Composition of the tender bill of quantities: the five parts of GB 50500-2013 (bill of divisional and elemental work items, bill of preliminaries, bill of provisional sums and other charges, bill of statutory levies, bill of taxes and duties) with the itemisation rules of each, and the composition contrast under GB/T 50500-2024

GB 50500-2013 Clause 4.1.4: the tender bill of quantities shall be compiled with the individual work (or project) as the unit and shall consist of the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and the bills of statutory levies and of taxes and duties. Under Clause 4.4.1 the bill of other charges contains provisional sums, provisional prices (provisional unit prices for materials, provisional unit prices for permanent plant, provisional prices for nominated specialist works), dayworks, and the main contractor's attendance and coordination provisions; under Clause 4.5.1 statutory levies cover social insurance contributions (old-age, unemployment, medical, work-injury and maternity), the housing provident fund, and the works pollution discharge fee; under Clause 4.6.1 taxes and duties cover business tax, city maintenance and construction tax, the education surcharge and the local education surcharge. GB/T 50500-2024 Clause 3.1.2 instead compiles and prices the bill of divisional and elemental work items, the bill of preliminaries and the bill of other charges together with value added tax (the statutory levies and tax bills are no longer set up; the tax becomes value added tax, computed per Clause 3.2.11 by multiplying the total of the three bills, after deducting the provisional prices of nominated specialist works, by the VAT rate).

Applicable Codes

  • GB 50500-2013 建设工程工程量清单计价规范 第4.1.1~4.1.4条、第4.2.1~4.2.2条、第4.3.1~4.3.2条、第4.4.1~4.4.6条、第4.5.1~4.5.2条、第4.6.1~4.6.2条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9条、第3.1.2条、第3.1.6条、第3.1.8条、第3.2.1条、第3.2.11条、第4.1.4条、第4.1.7条、第4.2.1~4.2.8条

Scope

This card answers 'what does the tender bill of quantities consist of': taking Chapter 4, Preparation of the Bill of Quantities, of GB 50500-2013 as the thread, it gives the clause number and itemisation rule of each of the five bills and contrasts the composition basis of GB/T 50500-2024, for locating clauses when compiling or reviewing tenders and when citing contract documents.

Core Conclusions

1. GB 50500-2013: the composition clause is Clause 4.1.4

Clause 4.1.4: the tender bill of quantities shall be compiled with the individual work (or project) as the unit and shall consist of the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and the bills of statutory levies and of taxes and duties. (Note the distinction from the first three clauses of the general provisions of 4.1: Clause 4.1.1 fixes the compiler - 'the tender bill of quantities shall be compiled by a tenderer with the capability to do so, or by a cost consultant with the corresponding qualification engaged by the tenderer'; Clause 4.1.2 is a mandatory provision - 'the tender bill of quantities must form part of the tender documents, and its accuracy and completeness shall be the responsibility of the tenderer'; Clause 4.1.3 makes the bill one of the bases for compiling the tender price ceiling and the tender, for calculating or adjusting quantities, and for claims. The composition clause is not 4.1.1.) The original Chinese title of the work-items bill carries the word 'item' in its name; when quoting the contract or the tender documents, follow the original wording of the standard.

