adjustment based on published price information
- 01
Valuation rules for the four variables of material price adjustment (adjustment based on published price information) and the step-by-step calculation flow: base price C0, risk band r, measurement-period market price Ci and adjustable quantity Q (GB/T 50500-2024 Annex A.2)
The published-price-information method takes its values in five steps. (…
GB/T 50500-2024 App. A.2.1GB/T 50500-2024 App. A.2.2GB/T 50500-2024 App. A.2.32026-11-08 - 02
Choosing among the three bases of material price adjustment (bid price / base-period published information / jointly confirmed price): statutory sources, defaults, difference-rate versus risk-band linkage and item-by-item locking (GB/T 50500-2024 term 2.0.21, Appendix A.2, G.2.1)
Per GB/T 50500-2024 Appendix A.2.1, the base price C0 is 'the market pri…
GB/T 50500-2024 术语第2.0.21条(合同基准日)GB/T 50500-2024 App. A.2.1(基准价三来源与价差公式)GB/T 50500-2024 App. A.2.2(暂按信息价计算后按实调整)2026-10-25 - 03
The step chain of adjusting on published price information: fix the adjustable list -> lock base price C0 -> take period prices Ci -> difference x adjustable quantity Q -> adjust the excess over the risk band -> book into progress and settlement, with fallbacks for missing periods and items and the Q test (GB/T 50500-2024 Appendix A.2; against superseded GB 50500-2013 Appendix A.2)
Six steps: (1) fix the adjustable material / labour list (2024: 3.3.5 it…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.5 条、第 8.7.2 条、第 8.7.4 条、第 8.7.6 条、第 8.1.6 条、第 9.4.6 条GB/T 50500-2024 App. A.2.1~A.2.5(价格信息调差法)GB/T 50500-2024 App. G Table G.2.1-1、Table G.2.1-22026-10-25 - 04
Fee boundary for material price adjustment: the price difference carries VAT only, with no management fee or profit; the eight cost categories under Clause 8.7.6 are not adjusted (GB/T 50500-2024)
Per GB/T 50500-2024 Clause 3.3.5 item 4, price differences of labor, mat…
GB/T 50500-2024 第3.3.5条(物价变化合同价格调整)GB/T 50500-2024 第8.7.6条(不应因物价变化调整的费用)GB/T 50500-2024 第7.3.1条(措施项目不予计量调整)2026-10-25 - 05
Direction-specific base rules in the price adjustment method based on published price information when the contractor's tender price deviates from the base price (GB/T 50500-2024 Annex A.2.4, corresponding to Section 9.7 of the superseded GB 50500-2013): rises judge on the higher of the two prices, falls on the lower, a two-way disadvantage that blocks arbitrage, with the selection boundary against the Annex A.1 index method
Under GB/T 50500-2024 Annex A.2.4, the published-price-information adjus…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.4(价格信息调差法 报价偏离基准价的涨跌幅判定基数)GB/T 50500-2024 App. A.2.1(价差公式与基准价、计量周期价格、数量、风险幅度系数定义)GB/T 50500-2024 App. A.2.3(计量周期多个市场价格的取定方法)2026-10-25 - 06
Selecting between the two methods of contract price adjustment for changes in costs: comparison of applicable conditions, clause-by-clause contrast and same-contract mixing boundaries of the Appendix A.1 index-based adjustment and the Appendix A.2 adjustment based on published price information under GB/T 50500-2024
The two methods share an identical adjustable scope, base time point and…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.3.5 条GB/T 50500-2024 第 8.7.1 条GB/T 50500-2024 第 8.7.2 条2026-10-25 - 07
The mechanism for determining the scope of price-adjustable materials and typical categories (GB/T 50500-2024 appendix G.2)
GB/T 50500-2024 sets no statutory "list of price-adjustable materials"…
GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条GB/T 50500-2024 App. A2026-09-25 - 08
Rules for determining the material adjustment base price (C0): base date, one-of-three sources and the adjustment computation base (GB/T 50500-2024)
The base price C0 = the market price level 28 days before the bid closin…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1GB/T 50500-2024 术语2.0.21GB/T 50500-2024 App. A.2.42026-09-25 - 09
Can published price information directly serve as the basis for material price adjustment: legality + three preconditions (listing / beyond band / tax) (GB/T 50500-2024)
Published price information (government guidance prices) is a price sour…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 10
Taking and weighting published price information for materials across multiple months: default per-period adjustment; weight only when one measurement period spans price issues (GB/T 50500-2024 Appendix A.2)
Per GB/T 50500-2024: for construction spanning measurement periods (e.g…
GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.3条、App. A.2.1~A.2.5、App. GTable G.2.1-1、第8.7.2条、第3.3.5条)2026-09-25 - 11
Price adjustment (for fluctuation) calculation for ready-mixed (commercial) concrete: whole-factor adjustment per m³, adjustment to actual beyond the risk band, and tax treatment (GB/T 50500-2024 Appendix A.2 adjustment based on published price information)
Ready-mixed concrete is adjusted as one whole adjustable factor per m³ (…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. A.2(价格信息调差法)GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 12
Appendix G main materials (adjustment) list of GB/T 50500-2024: locking stage and adjustment-quantity caliber (contract annex / completed quantities per measurement cycle)
Tables G.2.1-1/2 are filled during tendering and locked as a whole as a…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. G Table G.2.1-1/G.2.1-2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 App. A.2.12026-09-25 - 13
