Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Layered build-up of the fully loaded all-in rate: the base chain from labour, materials and plant through overheads, profit, statutory levies and taxes; the three charging-base regimes; why percentage rates cannot be added directly; and the cost boundary and conversion against the BOQ all-in unit rate (which excludes statutory levies as a separate line and VAT)

The fully loaded all-in rate must be built up layer by layer: overheads and profit are usually charged on labour cost plus plant and small tools cost, or on labour cost alone; statutory levies mostly on labour cost; VAT on the fully inclusive price excluding VAT. Each layer has a different, progressively larger base, so multiplying one base by (1 + the sum of the rates) overstates the result (a worked example overstates by about 33%). The correct chain is D = A + B + C -> overheads E and profit F charged on their own bases -> fully inclusive price excluding VAT P = D + E + F -> VAT T = P x t -> Q = P + T. The BOQ all-in unit rate under GB/T 50500-2024 cl. 2.0.9 and 3.1.6 is a pre-tax price excluding VAT (cl. 3.1.2's four BOQ categories no longer list statutory levies separately); the conversion is fully loaded all-in rate Q = (BOQ all-in unit rate Qc + statutory levies R) x (1 + VAT rate t).

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.9、3.1.2、3.1.6、3.2.11条
  • GB/T 51095-2015 · Code for construction cost consultation 第5.3.9、6.2.3条及App. C
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.8、3.1.9、3.1.10条
  • 陕西省《建设工程费用规则》(2025)第5章(表5-1、5-2、5-3)、第7章(表7-1、7-2)、5.3节
  • 湖北省《建筑安装工程费用定额》(2024)费用组成与计算程序

What This Card Covers

This card resolves two practical pricing questions: first, the order of calculation and the charging base of each layer when the fully loaded all-in rate is stacked from labour, materials and plant, overheads, profit, statutory levies and taxes (three regimes: direct-cost base / labour-plus-plant base / labour-only base); second, the cost boundary and conversion between the fully loaded basis and the BOQ all-in unit rate basis of GB/T 50500-2024. It applies to tender pricing and rate build-up, estimate and budget preparation, tender review and normalization, and settlement reconciliation.

Core Conclusions

1. Cost boundary of the two bases (original clause text)

GB/T 50500-2024 Standard for Valuation of Construction Works by Bills of Quantities cl. 2.0.9: 'The all-in unit rate of a BOQ item comprises labour cost, material cost, plant and small tools cost, overheads, profit and the risk allowance within a defined range, and excludes VAT.' It also makes clear that 'VAT is a price-exclusive tax and the all-in unit rate excludes VAT'.

Cl. 3.1.6: 'The all-in unit rates and sums of BOQ items shall be fully inclusive prices excluding VAT, composed of labour cost, material cost, plant and small tools cost, overheads, profit and the like, including the risk allowance agreed or reasonable for the corresponding BOQ item and the cost of indispensable auxiliary work; the taxes of BOQ items shall be entered under VAT, but as the provisional price for specialist (nominated) works in the bill of provisional sums and other charges already contains VAT, its corresponding tax shall not be charged again in the VAT of the BOQ.'

Cl. 3.1.2: 'The BOQ shall be prepared and priced by the divisional and sub-divisional works list, the bill of preliminaries, the bill of provisional sums and other charges, and VAT. Where other list forms are used for pricing, the rules of this standard still apply, and specific provisions may be further clarified by the employer and the contractor by reference to the relevant provisions of this standard.' -- the four categories no longer carry a stand-alone 'statutory levies' line.

Cl. 3.2.11: 'VAT shall take the total of the divisional and sub-divisional works list, the bill of preliminaries and the bill of provisional sums and other charges (excluding the provisional price for specialist (nominated) works) as the calculation base, multiplied by the VAT rate prescribed by the government authority to compute the tax.'

The fully loaded basis originates in GB/T 51095-2015 Code for Construction Cost Consultancy cl. 6.2.3: 'Quantities for the tender price ceiling and the tender shall be taken from the BOQ issued with the tender documents; the unit rates for the tender price ceiling and the tender shall be all-in unit rates, and such all-in unit rates shall include labour cost, material cost, plant cost, overheads, profit, statutory levies and taxes.' Its commentary notes this implements the 'fully loaded unit rate' of construction pricing so that feasibility-stage cost estimates, design estimates, budgets, tender price ceilings and tenders share one unit-rate composition.