2. Itemisation rules of the five bills (2013 edition)

  1. Bill of divisional and elemental work items - Clause 4.2.1 (mandatory): 'must state the item code, item name, item description, unit of measurement and quantity', all five elements being indispensable; Clause 4.2.2 (mandatory): 'must be compiled in accordance with the item codes, item names, item descriptions, units of measurement and quantity take-off rules of the current national measurement standards for the relevant works'.
  2. Bill of preliminaries - Clause 4.3.1 (mandatory): 'must be compiled in accordance with the provisions of the current national measurement standards for the relevant works'; Clause 4.3.2: items shall follow the actual circumstances of the proposed works, and compilation shall consider hydrology, weather, environment, safety and similar factors; preliminaries not listed in the annexes of the measurement standards may be added to suit the project. The measurement standards divide preliminaries into two classes: those not measurable by quantity are priced per 'item' (lump items, such as site safety and amenity provisions and temporary facilities); those measurable are priced by quantity (unit-rate items, such as scaffolding and dewatering).
  3. Bill of provisional sums and other charges - Clause 4.4.1: items shall be listed as follows: 1 provisional sums; 2 provisional prices, covering provisional unit prices for materials, provisional unit prices for permanent plant, and provisional prices for nominated specialist works; 3 dayworks; 4 the main contractor's attendance and coordination provisions. Supporting clauses: Clause 4.4.2, provisional sums are estimated per the character of the works under the relevant pricing provisions; Clause 4.4.3, provisional unit prices for materials and plant are estimated from published cost information or by reference to market prices with a schedule listed, and provisional prices for nominated specialist works are estimated by specialty under the relevant pricing provisions with a schedule listed; Clause 4.4.4, dayworks shall list the item name, the unit of measurement and the provisional quantity; Clause 4.4.5, the attendance and coordination provisions shall list the services and their content; Clause 4.4.6, items not listed in Clause 4.4.1 are added per the actual circumstances of the works.
  4. Bill of statutory levies - Clause 4.5.1: items shall be listed as follows: 1 social insurance contributions (old-age, unemployment, medical, work-injury and maternity insurance); 2 the housing provident fund; 3 the works pollution discharge fee. Clause 4.5.2: items not listed in Clause 4.5.1 follow the provisions of the provincial government or of the provincial authorities concerned.
  5. Bill of taxes and duties - Clause 4.6.1: shall include: 1 business tax; 2 city maintenance and construction tax; 3 the education surcharge; 4 the local education surcharge. Clause 4.6.2: items not listed in Clause 4.6.1 follow the provisions of the tax authorities.

3. Composition contrast under GB/T 50500-2024

  • Clause 3.1.2: the bill of quantities shall be compiled and priced separately as the bill of divisional and elemental work items, the bill of preliminaries, the bill of provisional sums and other charges, and value added tax; where pricing adopts another list form, the rules of this standard still apply, and specific provisions may be agreed between the employer and the contractor by reference to this standard. Under this division, the bill of divisional and elemental work items reflects the physical works of the project.
  • Clause 4.2.1 lists seven bases of compilation: this standard together with the national and sectoral quantity take-off standards for the relevant works; the measurement and pricing rules and supplementary quantity take-off rules issued by the national, provincial and sectoral construction authorities; the tender documents, the draft contract terms and related information; the tender drawings and related information; the relevant technical codes; the site conditions, the ground investigation and hydrological data, the character of the works and the delivery standard; and other relevant information.
  • Clause 4.1.7: under a unit-rate or a lump-sum contract alike, the item code, item name, item description, unit of measurement and work content of the bill of divisional and elemental work items shall follow the national and sectoral quantity take-off standards and the supplementary quantity take-off rules; the item code, item name and work content of the bill of preliminaries shall follow those standards likewise.
  • Clause 4.2.6 refines the bill of other charges: provisional sums may be listed in two classes, 'for works or services not yet defined or not specifiable in detail' and 'for adjustment of the contract price'; provisional prices for nominated specialist works are listed by class and (or) specialty with a schedule attached; directly let specialist works are listed separately; employer-supplied materials are listed according to whether the contractor is responsible for their installation, with the material schedule and provisional unit prices given under Annex G.1 Table G.1.1; dayworks state in the item description the categories of labour, the names of materials and construction plant, the sundry work items, and the demolition and make-good items, listing names, units of measurement and reasonable provisional quantities; the main contractor's attendance and coordination provisions for employer-supplied materials and for specialist subcontract works are listed separately and may be measured per item or by rate (rate-measured ones preferably with the provisional price as the pricing base), and for directly let specialist works preferably per item. Clause 4.2.7: items not covered by Clause 4.2.6 may be added per the requirements of the tender documents and the actual circumstances of the works.
  • VAT listing and computation: under Clause 4.2.8, value added tax is listed per the rules of the competent government authorities and Clauses 3.1.6 and 3.2.11, and computed at the VAT rate; under Clause 3.2.11, value added tax is computed by multiplying the total of the bill of divisional and elemental work items, the bill of preliminaries and the bill of other charges (provisional prices for nominated specialist works excluded) by the VAT rate fixed by the competent authority - that is, the provisional prices of nominated specialist works are deducted from the computation base (they are prices already including VAT, see Clause 3.1.6).
  • All-in unit rate basis (Clauses 2.0.9 and 3.1.6): the all-in unit rate covers labour, materials, plant and small tools, overheads, profit and the risk costs within a defined range, and excludes value added tax; the all-in unit rate and the combined price of items, and the prices of items billed per item, must all be fully inclusive prices excluding VAT, the corresponding tax being reflected in value added tax.
  • Division of responsibility (Clause 3.1.8): under unit-rate contracts the accuracy and completeness of the bill of divisional and elemental work items rest with the employer; under lump-sum contracts the accuracy and completeness of the priced bill of divisional and elemental work items rest with the contractor; under either contract type, the completeness and accuracy of preliminaries billed per item rest with the contractor.

