Contractor's objection period and tiered remedies against final account review results (GB/T 50500-2024)

After receiving the settlement verification/review result, the contractor must raise itemized written objections within the agreed objection period (28 days absent agreement), failing which the result is deemed accepted (GB/T 50500-2024 Clauses 10.3.8, 10.3.10); if dissatisfied, escalate through the ladder: recheck → incomplete settlement first for undisputed parts → negotiation/professional conferencing → dispute review/mediation → administrative mediation (within one month) → arbitration/litigation, while continuing performance during the dispute.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 建设部令第107号 建筑工程施工发包与承包计价管理办法
  • GB/T 51095-2015 建设工程造价咨询规范
  • 财建〔2004〕369号 建设工程价款结算暂行办法

Topic Positioning

The remedy path for contractors dissatisfied with the final account review result (including verification by a cost consultant engaged by the employer): objection → recheck → partial final account → negotiation/conferencing → dispute review/mediation → administrative mediation → arbitration/litigation; this card gives the time limits and clause basis for each step.

Core Conclusions

① The objection period is the first gate: where the contractor fails to object in writing to the consultant's verification result within the agreed time, it is deemed accepted (GB/T 50500-2024 Clause 10.3.10); where the employer fails to verify or reply within the time limit, the final account documents submitted by the contractor are deemed accepted (Clause 10.3.8). Absent agreement, 28 days apply (Construction Ministry Order No. 107, Article 16). Reply in writing the same day the result is received, listing disputed amounts, reasons, and supporting documents item by item — never just "we disagree". ② Recheck and partial final account: after the contractor's written objection, the consultant shall recheck within the agreed time; undisputed parts after recheck are confirmed with both parties' signatures and seals, disputed parts are negotiated — the undisputed parts may first be settled through a partial final account (Clause 10.3.7), avoiding all funds being held up by the dispute. ③ Remedy ladder: negotiate first; if agreed, sign a supplementary (settlement) agreement; objections may be resolved through a professional conferencing meeting whose minutes, signed by all parties, serve as a settlement basis (GB/T 51095-2015 Clause 8.3.7); failing negotiation, proceed to dispute review or mediation (Chapter 11); still dissatisfied with the consultant's review opinion, apply within one month of receipt to the county-level-or-above construction administrative authority for mediation (Order No. 107, Article 16); failing that, arbitration or litigation (Clause 11.4.1), which is final. During the dispute both parties continue performing the contract.

Applicable Boundaries

Applies where the contractor disputes the review result at the final account stage; contract-agreed objection periods and procedures prevail over default periods; once "deemed acceptance" enters litigation, some courts may refer the matter to judicial cost expert determination, lowering the prospects of the claim; in-process settlement and settlement upon contract termination are separate procedures requiring their own clauses.

Further Reading

GB/T 50500-2024 Clauses 10.3.5, 10.3.7, 10.3.8, 10.3.10, 10.3.16 and Chapter 11 (11.1.1 negotiation, 11.4.1 arbitration/litigation); Construction Ministry Order No. 107, Article 16 (28-day default period, administrative mediation, effect as final-account basis once confirmed); GB/T 51095-2015 Clause 8.3.7 (professional conferencing meeting); Cai Jian [2004] No. 369, Article 16 (failure to reply in time deemed acceptance).