Appendix G main materials (adjustment) list of GB/T 50500-2024: locking stage and adjustment-quantity caliber (contract annex / completed quantities per measurement cycle)

Tables G.2.1-1/2 are filled during tendering and locked as a whole as a contract annex at signing: the tenderer fills scope/base price (market price level 28 days before the bid deadline)/risk band; bidders fill tender prices and agree price data in the tender-letter appendix (3.3.5 item 2, A.2.1). Adjustment quantities are neither tender quantities nor actual purchase quantities but follow "the quantity calculation method the parties specify in the contract" (table note 2, A.2.1); the default framework is quantities corresponding to completed qualifying work in the measurement cycle, measured in segments per adjustment cycle and accumulated (7.1.3).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works App. G Table G.2.1-1/G.2.1-2
  • GB/T 50500-2024 第3.3.5条
  • GB/T 50500-2024 App. A.2.1
  • GB/T 50500-2024 第7.1.3条

Topic Positioning

Answering at which stage Appendix G "main materials (adjustment) list" (Tables G.2.1-1/2) of GB/T 50500-2024 is locked, who fills which columns, and whether adjustment quantities follow tender or actual quantities — for practical operation of price-fluctuation contract adjustments (price-information method / price-index method).

Core Conclusions

1. Locking stage: filled during tendering, locked as a "contract annex" at signing

  1. Tender stage: the tenderer fills Table G.2.1-1's "No., name, specification, model, unit, base price, risk band" (note 1) — i.e., adjustable material scope, base price C0, and risk band r are set unilaterally by the tenderer; for G.2.1-2 (index method), the tenderer fills "name/spec/model" and "base price index" columns, including labor if index-adjusted.
  2. Bid stage: bidders fill the "tender price" column per their offers and agree price data in the tender-letter appendix (Appendix A.2.1); base price C0 anchors the market price level 28 days before the bid deadline (28 days before contract signing for non-tendered works), and tender documents must specify price source, publisher, and quarter/month.
  3. Contract signing: 3.3.5 item 2 original: "The parties shall specify the adjustable main-material scope and complete Table G.2.1-1 or G.2.1-2 as a contract annex per Appendix G.2." After signing the whole table becomes part of the contract documents; scope, base prices, and risk bands no longer change during construction.

2. Adjustment-quantity caliber: neither tender nor actual purchase quantities, per "contractually agreed quantity rules"

  • G.2.1-1 note 2: "'Quantity' is calculated per the quantity calculation method the parties specify in the contract."
  • Appendix A.2.1: "Adjustable material quantities shall be calculated per the quantity rules agreed in the contract. Where other methods are used, they shall be specified in tender documents and special contract clauses."
  • Default framework absent special agreement: dP is defined as "the current adjustment cost per measurement cycle"; 7.1.3: "list items with contractually agreed price-fluctuation adjustment shall be measured in segments per the completed work of the agreed adjustment cycle." I.e., each cycle's quantity Q = confirmed completed qualifying quantities x contractually agreed material content (converted per list/quota consumption), accumulated cycle by cycle. Tender BOQ quantities are point-in-time estimates and do not participate; actual purchases belong to the contractor's performance management unless the contract agrees adjustment by confirmed purchase quantities (A.2.5 — quantities and unit prices submitted to the employer for confirmation before purchase).

3. Practice points: special clauses should state "Q = employer-confirmed completed qualifying quantities in the cycle x winning-list material content" to avoid settlement disputes; differences carry VAT only, not management fee or profit (3.3.5 item 4).

Applicable Boundaries

Applies to projects with contractually agreed price-fluctuation adjustments: G.2.1-1 for the price-information method, G.2.1-2 for the index method; the tables apply only to price-fluctuation events. Not applicable to: employer-supplied materials and provisional-sum list items (not adjusted per 8.7); construction consumables, small/medium tools, measure costs outside the adjustable scope; price risk within the risk band (already considered in bids). Quantity and price calibers may be further agreed by the parties; the standard is the default framework; delays adjust per Chapter 8.

Further Reading

See GB/T 50500-2024: Appendix G Tables G.2.1-1/2 and notes (filling division, quantity method, item/whole difference calculation); Appendix A.2.1 (information-method formula, base price and cycle market price sources, quantity rules); 3.3.5 (adjustment, contract annex, tax caliber, machinery fuel/power); 7.1.3 (segmented measurement per adjustment cycle); Section 8.7 (risk band and methods); term 2.0.21 (contract base date).