The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)

GB/T 50500-2024 sets no statutory "list of price-adjustable materials": the employer and contractor define the scope of adjustable main materials and lock it in as a contract annex by completing table G.2.1-1 (price-information adjustment method) or G.2.1-2 (price-index adjustment method) of appendix G.2; the statutory adjustable factors are only three classes — labor cost, main material cost, and fuel/power cost of construction plant; price differences carry VAT only, with no management fee or profit.

Applicable Codes

  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 第8.7.2条
  • GB/T 50500-2024 App. A
  • GB/T 50500-2024 App. G.2

Topic Positioning

Answers "which materials count as price-adjustable": GB/T 50500-2024 sets no statutory list — the adjustable scope is defined by the employer and contractor in the contract and locked via the appendix G.2 tables as a contract annex; this card gives the determination mechanism, the statutory classes of adjustable factors and typical practical categories.

Core Conclusions

(1) Only three statutory classes of adjustable factors: labour cost; main material cost; fuel and power costs within plant and small tools cost. (2) The adjustable scope is defined by the employer: the parties define the scope of adjustable main materials and complete table G.2.1-1 (adjustment based on published price information) or G.2.1-2 (index-based (formula) adjustment) of appendix G.2 as a contract annex; the employer fills in the name, specification, unit, base price and risk band; the bidder fills in the tender (priced offer). (3) In practice the materials listed for price adjustment are mostly those with "a large cost share + sensitivity to price fluctuation": steel categories — rebar, section steel, steel plate, steel pipe, strand; cement products — cement, ready-mixed concrete, ready-mixed mortar; aggregates, timber, asphalt categories; fuel/power — diesel, gasoline, electricity; and bulk materials — waterproof membranes, pipes, cables, bricks/blocks. Auxiliary and sundry materials, "other material fees" and amortization of revolving materials are usually excluded, with the risk borne by the contractor. (4) Adjustment applies only when the fluctuation exceeds the contractually agreed band; if there is no agreement or the agreement is unclear, fluctuations beyond 5% may be adjusted according to Appendix A; the price differential includes VAT only, not management fee or profit.

Applicable Boundaries

Applies only to adjustment of the contract price caused by changes in costs, distinct from variations and from adjustment for price differentials after the actual prices of provisional-sum materials are determined; whether adjustment applies is governed by the contract annex — the categories in this card are practice convention only, not a statutory list; the index-based (formula) adjustment also requires agreement on the weights or amounts of adjustable factors, the fluctuation band and the index source (Appendix A.1).

Further Reading

See GB/T 50500-2024 "China national pricing standard for BOQ" clause 3.3.5 (basic provisions), clause 8.7.2 (adjustment of the contract price), appendices A.1/A.2 (price adjustment methods), appendix G.2 (filling-in rules for tables G.2.1-1/2).