Alternative adjustment paths when price information lacks the specification: mutually confirmed price / purchase price / awarded-bid price fallbacks + the same-caliber red line for C0 and Ci (GB/T 50500-2024 Appendix A.2)

Price information is only one of the Ci sources listed in A.2.1; lacking the specification does not mean adjustment is impossible: determine Ci per (1) contract agreement, (2) the market price of the measurement period confirmed by both parties, (3) the purchase price determined by the employer (submitted before purchase; deemed accepted upon overdue silence), (4) the awarded bid price of the trading center for similar works under similar conditions in the same period; C0 takes prices by the same rules; where information is temporarily missing, provisionally account per the published price and settle later. Red lines: C0 and Ci must be of the same caliber; the alternative price must represent the market price level of the measurement period; keep a full trail of certified records of agreed material prices.

Applicable Codes

  • GB/T 50500-2024 App. A.2.1
  • GB/T 50500-2024 App. A.2.2
  • GB/T 50500-2024 App. A.2.5
  • GB/T 50500-2024 第 8.6.3 条
  • GB/T 50500-2024 第 1.0.3 条

Topic Positioning

This card answers "what to do for material adjustment when the published cost information (price information) has no corresponding material specification": price information is only one of the Ci sources in Appendix A.2.1; lacking the specification, switch to the alternative-price path and adjust as usual — the key is keeping C0 and Ci in the same caliber.

Core Conclusions

Alternative-price paths by priority: (1) contract agreement first (agreements prevail; special clauses often state "materials without price information are adjusted per the employer-confirmed price"); (2) the market price of the measurement period confirmed by both parties (market price enquiry certification records, expressly listed in A.2.1 as a statutory Ci source); (3) the purchase price determined by the employer (A.2.5: submit quantity + unit price before purchase; silence within the agreed period is deemed acceptance; batch purchases averaged by weight); (4) the awarded bid price published by the trading center at the project location for similar works under similar conditions within the same period (within the previous 1 month); (5) where information is temporarily missing or disputes are significant, per A.2.2 provisionally compute a "provisionally determined difference" with the current published price and account for it first, adjusting later payments per actuals. Supporting analogy: Clause 8.6.3 applies the same rule to dayworks — where price information lacks the relevant price, the contractor's purchase unit price confirmed by both parties may be used. Three red lines: C0 and Ci must take prices by the same rule (base price from price information while construction-period price from purchase price is a mixed caliber — the No. 1 source of disputes); the alternative price must represent the market price level of the measurement period (or the base time point); enquiry records, certified records of agreed material prices, and purchase submission forms must all be kept.

Applicable Boundaries

Applies only to adjustable materials under the price-information adjustment method (Appendix A.2); handling nearby specifications by conversion coefficients/interpolation is industry practice rather than a mandatory standard clause, requiring both parties' recognition and records; the price-index adjustment method (A.1) follows the price-index source rules and does not apply to this card's alternative paths.

Further Reading

GB/T 50500-2024 Appendix A.2.1 (three Ci sources and the adjustment formula), A.2.2 (provisionally determined difference), A.2.5 (employer-determined purchase price), Clauses 8.6.3, 1.0.3; early layout at the tendering stage: directly agree the adjustment price source in Table G.2.1-1 for known rare specifications.