Three-dimensional cost analysis method for billed (BOQ) items: quantity, price, and fee (quantity recheck → price reasonableness → fee composition)
Split the cost of a single billed (BOQ) item into three independent dimensions for review — quantity (recheck of quantities), price (three-layer review of the all-in unit rate), and fee (verification of costs outside the unit rate): the quantity dimension re-quantifies from drawings and compares with the BOQ quantities, checking missing items and duplicate listings; the price dimension reviews consumption, prices, and rates under the all-in unit rate = labour cost + material cost + plant and small tools cost + management fee + profit + risk cost within the agreed range (excluding VAT, GB/T 50500-2024 Clauses 2.0.9, 3.1.6) and identifies unbalanced rates / rate loading; the fee dimension verifies the completeness of preliminaries, non-competitive costs, provisional sums and specified-material/nominated-works provisional sums, and arithmetic checks. Based on the nine items of tender review and normalization in GB/T 51095-2015 Clause 6.3.2.
Applicable Codes
- GB/T 51095-2015 建设工程造价咨询规范
- GB/T 50500-2024 建设工程工程量清单计价标准
- TB 10801-2024
Topic Positioning
The 'quantity, price, fee' three-dimensional cost analysis method for billed (BOQ) items: split the cost of a single billed (BOQ) item into three independent dimensions — quantity (quantities), price (all-in unit rate), fee (costs outside the unit rate) — for review, used in tender review and normalization, final account review, and cost risk identification; after the three dimensions are linked, judge the item's risk level and give countermeasures.
Core Conclusions
Quantity dimension: re-calculate the quantities of major items from the construction drawings and compare with the BOQ quantities (differences >5% flagged for attention), checking missing items and duplicate listings; quantity difference risks are allocated by contract type — under re-measurable (unit-rate) contracts BOQ errors / omissions are the employer's responsibility with settlement adjusted to actuals, under lump-sum contracts they fall to the contractor. Price dimension: the all-in unit rate = labour cost + material cost + plant and small tools cost + management fee + profit + risk cost within the agreed range (a fully inclusive price excluding VAT, GB/T 50500-2024 Clauses 2.0.9, 3.1.6), reviewed at three layers — the consumption layer against budget quota line items, the price layer against market prices/published price information of the preparation period, the percentage rate layer checking the reasonableness of management fee and profit percentage rates; also identify abnormal unit rate structures (front-loading, quantity gaming, and other unbalanced rates / rate loading). Fee dimension: verify the completeness of preliminaries and the correctness of non-competitive costs, namely the mandatory health, safety and environmental (HSE) provisions, recheck provisional sums and specified-material/nominated-works provisional sums; under the 2024 edition taxes and duties are listed separately as VAT; check totals and extended prices arithmetically (the nine items of tender review and normalization of GB/T 51095-2015 Clause 6.3.2). Output: a three-dimensional analysis table per billed (BOQ) item — BOQ quantity / drawing quantity / quantity difference %, all-in unit rate / market-price estimate / price difference %, fee items, risk level, countermeasures.
Applicable Boundaries
Applies to tender review and normalization and final account review of building, municipal, and similar works priced on a bill of quantities basis (GB/T 50500 series); railway and other sector works must convert terminology per the sector BOQ system (e.g., the mandatory health, safety and environmental (HSE) provisions correspond to the statutory work safety levy (earmarked funds)). Not applicable to estimates without BOQ/drawing bases or single-point price inquiries; the three-dimensional analysis gives risk signals — final conclusions must be combined with the contract terms.
Further Reading
GB/T 51095-2015, Code for Construction Cost Consulting, Clause 6.3.2 (tender review and normalization work content) and Clause 5.3.9 (all-in unit rate build-up principles); GB/T 50500-2024, China national pricing standard for BOQ, Clause 2.0.9 (all-in unit rate terminology), Clause 3.1.6 (fully inclusive price excluding VAT, VAT listed separately), Section 8.2 (adjustment for quantity differences); for the railway statutory work safety levy (earmarked funds) basis see TB 10801-2024 Clause 3.11.11.