Six-step method for reviewing the reasonableness of all-in unit rates: rate build-up basis -> labour/materials/plant -> on-costs -> special items -> horizontal comparison -> arithmetic
Reviewing an all-in unit rate means breaking down and verifying the three pricing elements (labour/material/plant consumption x unit price + on-costs) layer by layer, plus horizontal comparison against market benchmarks. Six steps: (1) compliance of the rate build-up basis; (2) labour/material/plant consumption at quota norm values, unit prices at compilation-period market/published price information (government guidance prices); (3) compliance of on-cost rates and bases (in the 2024 edition, check for double-counting after statutory levies and fees are rolled in); (4) special items (provisional sums for specified materials adjust material price only; employer-supplied (free-issue) materials; attribution of risk allowances); (5) horizontal comparison against tender price ceilings/similar works/analogous projects and identification of unbalanced rates / rate loading; (6) arithmetic check (unit price x quantity = extended amount; analysis sheet consistent with the BOQ).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 51095-2015 建设工程造价咨询规范
- T/ZBD 100.5-2023 建设工程结算审核作业指引
- DB37/T 5161-2020 建设工程造价数据交换及应用标准
Topic Positioning
A systematic method for reviewing all-in unit rates: break the three pricing elements (labour/materials/plant x unit price + on-costs) apart for verification and compare horizontally against market benchmarks — for tender review and normalization (arithmetic and compliance check), final account, and budget/estimate review.
Core Conclusions
Six-step review: (1) Rate build-up basis — quota line items match the BOQ item description (work item specification), no over-application or mis-application, pricing method complies with the contract (T/ZBD 100.5-2023 clause 3.2.4). (2) Labour/materials/plant — consumption at quota norm values (GB/T 51095-2015 clause 5.3.9), unit prices at compilation-period market/published price information (government guidance prices); materials verified as material price at source (ex-works / ex-yard) + freight and handling charges + purchasing and custody charges. (3) On-costs — rates and bases compliant (clause 3.2.5); in the 2024 edition the former statutory levies and fees are already rolled in, guard against double-counting. (4) Special items — provisional sums for specified materials adjust the material price only; employer-supplied (free-issue) materials at the given unit price; risk allowances limited to the contract scope (GB/T 50500-2024 clause 8.4.6). (5) Horizontal comparison — against tender price ceilings, similar works, analogous projects; anomalies require clarification and proof of not being below cost (clause 3.5.3), and identification of unbalanced rates / rate loading. (6) Arithmetic — unit price x quantity = extended amount; analysis sheet consistent with the BOQ (clause 3.1.7).
Applicable Boundaries
Applies to BOQ pricing; first confirm the contractual pricing basis (quota edition, on-cost standard, published price information period) — without a basis "reasonableness" is meaningless; highway and other industries may use fully loaded all-in rate basis and must be adjusted per industry; tender review and normalization emphasizes reasonableness and unbalanced rates / rate loading, final account emphasizes unit-price consistency.
Further Reading
GB/T 51095-2015 clauses 5.3.9, 6.3.2; T/ZBD 100.5-2023 clauses 3.1.6, 3.2.4, 3.2.5; GB/T 50500-2024 clauses 2.0.9, 3.1.7, 3.5.3 and sections 8.4, 8.7; analysis-sheet format see appendix E.2.2; tender review and normalization points refer to DB37/T 5161-2020 chapter 5.