adjustment for cost fluctuation
- 01
Main-material price surge beyond the risk band: sequencing between GB/T 50500-2024 Section 8.7/Appendix A price adjustment and Civil Code Article 533 change of circumstances
When main-material prices surge far beyond the contractual risk band, fi…
《中华人民共和国民法典》第五百三十三条(2021年1月1日施行)《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》法释〔2026〕12号 第九条(2026年6月30日施行)《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》法释〔2020〕25号 第二十八条2026-11-06 - 02
The relationship between the risk allowance inside the all-in unit rate and contractual price adjustment for fluctuation: within the band the risk allowance absorbs the movement, beyond the band only the excess is adjusted, and the two are never counted twice
The risk allowance and contractual price adjustment are a two-stage allo…
GB 50500-2013 建设工程工程量清单计价规范 第2.0.8条(综合单价)、第2.0.9条(风险费用)、第3.4.3条、第5.2.2条、第6.2.2条、第9.8.1~9.8.3条、App. A.2.3、App. L.2/L.3GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条、第3.1.6条、第3.2.2条、第3.3.1条、第3.3.3条、第3.3.5条、第8.7.2条、第8.7.6条、App. A.1、App. A.2.4、App. G.22026-10-25 - 03
Quantity-price risk boundaries compared across lump-sum, unit-rate (re-measurable) and cost-plus contracts
The three contract types form a gradient of quantity and price risk tran…
建设部令第107号《建筑工程施工发包与承包计价管理办法》GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 建设工程造价术语标准2026-09-25 - 04
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes pri…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51290-2018 建设工程造价指标指数分类与测算标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 05
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the con…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第8.7.1条、第8.8.1条GB/T 50500-2024 App. A.1.6、A.2.1、A.2.42026-09-25 - 06
Framework for distinguishing quantity risk from price risk in contracts: risk objects, responsible parties, and quantified trigger lines (GB/T 50500-2024)
Quantity risk governs "how much is built" (BOQ defects, quantity changes…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.3.1~3.3.3条GB/T 50500-2024 第8.7.1~8.7.6条GB/T 50500-2024 第8.9.1~8.9.2条2026-09-25 - 07
Order of applicable bases for material price adjustment: contract agreement prevails, pricing standard as fallback (GB/T 50500-2024 "agreement governs" and the 5% band rule)
Material price adjustment follows the contract agreement first (agreemen…
GB/T 50500-2024 建设工程工程量清单计价标准 第1.0.3、3.3.5、3.4.4、8.7.2条及App. A、App. G2026-09-25 - 08
Statutory boundaries of what a "lump-sum price" actually covers: dual quantity-and-price lump sums and non-lumpable events (GB/T 50500-2024 / GB/T 50875-2013)
In practice a "lump-sum price" corresponds to a fixed total price, whose…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51262-2017 建设工程造价鉴定规范2026-09-25