GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)

The base date (GB/T 50500-2024 term 2.0.21) is the date on which the contractor, during the tender period, determined the tender total price, the BOQ all-in unit rates and their sums, and it serves as the price datum for adjustment for changes in costs and for adjustment arising from changes in laws, regulations and policies. Determination order: agreement first, statutory fallback — where the tender documents (inquiry documents for non-tendered works) and the contract are silent, tendered works take 28 days before the tender deadline (= FIDIC Base Date) and non-tendered works 28 days before contract signing. That point is at once the base period of index-based (formula) adjustment (A.1.6), the base price C₀ of adjustment based on published price information (A.2.1), and the common starting point for adjustment for changes in laws, regulations and policies (8.8.1).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第8.7.1条、第8.8.1条
  • GB/T 50500-2024 App. A.1.6、A.2.1、A.2.4

Topic Positioning

This card covers the definition of the "base date" in GB/T 50500-2024 (China national pricing standard for BOQ), its determination order (agreement first, statutory fallback), the computation for tendered and non-tendered works respectively, and its role as the starting point of the two price-adjustment paths: adjustment for changes in costs (8.7.1) and adjustment for changes in laws, regulations and policies (8.8.1).

Core Conclusions

Concept (term 2.0.21, original text): base date — "the date on which the contractor determined, during the tender period, prices such as the tender total price and the BOQ all-in unit rates and their sums; this date shall serve as the price datum for implementing adjustment for changes in costs and adjustment for changes in laws, regulations and policies."

Determination order: agreement first, statutory fallback. "Where the tender documents (inquiry documents for non-tendered works) and the contract are silent, the base date of tendered works is 28 days before the tender deadline, and that of non-tendered works is 28 days before the contract signing date." Equivalent wording: "Unless otherwise agreed in the contract, the base date of tendered works is the 28th day before the deadline for submission of tenders, and that of non-tendered works is 28 days before the contract signing date."

Application paths (all starting from the base date):

  1. Index-based (formula) adjustment (Annex A.1.6): "The base date price index of tendered works is the price index 28 days before the tender deadline, which the tenderer shall specify in the tender documents. For non-tendered works it is the price index 28 days before contract signing."
  2. Adjustment based on published price information (Annex A.2.1): the base price C₀ is the market price 28 days before the tender deadline (non-tendered works: 28 days before contract signing). Sources for the base price may be the market price used by the employer when setting the tender price ceiling, the quarterly (monthly) published price information (government guidance prices) issued by the construction-cost administration, or the tender/award prices of similar projects published by the trading centre under similar conditions within the previous 1 month, "but all shall represent the market price level 28 days before the tender deadline (non-tendered works: 28 days before contract signing); the tenderer shall specify in the tender documents the price source, publishing institution and specific quarter (month) adopted for the base price (C₀)". A contractor objecting shall request clarification or correction from the employer within the time limit set before tendering.
  3. Adjustment for changes in costs (cl. 8.7.1): per the market price information source agreed in the contract, compute the price difference of VAT-exclusive labour cost, material cost and the fuel/power element of plant and small tools cost published at the base date and in the relevant adjustment periods agreed in the contract, determine the market price fluctuation and the contractor-borne market price risk agreed in the contract, and adjust the price for the portion beyond the agreed risk band.
  4. Adjustment for changes in laws, regulations and policies (cl. 8.8.1): where, during performance, after the base date, laws, regulations or policy provisions are ① newly enacted, ② modified or ③ repealed, or ④ government interpretations of relevant laws/regulations change, causing contract price changes and/or delay, the parties shall adjust the contract price and/or the time for completion per the contract and the provisions issued by the competent authority; where such changes cause material extension of the time for completion and hence market price changes at the planned progress dates, adjustment follows the provisions on changes in costs.

Applicable Boundaries

  • These rules apply to GB/T 50500-2024 (transformed from the mandatory GB 50500-2013 to the recommended GB/T; binding once contractually referenced).
  • The statutory date (28 days before the tender deadline / before contract signing) applies only where the tender documents, inquiry documents and the contract are silent — agreement first is the general principle (echoing cl. 1.0.3, agreed terms prevail).
  • The base date only fixes "the price level of which point in time is the datum"; actual adjustment additionally requires the three-choose-one base price source, the risk band, the quantities subject to price adjustment and other elements (see the cited cards).
  • Regulations and price fluctuations existing before the base date are deemed to have been considered in both parties' pricing and fall outside the adjustment scope.

Further Reading

  • GB/T 50500-2024: cl. 2.0.21 (term: base date), cl. 8.7.1 (adjustment for changes in costs), cl. 8.8.1 (adjustment for changes in laws, regulations and policies), Annex A.1.6 (index-based (formula) adjustment), Annex A.2.1 (base price under adjustment based on published price information), Annex A.2.4 (beyond-risk-band adjustment rules where published price information serves as the base price).
  • Related cards: "Material adjustment base price (C₀) determination: base date, three-choose-one source and adjustment base"; "Overview of construction material price adjustment"; "Order of precedence for material price adjustment: contractual agreement takes precedence"; "Price difference computation after prices exceed the risk band"; "Determination of construction-period prices (market price Ci of the measurement period)".