Overview of bills of quantities: composition, compilation, item descriptions and handling of errors/omissions (GB/T 50500-2024)

A bill of quantities comprises four sections — trade items, preliminaries, other items and VAT; the five BOQ elements (code/name/item description/unit of measurement/quantity) are compiled per the national and industry measurement standards. Division of responsibility: under unit-rate contracts the trade-items BOQ is the employer's responsibility, under lump-sum contracts the contractor's, and the bill of preliminaries is always the contractor's. BOQ defects are per definition 2.0.27; unit-rate contracts re-measure under section 8.2 with price adjustment at the 15% boundary; lump-sum contracts are generally not adjusted except provisional-quantity items.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB 50860-2013 构筑物工程工程量计算规范
  • DBJ51/T 040-2015 四川省工程建设项目招标代理操作规程
  • DB37/T 5096-2017 建设工程项目管理咨询规范

Topic Positioning

This card provides an overview of the composition, compilation rules, allocation of responsibility and handling of errors/omissions in bills of quantities under GB/T 50500-2024 'Standard for bill-of-quantities pricing of construction works' — the programmatic overview for understanding the whole BOQ pricing process, applicable to tender pricing, compilation of the tender price ceiling and final account review.

Core Conclusions

(1) Composition (3.1.2): the BOQ is compiled and priced in four sections — the trade-items BOQ, the bill of preliminaries, the bill of provisional sums and other charges, and VAT — with the trade-items BOQ reflecting the physical works; the bill of provisional sums and other charges contains provisional sums, provisional sum for nominated specialist subcontract works, directly awarded specialist works, employer-supplied (free-issue) materials, dayworks and the main contractor's attendance and coordination provisions (4.2.6). (2) Five elements (GB 50860-2013 clause 4.2.1, mandatory): code, name, item description, unit of measurement and quantity — none may be missing; code, name, item description, unit and work content are all compiled per the national and industry measurement standards and supplementary rules (4.1.7). (3) Allocation of responsibility (3.1.8): under unit-rate contracts the itemization, item descriptions and quantities of the trade-items BOQ are the employer's responsibility and tenderers may not alter them; under lump-sum contracts they are the contractor's responsibility, and the contractor may supplement them; the bill of preliminaries is the contractor's responsibility under any contract type. (4) Quantity basis: under unit-rate contracts BOQ quantities are provisional quantities and are re-measured during performance against the actual drawings (4.1.5); under lump-sum contracts they are deemed to match the drawings on a lump-sum basis; where drawing depth is insufficient, 'provisional quantity' may be noted and adjusted under the unit-rate contract rules (4.1.4). (5) Handling of defects: a defect is a difference in itemization, item description or quantity from the contract drawings/specifications (2.0.27). Unit-rate contracts re-measure under 8.2.1; quantity differences of <=15% (inclusive) use the contract unit rate or converted adjustments under 8.9.1, and differences >15% are negotiated under 8.9.2; lump-sum contracts do not adjust the contract price for defects except for provisional-quantity items (6.1.7).

Applicable Boundaries

Applies to unit-rate/lump-sum works priced on a BOQ basis; not to quota-based pricing or small projects without a BOQ. Local procedures (e.g. Sichuan tender agency operating rules, Shandong project management consulting standards) serve as procedural references only — responsibility and adjustment rules follow national and industry standards. The 2024 edition removes the separate line for statutory levies and fees, and the all-in unit rate is on a fully inclusive basis excluding VAT, differing from 2013 — confirm the governing edition before citing.

Further Reading

See GB/T 50500-2024 clauses 2.0.27, 3.1.2, 3.1.8, 4.1.4, 4.1.5, 4.1.7, 4.2.6, 6.1.7, 8.2.1, 8.9.1, 8.9.2; the mandatory five-element rule: GB 50860-2013 clause 4.2.1; BOQ completeness checks may reference DBJ51/T 040-2015 clause 5.2.11 and DB37/T 5096-2017 clause 6.3.2.