GB/T 50500-2024 vs GB 50500-2013 edition change: all-in unit rate composition changes and the repositioning of statutory levies and fees and taxes and duties in the BOQ-based pricing system
The 2024 edition removes "statutory levies and fees" entirely from the BOQ system (no longer listed; the mandatory "shall not be competitive" clause canceled); taxes and duties become value added tax (VAT) listed separately at the summary level (= total of summarized list prices x VAT rate); the all-in unit rate is explicitly a fully inclusive price excluding VAT (labour cost + materials + plant and small tools cost + management fee + profit + agreed-scope risk + indispensable auxiliary work costs); "overheads (company and site)" is renamed "management fee". The 2013 edition excluded statutory levies and fees and taxes and duties indirectly via mandatory provisions of codes; 2024 declares "excluding VAT" directly in the term definition. The standard changed from mandatory GB to recommended GB/T, effective 2025-09-01 with the 2013 edition abolished.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works (住房城乡建设部公告 2024 年第 212 号,2025-09-01 实施)
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止)
Topic Positioning
Comparing GB 50500-2013 and GB/T 50500-2024 on the all-in unit rate composition after the edition change, and the repositioning of statutory levies and fees and taxes and duties in the BOQ-based pricing system — statutory levies and fees exiting wholesale, taxes and duties becoming separately listed value added tax (VAT). Answers edition-comparison questions like "how did the unit rate composition change, where do statutory levies and fees and taxes and duties sit now".
Core Conclusions
1. Edition background: MOHURD Announcement No. 212 of 2024 approved GB/T 50500-2024, effective 2025-09-01; GB 50500-2013 was simultaneously abolished. The designation changed from mandatory GB to recommended GB/T; former mandatory provisions of codes ("must be strictly enforced") are no longer retained.
2. All-in unit rate composition (2013 clause 2.0.8 -> 2024 clause 2.0.9):
- 2013 2.0.8: "labour cost, materials and engineering equipment cost, plant and small tools cost, overheads (company and site), profit, and risk costs within a certain range, required to complete one specified billed (BOQ) item."
- 2024 2.0.9: "the cost of completing one unit quantity of a billed (BOQ) item, comprehensively considering technical standards, construction duration, sequence, conditions, geography and climate, and risks within the agreed scope and risk band. The all-in unit rate includes labour cost, materials, plant and small tools cost, management fee, profit, and risk costs within a certain range, excluding VAT." "VAT is a price-exclusive tax; the all-in unit rate excludes VAT."
- Differences: (1) "overheads (company and site)" renamed "management fee"; (2) 2013 excluded statutory levies and fees and taxes and duties indirectly via mandatory 3.1.4 ("the bill of quantities shall be priced on an all-in unit rate basis... including all amounts except statutory levies and fees and taxes and duties"), while 2024 declares "excluding VAT" directly in the definition; (3) 2024 3.1.6 further clarifies that "billed (BOQ) item all-in unit rates and totals shall be fully inclusive prices excluding VAT, composed of labour cost, materials, plant and small tools cost, management fee, profit, including agreed or reasonable-scope risk costs and indispensable auxiliary work costs", writing auxiliary work costs and reasonable risk into the composition.
3. Statutory levies and fees: from "one of five cost parts + mandatory non-competition" to wholesale exit:
- 2013: 1.0.3 — pricing at contracting and implementation stages consists of work-item costs, preliminaries, other charges, statutory levies and fees, and taxes and duties (five parts); 4.5.1 — statutory levies and fees listed as social insurance (pension, unemployment, medical, work injury, maternity), housing provident fund, pollution discharge fee; 3.1.6 (mandatory) — "statutory levies and fees and taxes and duties must be calculated per state or provincial/departmental regulations and shall not be competitive".
- 2024: statutory levies and fees as a cost item no longer appears anywhere in the standard (terms, general provisions, preparation of the bill of quantities, pricing, appendices); the price structure becomes four blocks: billed (BOQ) items + bill of preliminaries + bill of provisional sums and other charges + VAT (6.1.11: "the tenderer's tender total shall agree with the sum of the totals of the bill of work sections and items, the bill of preliminaries, the bill of provisional sums and other charges, and VAT"); the "shall not be competitive" mandate is canceled along with the fee item. Statutory obligations like social insurance and housing provident funds still exist at the legal level but are no longer listed or mandatorily rated in BOQ-based pricing — absorbed by tenderers in their pricing (management fee and overall offer).
4. Taxes and duties: from the "business-tax era four-tax list" to separately listed value added tax (VAT):
- 2013 4.6.1 taxes and duties list: business tax, urban maintenance and construction tax, education surcharge, local education surcharge (pre-VAT-reform basis, not updated in the text).
- 2024 regulates via VAT directly: 6.2.11 — "after summing the list totals of the bill of work sections and items, the bill of preliminaries, and the bill of provisional sums and other charges (less provisional sums for nominated specialist subcontract works), the tenderer shall determine the VAT offer by multiplying the summed total by the VAT rate per 3.2.11"; 3.1.6 — "taxes and duties for billed (BOQ) items shall be entered under VAT; however, the provisional sum for nominated specialist subcontract works in the bill of provisional sums and other charges already includes VAT, and the corresponding taxes and duties shall not be calculated again in the VAT of the bill of quantities".
Applicable Boundaries
- This card covers only the general BOQ-based pricing basis under GB/T 50500-2024 for building and municipal works; highway, water conservancy and other sector standards may still use full-cost bases including statutory levies and fees and taxes and duties — confirm the sector standard when citing.
- The 2024 edition is recommended (GB/T); agreed terms prevail in pricing; state-funded projects still follow the tender price ceiling and related regulations.
- GB 50500-2013 provisions are abolished and used only for edition comparison, not as a pricing basis.
Further Reading
- Issuance: MOHURD Announcement No. 212 of 2024, public at www.mohurd.gov.cn; published by China Planning Press via the MOHURD Standards and Quotas Institute.
- GB/T 50500-2024 clauses: 2.0.9 (term, all-in unit rate), 3.1.6 (general provisions, fully inclusive price excluding VAT; VAT), 6.1.11 (tender total basis), 6.2.11 (VAT offer calculation), 3.2.11 (VAT rate determination).
- GB 50500-2013 (abolished, comparison only): 1.0.3, 2.0.8, 3.1.4, 3.1.6, 4.5, 4.5.1, 4.6.1.
Keywords
- all-in unit rate
- composition of project costs
- statutory levies and fees
- value added tax (VAT)
- GB/T 50500-2024
- GB 50500-2013
- pricing on a bill of quantities basis
- 换版对比