Applicability Boundaries

  • The 'business tax' item of Clause 4.6.1 (2013 edition) has not been listed on a business-tax basis since the VAT reform was fully rolled out across construction (1 May 2016); practice now itemises value added tax. Current compilation of the bill of quantities should follow GB/T 50500-2024; the 2013 edition mainly serves clause comparison for existing contracts, legacy settlements and historical documents.
  • The two editions differ in composition: 2013 is 'five parts' (the last two being statutory levies and taxes and duties); 2024 is 'four parts' (the last merged into value added tax, with no separate statutory levies bill; statutory levy costs are handled under the 2024 edition and its supporting rules). Confirm which edition is the basis before citing clause numbers.
  • The sectoral quantity take-off standards carry their own divisional splits and classifications of preliminaries; this card gives only the composition and itemisation frame, and specific item codes, units of measurement and measurement rules must be taken from the national or sectoral quantity take-off standard of the specialty concerned.

Further Reading

  • GB 50500-2013, Chapter 4, compilation of the bill of quantities: 4.1.1 to 4.1.4 (compiler, contractual status and responsibility, composition); 4.2.1 to 4.2.2 (the five elements of the work-items bill); 4.3.1 to 4.3.2 (the bill of preliminaries, lump items and unit-rate items); 4.4.1 to 4.4.6 (the bill of other charges); 4.5.1 to 4.5.2 (the bill of statutory levies); 4.6.1 to 4.6.2 (the bill of taxes and duties).
  • GB/T 50500-2024: Clause 2.0.9 (term, all-in unit rate); Clause 3.1.2 (composition of the bill of quantities); Clause 3.1.6 (fully inclusive price excluding VAT, and VAT-inclusive provisional prices for nominated specialist works); Clause 3.1.8 (responsibility for accuracy and completeness); Clause 3.2.1 (unit-rate and lump-sum pricing); Clause 3.2.11 (computation base of value added tax); Clause 4.1.4 (responsibility for errors and omissions in the BOQ); Clause 4.1.7 (content of compilation); Clause 4.2.1 (bases of compilation); Clauses 4.2.2 to 4.2.3 (compilation under unit-rate and lump-sum contracts); Clause 4.2.4 (employer-supplied materials and provisional material prices); Clause 4.2.5 (the bill of preliminaries); Clauses 4.2.6 to 4.2.7 (the bill of other charges and additions); Clause 4.2.8 (listing of value added tax); Annex E.2 and Annex G.1 (table of provisional material unit prices and adjustment; schedule of employer-supplied materials).
  • Read together on responsibility: 2013 Clause 4.1.2 (the tenderer responsible for accuracy and completeness; mandatory provision) and 2024 Clauses 3.1.8 and 4.1.4 (responsibility split by contract type), Clause 6.1.7 and Section 8.2 (treatment of errors and omissions in the BOQ and price adjustment).