Whether the all-in unit rate includes statutory levies and taxes: comparison and determination between BOQ-based pricing (non-fully-loaded) and the fully loaded all-in rate
Whether the all-in unit rate includes statutory levies and taxes depends on the pricing basis: under GB/T 50500-2024 BOQ-based pricing it excludes value added tax (VAT) (a price-exclusive tax listed separately) and no longer lists statutory levies and fees as a separate item (social insurance and housing fund contributions are amortized into labour cost and the overheads percentage rate); under the fully loaded all-in rate basis (GB/T 51095-2015 Clause 6.2.3, DB42/T 823-2021, DB14/T 1319-2021 highway) it includes statutory levies and fees and taxes. Confirm the applicable basis before pricing and review; the two sets must never be mixed.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- GB/T 51095-2015 建设工程造价咨询规范
- DB42/T 823-2021
- DB14/T 1319-2021
Topic Positioning
"Whether the all-in unit rate includes statutory levies and taxes" splits into two bases: BOQ-based pricing (GB/T 50500-2024) excludes VAT and does not list statutory levies and fees separately; the fully loaded all-in rate basis includes statutory levies and fees and taxes.
Core Conclusions
BOQ-based pricing basis: all-in unit rate = labour cost + material cost + plant and small tools cost + overheads (company and site) + profit + risk cost within the agreed scope (Clause 2.0.9); VAT is a price-exclusive tax listed separately, and the all-in unit rate is the fully inclusive price excluding VAT (Clause 3.1.6); the taxable base = the total of divisional/sub-divisional + preliminaries + other items (less provisional sum for nominated specialist subcontract works) x the tax rate (Clause 3.2.11); the 2024 edition abolished the independent statutory levies and fees item — social insurance and housing fund contributions are amortized into labour cost and the overheads percentage rate. Fully loaded basis: GB/T 51095-2015 Clause 6.2.3 — the fully loaded all-in rate (incl. taxes and specified on-costs) for price limits and bids includes statutory levies and fees and taxes; DB42/T 823-2021 recommends the fully loaded all-in rate; DB14/T 1319-2021 highway — the all-in unit rate includes permanent equipment procurement cost, preliminaries, statutory levies and fees, taxes, and risk cost. Confirm the basis first; never mix.
Applicable Boundaries
GB 50500-2013 (old edition) lists statutory levies and fees and taxes separately and does not merge them into the all-in unit rate — different from the 2024 edition; the railway sector has an independent expense system (on-costs (indirect costs) including overheads and profit, with taxes listed separately), not a tax-inclusive all-in unit rate model; where the contract provides otherwise, its provisions prevail.
Further Reading
GB/T 50500-2024 Clauses 2.0.9, 3.1.6, 3.2.11, 3.3.5; GB/T 50875-2013 Clause 2.2.58; GB/T 51095-2015 Clause 6.2.3; DB42/T 823-2021 Clause 6.3.8; DB14/T 1319-2021 Clause 3.4; for price adjustment (for fluctuation) carrying VAT only with no overheads or profit, see Clause 3.3.5 item 4.