index-based (formula) adjustment
- 01
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, mat…
GB/T 50500-2024 第3.3.5条(物价变化合同价格调整)GB/T 50500-2024 第8.7.6条(不应因物价变化调整的费用)GB/T 50500-2024 第7.3.1条(措施项目不予计量调整)2026-10-25 - 02
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjus…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.4(价格信息调差法 报价偏离基准价的涨跌幅判定基数)GB/T 50500-2024 App. A.2.1(价差公式与基准价、计量周期价格、数量、风险幅度系数定义)GB/T 50500-2024 App. A.2.3(计量周期多个市场价格的取定方法)2026-10-25 - 03
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.5 条GB/T 50500-2024 第 8.7.1 条GB/T 50500-2024 第 8.7.2 条2026-10-25 - 04
The index-based adjustment method (GB/T 50500-2024 Appendix A.1): the adjustment formula, fixing the fixed weight A and variable weights Bi, and the sources and timing of price indices (factors)
The index method computes dP = P0 x [A + sum Bi x (Fti/F0i) - 1]: P0 the…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.1.1~A.1.6GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.1~8.7.6条2026-10-18 - 05
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials"…
GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条GB/T 50500-2024 App. A2026-09-25 - 06
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 07
Three-layer playbook for locking in the prices of bulk materials: contract-side price-adjustment mechanism + procurement-side price-locking methods + material-differentiated strategy (GB/T 50500-2024)
Locking the price of bulk materials = on the contract side, first fix th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50358-2017 建设项目工程总承包管理规范DB37/T 5096-2017 建设工程项目管理咨询规范2026-09-25 - 08
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable s…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引建设部令第107号 建筑工程施工发包与承包计价管理办法2026-09-25 - 09
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-ba…
GB/T 50500-2024 建设工程工程量清单计价标准(App. A、第8.7节、App. G)GB 50500-2013 建设工程工程量清单计价规范(App. A、第9.8节)2026-09-25 - 10
GB/T 50500-2024 rules for determining the base date: agreement first; tendered works = 28 days before the tender deadline, non-tendered works = 28 days before contract signing (term 2.0.21)
The base date (GB/T 50500-2024 term 2.0.21) is the date on which the con…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第8.7.1条、第8.8.1条GB/T 50500-2024 App. A.1.6、A.2.1、A.2.42026-09-25 - 11
Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)
Cross-month construction is not computed in a lump: adjust independently…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25