Checking tender prices for omitted taxes and duties, statutory levies and fees, and preliminaries (edition basis → tax back-calculation → levy rates → preliminaries comparison)

Four-step check for omitted taxes and duties / statutory levies and fees / preliminaries: ① confirm the pricing edition basis first (2013: five costs listed separately vs 2024: statutory levies and fees embedded in all-in unit rates, only VAT listed separately); ② taxes and duties — check the rate and the base (work items + preliminaries + bill of provisional sums and other charges, net of provisional sums for nominated specialist subcontract works), and verify by back-calculation: total price ÷ 1.09; ③ statutory levies and fees — check completeness of the listed items and consistency of percentage rates (non-competitive; must exactly match the tender documents / provincial rates); ④ preliminaries — compare item by item against the project execution plan (construction methodology and site organization), with a dedicated check on the non-competitive mandatory health, safety and environmental (HSE) provisions; under the 2024 edition a cost-breakdown table must be submitted with the tender.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 50722-2011 城市轨道交通建设项目管理规范
  • DB37/T 5161-2020 建设工程造价数据交换及应用标准
  • TB 10801-2024 铁路工程工程量清单计价规范

Topic Positioning

A method for systematically checking, at tender review and normalization (arithmetic and compliance check), whether taxes and duties, statutory levies and fees, or preliminaries have been omitted or under-counted: establish the pricing edition basis first, then check layer by layer against the cost composition, and close with a back-calculation verification.

Core Conclusions

① Edition basis first: GB 50500-2013 and current local documents list five costs separately (work items + preliminaries + bill of provisional sums and other charges + statutory levies and fees + taxes and duties); GB/T 50500-2024 embeds statutory levies and fees into the pre-tax fully loaded all-in rate (fully inclusive price excluding VAT), listing only value added tax (VAT) separately (multiply the summed BOQ total by the VAT rate, Article 6.2.11). Getting the basis wrong leads to misjudgment. ② Taxes and duties — three points to grip: the rate must be consistent with the tender documents and the tax status (general 9% / simplified 3%); the base = total of work items + preliminaries + bill of provisional sums and other charges (net of provisional sums for nominated specialist subcontract works); back-calculation verification — total price ÷ 1.09 ≈ pre-tax cost; any mismatch means omission or a wrong base. ③ Statutory levies and fees (under the separate-listing basis): completeness of the listed items (five social insurances + housing fund; the construction pollution discharge fee ceased when the environmental tax was introduced in 2018 — its presence is itself an error); the percentage rates are non-competitive and must exactly match the tender documents / provincial rates — any inconsistency is a violation (DB37/T 5161-2020 Table 5.1.4 requires red-flagging); verify that the base to which percentage rates are applied (usually labour cost) has not been reduced. ④ Preliminaries: technical and organizational items complete; compared item by item against the project execution plan (construction methodology and site organization) (in the plan but not in the BOQ = omission); the mandatory health, safety and environmental (HSE) provisions (in railway works, the statutory work safety levy (earmarked funds)) are non-competitive and priced per national and provincial rules (Article 3.2.5); under the 2024 edition a cost-breakdown table must be submitted with the tender (initial establishment / mid-term operation / late demolition, Articles 6.2.12/6.2.13) — missing items mean the submission is incomplete.

Applicable Boundaries

Applies to tender review and normalization checks for tenders priced on a bill of quantities basis; it does not cover industry-specific percentage rate values (consult the respective quota norms (prescribed resource consumption standards)). Under the 2024 edition basis, "statutory levies and fees listed separately" should no longer be checked — follow the pricing basis and tax method stated in the tender documents. Preliminaries are priced autonomously by the tenderer under its own implementation plan (Article 6.2.6); the check only verifies consistency between the plan and the price, not the merits of the plan.

Further Reading

GB/T 50500-2024 Articles 3.2.5, 6.2.6, 6.2.11–6.2.13 and Appendix E Tables E.2.2-1, E.3.2–E.3.4; GB 50722-2011 Article 5.2.9 (mandatory health, safety and environmental (HSE) provisions and migrant-worker injury insurance are non-competitive); DB37/T 5161-2020 Table 5.1.4 (tender review and normalization check items for levies and taxes); for the railway basis see TB 10801-2024 Article 3.11.11 and TB 10811-2024 Article 2.11.9.