100.5-2023 §3.1.8; Cai Jian [2004] No. 369 §16.