Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point

The tender price ceiling (employer's maximum acceptable price) takes prices at the price level of the preparation period: use the latest issue (month/quarter) of construction cost price information published as at the date of completion of preparation, noting the issue in the deliverable; where a difference from actual construction-period conditions exists, adjust reasonably (GB/T 50500-2024 Clause 5.2.9). "28 days before the tender deadline" (for works not subject to tendering, 28 days before the date of contract signing) is the lock-in time point for the contractual adjustment base price C₀ in Appendix A.2.1, used for adjustment for cost fluctuation after award, and is unrelated to price-taking for the tender price ceiling.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51290-2018 建设工程造价指标指数分类与测算标准
  • GB/T 50875-2013 工程造价术语标准

Topic Positioning

Answers "which issue of price information should be used when preparing the tender price ceiling": price-taking is anchored to the latest published issue as at the date of completion of preparation, and it clarifies the two easily confused time points — that one and the "28 days before the tender deadline" adjustment base price.

Core Conclusions

The standard does not specify a particular month; the principle is the "price level of the preparation period": (1) the tender price ceiling adopts the latest issue (month/quarter) of construction cost price information published as at the date of completion of preparation, with the time base anchored to the date of completion of the deliverable (GB/T 51290-2018 Clause 3.0.2); (2) where a difference from actual construction-period conditions exists, adjust reasonably (GB/T 50500-2024 Clause 5.2.9), noting in the deliverable the issue used; (3) "28 days before the tender deadline" is the lock-in time point for the cost-fluctuation adjustment base price C₀ (Appendix A.2.1), used for contractual adjustment after award, and is unrelated to price-taking for the tender price ceiling; (4) where several market prices fall within one measurement period, take the arithmetic or weighted average (A.2.3); where no current issue of price information is available, the published price information may be used provisionally and adjusted against actuals subsequently (A.2.2).

Applicable Boundaries

Applies to determining the price-taking time point when preparing the maximum tender price under GB/T 50500-2024; the specific issue is governed by the documents published for the current period by the construction cost administrative body at the project location. It does not apply to determining the contractual price-adjustment base price — that follows the "28 days before the tender deadline" rule. This card contains no region-specific months or price data.

Further Reading

GB/T 50500-2024 Clauses 5.2.1, 5.2.8, 5.2.9 and Appendices A.2.1-A.2.5; GB/T 51290-2018 Clause 3.0.2; GB/T 50875-2013 Clause 2.1.16.