Three-layer playbook for locking in the prices of bulk materials: contract-side price-adjustment mechanism + procurement-side price-locking methods + material-differentiated strategy (GB/T 50500-2024)
Locking the price of bulk materials = on the contract side, first fix th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50358-2017 建设项目工程总承包管理规范DB37/T 5096-2017 建设工程项目管理咨询规范2026-09-25 - 14
Overview of material price adjustment in construction works: applicable conditions, base price (reference price for adjustment), risk band, and calculation methods (GB/T 50500-2024 Sections 3.3/8.7 and Appendices A, G)
Four indispensable elements of material price adjustment: ① adjustable s…
GB/T 50500-2024 建设工程工程量清单计价标准T/ZBD 100.5-2023 建设工程结算审核作业指引建设部令第107号 建筑工程施工发包与承包计价管理办法2026-09-25 - 15
Price adjustment for wires and cables: itemized by full specification, copper-linkage agreements, and handling missing published price information (government guidance prices) (GB/T 50500-2024 Appendix A.2)
Cable price adjustment shares the same mechanism as steel (GB/T 50500-20…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7节2026-09-25 - 16
Handling rules when the price-information issue and the construction month are misaligned (GB/T 50500-2024 Appendix A adjustment)
Price-information adjustment takes the issue corresponding to the measur…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50875-2013 第2.1.16条T/ZBD 100.1-2022 第7.2.3条2026-09-25 - 17
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 18
Appendix A price adjustment (for fluctuation) methods for changes in costs, GB 50500-2013 vs GB/T 50500-2024: weighting coefficient basis and adjustment threshold differences
The two editions share the same formula skeleton in Appendix A (index-ba…
GB/T 50500-2024 建设工程工程量清单计价标准(App. A、第8.7节、App. G)GB 50500-2013 建设工程工程量清单计价规范(App. A、第9.8节)2026-09-25 - 19
Price-difference calculation method after material prices exceed the risk band (price-information adjustment method, GB/T 50500-2024 Appendix A.2)
The excess beyond the risk band is adjusted per actuals: when prices ris…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.1~8.7.4条GB/T 50500-2024 第3.3.5条2026-09-25 - 20
Which period's published price applies to settlement material prices: the two-date system — base price locked at the contract base date (28 days before bid closing) plus period-by-period pricing per measurement cycle (GB/T 50500-2024 Annex A.2 price-information method)
Settlement material prices are not taken from a single period (completio…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.21条、第3.3.5条、第8.7.1~8.7.4条、第10.2.3条、第10.2.7条、第10.3.2条、App. A.2.1~A.2.4、App. G.2T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-09-25 - 21
Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)
Price information is only one of the Ci sources listed in A.2.1; lacking…
GB/T 50500-2024 App. A.2.1GB/T 50500-2024 App. A.2.2GB/T 50500-2024 App. A.2.52026-09-25 - 22
Cement price adjustment calculation: determining the adjustment object by usage path (site-mixed / ready-mixed concrete / direct purchase) + price-information adjustment method formulas and caliber points (GB/T 50500-2024 Appendix A.2)
Cement adjustment first fixes the object by usage path: site-mixed concr…
GB/T 50500-2024 建设工程工程量清单计价标准 App. A.2.1~A.2.5GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.1~8.7.6条2026-09-25 - 23
Whether actual purchase quantities can directly serve as the material adjustment quantity: triple filtering of contract agreement + employer confirmation + not exceeding rational consumption (GB/T 50500-2024)
The purchase quantity cannot directly serve as the adjustment quantity Q…
GB/T 50500-2024 App. A.2.1、A.2.5、App. GTable G.2.1-1、第3.6.3条、第8.7.2条T/ZBD 100.4-2023 第4.5.7条2026-09-25 - 24
Cross-month material price adjustment: adjustment-period division and three methods for synthesizing multiple prices within a period (arithmetic mean / weighted mean with completed quantities / price of the main-consumption construction period)
Cross-month construction is not computed in a lump: adjust independently…
GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 25
Rules for determining the construction-period price (measurement-period market price Ci) in material adjustment (GB/T 50500-2024 appendix A.2)
The construction-period price is the measurement-period market price Ci…
GB/T 50500-2024 App. A.2.1~A.2.5GB/T 50500-2024 第8.7.2/8.7.4条GB/T 50500-2024 App. A.1.52026-09-25 - 26
Handling paths when published price information clearly deviates from actual market prices: unify the bases of comparison first to exclude illusions, then correct by scenario (temporary adjustment with later true-up / price certification / expert assessment as fallback)
Published price information is only a reference guide price issued by th…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范GB/T 50875-2013 工程造价术语标准2026-09-25 - 27
Overview of the full-chain use rules for construction cost published price information: nature, price calibers, stage-by-stage pricing, and frequent misconceptions
Published price information means reference guide prices issued by cost…
GB/T 50875-2013 工程造价术语标准GB/T 50500-2024 建设工程工程量清单计价标准TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25