Boundary comparison:

Cost layer Fully loaded all-in rate BOQ all-in unit rate (GB/T 50500-2024 basis)
Labour cost, material cost (including works equipment), plant and small tools cost Included Included
Overheads, profit Included Included
Risk allowance within the agreed range and band; indispensable auxiliary work Included Included
Statutory levies (social insurance, housing provident fund, etc.) Included (under local rules possibly already merged into labour cost / overheads and charged up with them) Not listed separately (gone from the 2024 four-category BOQ)
VAT Included, as the last layer on the fully inclusive price excluding VAT Excluded; listed separately as 'VAT', on the total of divisional + preliminaries + other items (less the provisional price for specialist (nominated) works)

2. The layered build-up chain and each layer's base (bases expand layer by layer)

A labour cost + B material cost + C plant and small tools cost -> D subtotal of labour, materials and plant (plus any dynamic adjustment differential of the three)
Construction workers' social insurance (where local cost rules list it separately) = A1 x social insurance rate -> merged into the direct-cost subtotal D
Overheads E = (A1 + C1) x e  or  A1 x e            (per the charging-base regime)
Profit    F = (A1 + C1) x p  or  A1 x p            (same base as overheads)
Fully inclusive price excluding VAT P = D + E + F
VAT       T = P x t                                 (t = the VAT rate prescribed by the government authority)
Fully loaded all-in rate Q = P + T
BOQ all-in unit rate Qc = D + E + F (the part of P with no separate statutory levies and no VAT)

Conversion (mutual calculation of the two bases for the same BOQ item, general form): Q = (Qc + R) x (1 + t), where R is the statutory levies (if local rules have already merged the levies into labour cost / overheads, R is already inside Qc; take R = 0).

3. The three charging-base regimes (evidenced by local and sector quota manuals)

Base regime Charging base Source and key points
Direct-cost regime Norm-based direct cost, or direct cost including preliminaries JTG 3830-2018 notes for completing the estimate and budget schedules: 'preliminaries and overheads are calculated as the sum of the norm-based labour cost and the norm-based plant cost of the relevant item, or as the norm-based direct cost multiplied by the prescribed percentage rate'; 'statutory levies are calculated as the labour cost of the relevant item multiplied by the prescribed rate'; 'profit is calculated as (norm-based direct cost + preliminaries + overheads) of the relevant item multiplied by the profit rate'; 'taxes are calculated as (direct cost + preliminaries + overheads + statutory levies + profit) of the relevant item multiplied by the tax rate'; the same rules, 3.1.9: 'profit ... is calculated at 7.42% of the sum of the norm-based direct cost, the preliminaries and the overheads'; 3.1.10: taxes = (direct cost + permanent equipment procurement cost + preliminaries + overheads + statutory levies + profit) x the construction VAT rate
Labour cost + plant and small tools cost A + C Shaanxi 2025 cost rules Table 5-2: 'overheads = (A1 + C1) x the overhead rate'; 'profit = (A1 + C1) x the profit rate'; 'all-in unit rate = D + E + F'; Hubei 2024 cost norms, computation of the all-in unit rate: 1 labour cost; 2 material cost; 3 plant and small tools cost; 4 overheads = (1 + 3) x rate; 5 profit = (1 + 3) x rate; 6 risk factors per the tender documents or agreement; 7 all-in unit rate = 1 + 2 + 3 + 4 + 5 + 6
Labour cost only A Shaanxi Table 5-3: 'overheads = A1 x the overhead rate'; 'profit = A1 x the profit rate'; 'all-in unit rate = D + E + F'; statutory levies are almost always on labour cost -- JTG 3830-2018 cl. 3.1.8: 'each statutory levy takes the sum of the labour cost of the works category as its base, calculated at the standards set by the state or the laws, regulations, rules and codes at the project location'; Hubei 2024: 'social insurance and the housing provident fund take the norm-based labour cost as the base ... the sum of (norm-based labour cost of the works x the social insurance and housing fund rate)'

Sector split (Shaanxi 2025 cost rules 5.1): the labour-plus-plant base applies to building and decoration works, standalone decoration works, municipal works and urban utility tunnel works (building and decoration); the labour-only base applies to general installation works, landscape and greening works, urban utility tunnel works (installation) and green building works.

4. Why the percentage rates cannot simply be added

The rates sit on different bases: material cost enters only the labour-materials-plant subtotal and never the charging bases of overheads and profit; statutory levies tie only to labour cost; the base of VAT contains all preceding costs plus the levies. Computing in one step as D x (1 + levy rate + overhead rate + profit rate) x (1 + tax rate) inflates the charging bases of overheads, profit and levies to the whole labour-materials-plant total -- a repeated magnification of the base. The gap can be checked with a worked example: Q from the correct chain (social insurance merged into D, overheads / profit charged on A + C, VAT on the fully inclusive price excluding VAT) must equal Q = (Qc + R) x (1 + t); at the same rate levels, the 'add the rates' shortcut overstates the correct result by roughly thirty percent (33.4% in the example).

