Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Whether published price information includes VAT: the code caliber is a tax-exclusive price, while regional publications mix tax-inclusive and tax-exclusive in practice

Under the code caliber, price information as a pricing basis should be a tax-exclusive price excluding deductible input VAT (GB/T 50500-2024 Clause 3.1.6, T/ZBD 100.2-2022 Clause 4.4.2, TB 10801-2024 general principles), with VAT = tax-exclusive cost x tax rate (9% under general taxation) listed separately; however, the actual calibers of regionally published price information mix tax-inclusive and tax-exclusive — always verify against the current issue's publication notes before use; provisional prices of specialty works are tax-inclusive as an exception.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.2-2022 建设项目投资估算编制作业指引
  • TB 10801-2024 铁路工程材料基期价格
  • GB/T 50875-2013 工程造价术语标准
  • T/ZBD 100.1-2022 建设工程造价数据建设通用标准

Topic Positioning

Answers "whether published price information includes VAT": the code basis is a tax-exclusive price, while regional publications mix tax-inclusive and tax-exclusive prices in practice.

Core Conclusions

Code basis: under general VAT taxation the pricing basis is the fully inclusive price excluding VAT, and VAT is a price-exclusive tax listed separately — GB/T 50500-2024 Clause 3.1.6, T/ZBD 100.2-2022 Clause 4.4.2, and the general principles of TB 10801-2024 share the same basis (materials/equipment/construction and installation works costs all exclude tax; railway base-period prices exclude deductible input VAT). Published price information used under general taxation shall adopt the tax-exclusive basis; VAT = tax-exclusive cost x tax rate (9% under general taxation), listed separately. Publication practice: after the business-tax-to-VAT reform, regional bases are not unified — tax-exclusive prices serve budget compilation and price adjustment under general taxation, while tax-inclusive prices serve the simplified VAT scheme and as references for tax-inclusive provisional sums; most provinces and cities publish both sets — the current issue's publication notes govern, and wrong use leads to double-counting or omission of the tax. Where a contract provides for price adjustment based on published price information, the tax-inclusive/tax-exclusive basis must be stated; the provisional sum for nominated specialist subcontract works is a tax-inclusive amount (Clause 3.1.6), unlike the pre-tax basis for provisional sums for specified materials/equipment.

Applicable Boundaries

Applies to judging the pricing basis and the basis for price adjustment under general taxation or the simplified VAT scheme; the current local basis is governed by the official publication notes. Market prices, published price information, and manufacturer quotations are established through three classified channels and must never be mixed (T/ZBD 100.1-2022 Clause 7.2.3).

Further Reading

GB/T 50500-2024 Clause 3.1.6 (fully inclusive pre-tax price; the tax-inclusive exception for provisional sums); T/ZBD 100.2-2022 Clause 4.4.2; TB 10801-2024 general principles; GB/T 50875-2013 Clause 2.1.16; T/ZBD 100.1-2022 Clause 7.2.3.