28 days before the tender deadline (= FIDIC Base Date)
- 01
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 02
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第3.3.5条、第8.7.1~8.7.4条、第10.2.3条、第10.2.7条、第10.3.2条、App. A.2.1~A.2.4、App. G.2T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-09-25 - 03
Price-taking time point for the tender price ceiling: the latest issue of price information published as at the date of completion of preparation; "28 days before the tender deadline" is the adjustment base price time point, not the price-taking time point
The tender price ceiling (employer's maximum acceptable price) takes pri…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51290-2018 建设工程造价指标指数分类与测算标准GB/T 50875-2013 工程造价术语标准2026-09-25 - 04
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the con…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第8.7.1条、第8.8.1条GB/T 50500-2024 App. A.1.6、A.2.1、A.2.42026-09-25