5. Sources of the rates and linkage with local rules

  • Sources: rates for overheads, profit, statutory levies and general preliminaries come from the provincial cost norms (or sector quota manuals) at the project location and their charging standards; at tender stage the bidder may set them from its own in-house norms.
  • Shaanxi 2025 charging base: when preparing the tender price ceiling, labour cost in the base is the base-period daily labour rate multiplied by the workday consumption in the consumption quota manuals of each discipline, excluding construction workers' social insurance and the dynamic adjustment part; plant and small tools cost is the machine-shift rate in the Shaanxi Plant Rate Norms per Machine-Shift for Construction Machinery (2025) and the Plant Rate Norms per Machine-Shift for Site Instruments and Meters (2025) multiplied by the norm machine-shift consumption, excluding the dynamic adjustment part; at tender stage the bidder sets these itself. Dynamic adjustment differentials within labour cost (A2) attract no overheads or profit.
  • Shaanxi 2025 rates (Tables 7-1, 7-2): overheads -- building and decoration 21.69%, standalone decoration 16.54%, general installation 22.34%, municipal 21.85%, landscape and greening 20.54%, urban utility tunnel (building and decoration) 15.73%, utility tunnel (installation) 17.01%, green building 18.55%; profit -- building and decoration 13.20%, standalone decoration 10.59%, general installation 14.71%, municipal 14.65%, landscape and greening 12.54%, utility tunnel 11.23% (building and decoration) / 13.05% (installation), green building 17.56%. Managers' social insurance paid by the enterprise is already inside overheads at 12.80% of overheads and is non-competitive.
  • Tax linkage (Shaanxi 5.1): under the general VAT scheme, the divisional and sub-divisional item costs, preliminaries and other item costs forming the pre-tax construction cost exclude the input VAT amount; under the simplified VAT scheme each includes the input VAT amount, the rules converting the net-of-input-VAT costs by a composite coefficient for the discipline.
  • Hubei 2024: the cost composition of construction and installation works drops the stand-alone statutory levies item -- the five insurances and one fund for production workers formerly in the levies move into labour cost, and those for management staff plus the works pollution discharge fee (since converted to the environmental protection tax) move into overheads; VAT is non-competitive and must be charged as prescribed; profit is assessed per unit (single-item) works, at a rate no less than 5% and no more than 7% of its share in the pre-tax construction and installation cost, and shall be placed in divisional and sub-divisional works and preliminaries.
  • Rate build-up principle (GB/T 51095-2015 cl. 5.3.9): 'The all-in unit rate of each quota line item may be determined through the budget quota manual and its companion cost norms. Labour cost, material cost and plant cost are determined from the labour, material and plant consumption of the relevant budget quota line item and the market prices current at the reporting date; overheads, profit, statutory levies and taxes are determined from the companion cost norms of the budget quota manual or the charging standards, adjusted for the actual conditions and market level of the proposed project at the reporting date. A budget for building works shall be accompanied by an all-in unit rate build-up sheet.'

Applicability Boundaries

  • Never mix the two bases: a fully loaded all-in rate (with levies and taxes) must not be entered in the BOQ all-in unit rate column under GB/T 50500-2024, nor the reverse; the basis must be stated when deliverables change hands.
  • After the 2024 standard dropped the stand-alone levies line, local cost norms may still list 'construction workers' social insurance' inside the all-in unit rate (Shaanxi 2025 books A3 into D); that part then lives inside the all-in unit rate and must not be charged again before VAT; Hubei 2024 has already merged the five insurances and one fund into labour cost and overheads respectively.
  • In highways and similar sectors the cost of works also contains permanent equipment procurement cost and special charges (site establishment costs, the statutory work safety levy), with rates and bases per JTG 3830-2018 Section 3.1; building-sector cost norms must not be borrowed.
  • Under the simplified VAT scheme the costs already contain input VAT and the general-scheme conversion formula must not be applied directly; the tax rate is always the VAT rate prescribed by the government authority, a non-competitive charge.
  • Dynamic adjustment differentials in the charging base normally attract no overheads or profit and must be separated out when stacking, or charges repeat.
  • Overhead and profit rates may be set freely by the enterprise at tender stage, but non-competitive charges -- social insurance, VAT, mandatory HSE provisions and the like -- must be charged at the prescribed rates.

Further Reading

  • GB/T 50500-2024 Standard for Valuation of Construction Works by Bills of Quantities: cl. 2.0.9 (definition of the all-in unit rate), cl. 3.1.2 (four BOQ categories and their pricing), cl. 3.1.6 (fully inclusive price excluding VAT, VAT listed separately, VAT already inside the provisional price for specialist (nominated) works), cl. 3.2.11 (VAT base and the deduction of that provisional price).
  • GB/T 51095-2015 Code for Construction Cost Consultancy: cl. 5.3.9 (rate build-up principles and the all-in unit rate build-up sheet; format in Annex C), cl. 6.2.3 (tender price ceilings and tenders to use the fully loaded all-in rate including levies and taxes).
  • JTG 3830-2018 Administrative Compilation Rules for Estimates and Budgets of Highway Construction Projects: cl. 3.1.8 to 3.1.11 (statutory levies, the 7.42% profit, taxes, special charges) and the charging bases in the notes for completing the schedules.
  • Shaanxi Cost Rules for Construction Works (2025): Chapter 5 (charging bases and pricing schedules: Table 5-1 pricing schedule for tender stages, Table 5-2 labour-plus-plant base, Table 5-3 labour-only base), Chapter 7 (rates: Table 7-1 overhead rates, Table 7-2 profit rates), 5.3 pricing under the simplified VAT scheme.
  • Hubei Cost Norms for Construction and Installation Works (2024): chapters on cost composition and computation schedules (the all-in unit rate computation schedule, treatment of the dropped levies line, the 5% to 7% profit band).