Engineering Knowledge Cards.

published price information (government guidance prices)

28 knowledge cards · sorted by most recently updated

Concept Guide

Concept

Published price information (government guidance prices) is a category of officially issued guidance price data in China's construction cost system. Provincial and municipal cost management agencies (cost management stations and quota stations) collect, weight and verify market transaction prices for labour days, major materials and construction plant on a fixed cycle — usually monthly or bi-monthly — and publish the resulting figures for their locality. Because the data come from local market surveys and price-monitoring networks, the published prices are both regional and time-sensitive: the same material carries different published prices in different provinces and in different months.

The legal character is guidance, not state pricing. A published price does not bind the contracting parties, who remain free to agree market price enquiry, supplier quotations or negotiated rates. Its practical force lies elsewhere: for state-funded projects it is a customary basis for preparing the tender price ceiling (tender control price), and it is a reference dataset for final account review, for price adjustment and for construction cost expert assessment (judicial appraisal). Under the GB 50500-2013 regime, labour, material and plant prices in the tender control price were determined from published price information or market prices; the current GB/T 50500-2024 (in force from 1 September 2025) has shifted ceiling preparation towards comparable-project and market data, with published price information remaining a common reference.

The typical mechanism is price adjustment for fluctuation. The contract fixes a base price by reference to a stated issue of published price information; the difference between that base price and either the actual procurement price or a later published price is adjusted, but only to the extent it exceeds the agreed risk allowance. This is the adjustment based on published price information. The alternative is index-based (formula) adjustment, which applies published cost or element price indices through an agreed formula instead of comparing individual prices. The two differ in data granularity, evidential weight and dispute cost.

FIDIC Mapping

FIDIC contract conditions contain no equivalent institution: no government cost management agency issues periodic, locality-specific price information for contractual use (absent). Under the 2017 Red Book and Yellow Book, Sub-Clause 13.7 [Adjustments for Changes in Cost] applies only if Schedule(s) of cost indexation are included in the Contract; where they are, payments are adjusted by the amounts calculated under those Schedules, using the formula in both directions (only where the Contractor fails to complete within the Time for Completion does Sub-Clause 13.7 thereafter use whichever index or price is more favourable to the Employer). The adjustment baseline therefore comes from an indexation schedule agreed by the parties, not from any administratively published price information.

The difference is one of pricing infrastructure, not of terminology. First, the issuing body: published price information is issued centrally by cost management agencies with administrative backing and a uniform format, which lowers the evidentiary burden on both sides; FIDIC leaves index selection to the parties (often drawing on official statistical or industry indices), who bear the credibility risk themselves. Second, decision-making: published prices are guidance while the contract may still rely on market price enquiry, whereas FIDIC allocates pricing entirely to contract and market. Third, procedure: published-price adjustment needs only a dated price list as comparator, so it is simple and fast; formula adjustment requires an agreed formula and weightings before the works, trading flexibility for greater front-end and verification effort.

Usage warning: an English rendering should always carry a note on the guidance character and the locality of these prices, so that readers do not infer state-set prices for construction materials in China. Equally, published price information should not be cited as the index source for Sub-Clause 13.7 on an international project unless the Contract expressly so provides. Note also that base price is the numerical starting point for comparison, whereas the FIDIC Base Date is a point in time for risk allocation; the two are not interchangeable.

Chinese TermEnglish TermFIDIC TermRelationNotes
信息价published price information (government guidance prices)Schedule(s) of cost indexation (Sub-Clause 13.7)absentFIDIC 无政府造价管理机构定期发布属地价格信息的制度,其调价基线由双方约定的费用指数表提供并按公式双向调整(仅承包商延误超竣工时间期间,13.7 才取对雇主有利的指数/价格);信息价则依赖行政发布平台与统一口径,二者背后的数据基础设施根本不同。
价格指数调差法index-based (formula) adjustmentAdjustments for Changes in Cost (Sub-Clause 13.7)adjacent同为按指数或公式调整物价波动,但 FIDIC 以合同附具费用指数表为适用前提,指数来源与权重由双方谈定;中国的造价(要素价格)指数由造价管理机构统一发布,口径一致且有行政背书。
基准价base price (reference price for adjustment)Base Datedistinct基准价是价格调差对比的起点数值,如合同约定的某一期信息价;FIDIC 的 Base Date 是划分风险归属的时间节点,一为价格、一为日期,不可互换使用。

Updated 2026-09-13